Boatlanding Bridge, Sixth Avenue, spanning Chadakoin River at Lake Chautauqua, Jamestown

Boatlanding Bridge, Sixth Avenue, spanning Chadakoin River at Lake Chautauqua, Jamestown, Chautauqua County, NY. Surveyed as HAER NY,7-JAMTO,2-, with a 1,932-word written history.

From the record

“According to a New York State Department of Transportation bridge inventory, this bridge is one of the earlier reinforced concrete arch bridges in New York, as well as an example of a bridge using the "Kahn" system of reinforcement.”

Written record, HAER NY,7-JAMTO,2- survey. Machine-read text.

Surveyed by the federal HAER program as HAER NY,7-JAMTO,2- · the record runs 1932 words · one of 19 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Location

138 words

Source document Quoted word for word from HAER NY,7-JAMTO,2-. Not written, edited or summarised by this site.

Sixth Avenue spanning the Chadakoin River at the outlet of Lake Chautauqua, City of Jamestown, Chautauqua County, New York. Bridge is 500 feet northeast of Route 394 and the railroad, bridge. UTM: N E New York State Quad: Lakewood Date of Construction: Contract signed May construction begun July bridge completed September 21, Style: Two span, earth filled spandrel, reinforced concrete arch bridge with minimal ornamentation and concrete parapets. Engineer/ Builder; Initial design proposal prepared by the city engineer in The design proposal was prepared by Richard Irvin, civil engineer and representative of the Pittsburgh, Pennsylvania office of the Detroit, Michigan-based Trussed Concrete Steel Company. Actual construction plans and specifications prepared by Edward C.

Burns, a consulting civil engineer of Jamestown, and Clyde G. Jones, the City of Jamestown engineer. Constructed by Mahoney and Swanson Contractors, Jamestown, New York.

Significance

428 words

Source document Quoted word for word from HAER NY,7-JAMTO,2-. Not written, edited or summarised by this site.

According to a New York State Department of Transportation bridge inventory, this bridge is one of the earlier reinforced concrete arch bridges in New York, as well as an example of a bridge using the "Kahn" system of reinforcement. The bridge was designed with some assistance from a civil engineer specializing in reinforced concrete construction, but was constructed according to plans prepared by local engineers not associated with a major consulting engineering firm specializing in the field of reinforced concrete arch design. The two span bridge built in is similar in configuration to the bridge first Boatlanding Bridge HAER No.

Page 2 proposed in The primary reason for building the bridge of concrete was the lower cost of reinforced concrete in comparison to an alternative steel truss design. Materials of Construction; Bridge uses forty-nine tons of the "Kahn" system of reinforcement. The Kahn system used longitudinal steel reinforcing rods with diagonal prongs to improve shear strength. Both round and square section steel reinforcement bars are used, but all bars are the "deformed" type. In plan, a horizontal row of steel reinforcing rods spaced one foot apart laterally for the full width of the bridge is placed at the intrados and the extrados of the arch.

At both the intrados and extrados the longitudinal rods are connected by one-half inch diameter rods running transverse and spaced two feet apart laterally for the full length of the bridge. Vertical [shear] rods spaced at intervals of two feet connect the longitudinal rods of the intrados and extrados. The spandrel walls are 12 Inches thick, and the concrete is 18 inches thick at the crown of the arch. A total of linear feet of timber piling supports the reinforced concrete footings of the pier and abutments. Dimensions: A two span bridge with a total length of 158 feet. Each arch is 60 feet between spring lines. Bridge has an out-to-out width of 60 feet and a curb-to-curb width of 40 feet. The distance between the curb line and the exterior face of the solid parapet wall is 10 feet.

Total deck area is square feet. On each side of the bridge is a 7 foot wide pedestrian sidewalk. Each span has a rise of 10 feet 8 inches between the spring line and intrados of the arch. The single center pier is 20 feet 6 inches wide. Major Alterations and Additions: Since construction was completed in the bridge has required minimal maintenance and repair. The only notable repair has been the application of gunnite to the intrados of the arch prior to

Written history

1272 words

The headings the report itself prints. Each one jumps to where it begins.

Source document Quoted word for word from HAER NY,7-JAMTO,2-. Not written, edited or summarised by this site.

The documentation of Boatlanding Bridge was prepared by the Historic American Engineering Record (HAER), National Park Service, during the summer of for the New York State Historic Bridges Recording Project. This project was sponsored by the New York State Department of Transportation under the supervision of Eric DeLony, Chief & Principal Architect, HAER. This report was written by Andrew Cole and Charles Scott. When citing this report, please credit the Historic American Engineering Record and the authors. Boatlanding Bridge HAER No. Page 3 The Chadakoin River is a slow moving outlet for Lake Chautauqua and flows southeast through the City of Jamestown.

A bridge has been at this site since around In the the city had a single span, ten panel, pin connected, through Pratt truss bridge erected at the site, known locally as the "Boatlanding" because of the adjacent Lake Chautauqua steam boat dock. In the truss was reinforced, and thereafter the bridge was frequently examined because of increasing deterioration. In the bridge was temporarily deemed structurally insufficient for the type of traffic crossing it. This traffic included heavy street railway cars and wagons laden with the raw materials and finished products of numerous adjacent table and furniture factories.

The Board of Public Works, after investigating alternative bridge types, recommended the construction of a concrete arch bridge reinforced with "expanded metal," at a cost of The bridge was to be financed by issuing ten year maturity municipal bonds. The plans prepared at this time specified a two span, earth filled, reinforced concrete arch bridge with an ornamental stone or brick facade and a six inch concrete deck with brick pavement. The opposition of seven of the eleven council members, including the chairman of the Bridge Committee, to the proposal to pay for the bridge with ten year bonds doomed the proposal to defeat.

In his annual report for the year the Mayor of Jamestown stated the issues of the case: "It cannot be doubted that a new bridge at the Boatlanding is demanded to accommodate and promote the safety of the traveling public. A recommendation of the Board of Public Works, dated October 20, is already before you, upon this subject, but providing for the payment of the cost by the issue of bonds for [is] a method now impossible, even if voted by the taxpayers." The Mayor then recommended paying for the bridge from general tax revenues if authorized to do so by a special taxpayers election. The issue of the bridge surfaced again the following year, but a bridge construction proposal was referred to a committee and once again no action was taken.

The city engineer continued to urge that the condition of the bridge be "closely watched" and acknowledged that the bridge would soon need rebuilding. No action was taken until after the bridge was deemed unsafe and temporarily closed in October The City Engineer concluded that the Fairmount Avenue Bridge could not carry the weight of Jamestown's new 30 ton trolleys and loaded wagons carrying freight to and from adjacent factories. The trusses were deemed sufficient for one 25 ton trolley only when no other traffic was on the bridge. As doubts to the structural integrity of the truss bridge grew, Clyde G. Jones, the city engineer, made a recommendation to repair the structure while planning for its replacement.

His evaluation of the two options for a new bridge, a steel truss or a reinforced concrete arch bridge, produced estimates favoring the construction of a reinforced concrete arch Boatlanding Bridge HAER No. Page 4 bridge. Jones calculated the cost of a single span steel truss bridge at between and as compared to for a two span reinforced, concrete arch bridge. After repairing the span the engineer reported that the bridge was "reasonably safe under the most favorable and judicious use," but advised that only one streetcar or heavy wagon be permitted across the bridge at one time. The City Council, recognizing that the repairs were "only temporary at best," authorized spending for a new bridge if approved by the voters at a special election.

The election, held in April of resulted in the defeat of the bridge construction proposal. Eighteen months later the issue of a new bridge at the Boatlanding surfaced once again when the aldermen adopted a resolution to investigate relocating the existing steel truss bridge to Winsor Street, the site of an even more deteriorated bridge, but where the traffic was lighter. Six months later this plan was abandoned and the Alderman instructed the city engineer to prepare plans and specifications for new bridges at both Boatlanding and Winsor Street. The design for the Boatlanding bridge was once again for a double arch reinforced concrete bridge of two 60 foot spans with a 60 foot width to accommodate a 40 foot roadway and two 10 foot sidewalks.

The cost of the two- bridge project, however, had grown to an estimated At a special election held on April 15, the public approved the bridge construction referendum. In May, bids were solicited and received from four contractors: Reinforced Concrete Construction Co., Pittsburgh, Pa. Nicola Building Co., Pittsburgh, Pa. F. M. Roessing Co., Pittsburgh, Pa. Mahoney and Swanson, Jamestown, New York Mahoney and Swanson, the low bidder, was awarded the contract on May 31, The contract specified that the bridge would be completed within 110 days. The initial plans for the concrete arch bridge had been prepared in consultation with civil engineer Richard Irvin of Pittsburgh, Pennsylvania.

Irvin was the Pittsburgh representative of the Trussed Steel Concrete Company of Detroit, Michigan, the licensee for the "Kahn" system of longitudinal arch reinforcement. The Kahn "K trussed" steel reinforcing bar, as described by its advertising, was a "main horizontal bar with rigidly connected diagonal shear members.* The cross section had "two horizontal flanges projecting at opposite sides" to provide rigid diagonal reinforcement against shear. During June of however, the City Council directed the Board of Review and Estimate to "dispense" with Irvin's services and "employ a competent engineer to furnish a detailed set of drawings for and supervise the construction of the Fairmount Avenue bridge." Engineer Irvin was replaced by local consulting engineer Edward C. Burns.

Although Irvin's services were terminated, the bridge specifications drawn by Burns called for the use of the Kahn reinforcement system. Boatlanding Bridge HAER No. Page 5 Burns was a civil engineer who had graduated from the University of Michigan and obtained extensive railway and river and harbor engineering experience, including employment in the design and construction of the Sault Ste. Marie Canal, before returning to Jamestown to open a consulting engineering practice. He served as a consultant to the Jamestown Board of Public Works and designed the steel truss Boatlanding bridge. The Fairmount Ave. concrete arch bridge was his last major project before retiring. With the sale of the bridge construction bonds in September construction was clear to proceed.

By September construction of the bridge was reported to the City Council to be "practically finished" and the contract was declared complete on September 21, Boatlanding Bridge HAER No. Page 6

Bibliography

Downs, John P., and Hedley, Fenwick Y., eds. History of Chautauqua County. New York and Its People. Boston: American Historical Society, Inc., "Fairmount Avenue Bridge," Files of the City Engineer, City of Jamestown, New York. Jamestown Evening Journal. October 21, Mayor's Annual Message and Annual Reports of City Officers. Jamestown, Fenton Historical Society, Proceedings of the Common Council, City of Jamestown, New York. National Association of Cement Users. Proceedings of the Seventh Annual Convention. New York. (December New York State Department of Transportation, Bridge Identification Number File, Region 5, Buffalo, New York.

In context

Jamestown, New York The place record: every map, photograph and survey of this town.
Chautauqua County, New York 149 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Jamestown

1 record

The federal surveyors worked through Jamestown building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
Erie RailwayHAER NY,7-JAMTO,1A-33 words

Provenance

  • Written history. Quoted verbatim from HAER NY,7-JAMTO,2-. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.