New York State Barge Canal, Lock E33, 1205 Edgewood Avenue, Henrietta

New York State Barge Canal, Lock E33, 1205 Edgewood Avenue, Henrietta, Monroe County, NY. Surveyed as HAER NY-463, with a 1,819-word written history.

From the record

“Lock E33, located on the Erie Canal, is a component of the nationally significant New York State Barge Canal.”

Written record, HAER NY-463 survey. Machine-read text.

Surveyed by the federal HAER program as HAER NY-463 · the record runs 1819 words · one of 73 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Significance

1102 words

Source document Quoted word for word from HAER NY-463. Not written, edited or summarised by this site.

Lock E33, located on the Erie Canal, is a component of the nationally significant New York State Barge Canal. The lock is also significant because it retains the original DC gate and valve operating machinery. Description: Lock E33 is located 1.3 miles west of Lock E32.1 The lock site consists of the lock and associated structures, powerhouse, lockhouse, garage, and spillway on a bypass channel to the south of the lock. The lock has a lift to the west with normal pool elevations of below and above. The lock chamber walls are scored concrete with cast-iron quarter-round coping. There are double-leaf, steel miter lock gates at each end of the chamber operated by spars and gear trains powered by DC electro-mechanical gate machinery.

The flow of water through the culverts in the chamber walls is controlled by valves also operated by DC electro-mechanical machinery. The lock retains the original DC gate and valve operating machinery. Since there is a highway bridge just below the lock chamber, the culverts discharge under the roadways to riser pipes in the lower pool. Control stand shelters are located on the upstream and downstream corners of the north side of the chamber. The shelters are single-story frame buildings with horizontal board siding and pyramidal asphalt roofs. They are each equipped with sliding wood windows and pane-and-panel doors. Concrete-filled cast-iron bollards on concrete pads line either side of the chamber, and there is pipe railing on the public access side of the chamber.

The lock is illuminated by modern reproduction light fixtures. The lock and control stand shelters are in good condition. An I-beam pedestrian and cable bridge spans the downstream end of the lock and is overall in good condition. Southeast of the lock chamber are concrete stairs that have open-grate treads and are lined with pipe railings. The stairs are in good condition. There are also concrete stairs with pipe railings on the southwest corner of the lock chamber that are in good condition. The powerhouse sits on the south bank of the canal about west of the upper lock gates between the bypass spillway and sluice gates. It is a single-story concrete building on a concrete foundation with a slate-covered hipped roof. The windows have been covered with modern screens.

The entrance is a wood double door with a four-light transom and modern screens. A concrete cantilevered platform extends from the northwest side of the structure. The powerhouse 1 Description of current conditions is based on a site visit by the HAER recording team in summer NEW YORK STATE BARGE CANAL, LOCK E33 HAER No. Page 2 originally contained two vertical-shaft AC generators and a motor-generator set that converted AC to DC for use at the lock, but none of the machinery remains. The powerhouse is in good condition. On the north side of the chamber is the lockhouse, which is a single-story concrete block building on a concrete foundation. The cross-gable roof is covered with asphalt shingles, and there is wood siding in the gable ends.

There are one-over-one-light wood windows with steel mesh coverings. The entrances are comprised of a single-panel wood door and a modern pane- and-panel door. The lockhouse is in good condition. The garage is a single-story concrete building on a concrete slab foundation near the upper lock gates. The gable roof is covered with asphalt shingles and has horizontal siding in the gable ends. There is a modern pane-and-panel door and a modern vinyl garage door. The garage is also in good condition. The guide walls are generally in good condition. The northwest one is scored concrete with a concrete-filled cast-iron bollard. The northeast guide wall is also scored concrete, with some areas of heavy spalling and breaking.

Concrete-filled cast-iron bollards and reproduction light fixtures line this wall. The southeast guide wall is scored concrete, as is the southwest one. Both are lined with concrete-filled cast-iron bollards, and the southeast one is also equipped with modern light fixtures and steel ladders. West of the lock is a steel dock on steel piers. It has an open-grate deck lined with pipe railings. It is in fair condition. To the south of Lock E33 is a bypass channel with a concrete spillway. This spillway has a single concrete apron with embedded stones to break up and aerate the water flowing over it. Four piers across the spillway s crest contain slots to hold stoplogs and support an open-grate catwalk lined with a modern steel railing that spans the spillway.

Both the spillway and catwalk are in good to fair condition. History: Millard & Lupton Company of Philadelphia, Pennsylvania, won Contract 23 on August 18, which included construction of Lock E33. The contract was under the direction of Marsh and Wickman, State Assistant Engineers, at various times. Work started in October with excavation. By September 30, the prism between locks E32 and E33 was 60 percent complete. During the concrete floor, bottom of both side walls, and the breast wall had been poured, and the upper spillway and powerhouse were in place. The following year saw the completion of the concrete work of the lock and all structures.

The lock was finished in 2 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, and Annual Report of the State Engineer and NEW YORK STATE BARGE CANAL, LOCK E33 HAER No. Page 3 The power plant was part of Contract 94, awarded to MacArthur Brothers Co. & Lord Electric Co.

of New York City on February 17, The contract encompassed the power plants, electrical equipment and machinery for operating and lighting locks E26, E27, E28A, E28B, E29, E30, E32, E33, E34 and E35, and guard locks. The contract was completed on July 9, In the Department of Public Works decided that extra power generated at this lock would be transmitted to Pittsford for use at the canal maintenance shops there.3 Later work and alterations to the site included repairs to the motor, valve, and gate controls in as well as powerhouse equipment. Five years later, the lower gate machinery had to be overhauled. The lockhouse was a later addition to the site, built by the Department of Public Works prior to

Sources

422 words

Source document Quoted word for word from HAER NY-463. Not written, edited or summarised by this site.

Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1.

Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Hay, Duncan. New York State Barge Canal. National Register of Historic Places Registration Form, Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 3 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol.

1 (Albany: Lyon Company, and State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (Albany: Lyon Company, Printers, 19. 4 State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (New York: Publishers Printing Co., 22; State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (Albany: Williams Press, Inc., Series New York State Archives, Albany, New York, Western Division, Erie Canal, Section 9, Sta. to Sta. approved December 29, 88. NEW YORK STATE BARGE CANAL, LOCK E33 HAER No. Page 4 Series New York State Archives, Albany, New York. Western Division, Erie Canal, Section 9, Sta. to Sta. Approved December 29, 88. State of New York, Department of Public Works.

Annual Report of the Superintendent for the Year Albany: Lyon Company, Printers, Annual Report of the Superintendent for the Year New York: Publishers Printing Co., Annual Report of the Superintendent for the Year Albany: Williams Press, Inc., Historians: Laura S. Black and Jami Babb, summer

Written history

198 words

Source document Quoted word for word from HAER NY-463. Not written, edited or summarised by this site.

The Historic American Engineering Record (HAER) is a long- range program that documents and interprets historically significant engineering sites and structures throughout the United States. HAER is part of Heritage Documentation Programs (Richard O Connor, Manager), a division of the National Park Service, United States Department of the Interior. The New York State Barge Canal Survey was undertaken in summer in cooperation with the Erie Canalway National Heritage Corridor (ERIE), Beth Sciumeca, Executive Director. Justine Christianson, HAER Historian, and Duncan Hay, ERIE, served as project leaders. The staff of the New York State Canal Corporation provided access to the sites. Craig Williams of the New York State Museum provided research materials and assistance.

The HAER field team consisted of Jami Babb and Laura Black. NEW YORK STATE BARGE CANAL, LOCK E33 HAER No. Page 5 Appendix: Images of Current Conditions Image 1: Powerhouse. Field photograph taken by HAER recording team, summer Image 2: Lockhouse. Field photograph taken by HAER recording team, summer NEW YORK STATE BARGE CANAL, LOCK E33 HAER No. Page 6 Image 3: Garage. Field photograph taken by HAER recording team, summer Image 4: Bypass channel with spillway. Field photograph taken by HAER recording team, summer

In context

Henrietta, New York The place record: every map, photograph and survey of this town.
Monroe County, New York 198 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Henrietta

1 record

The federal surveyors worked through Henrietta building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
Elihu Kirby HouseHABS NY,28-HEN,1-274 words

Provenance

  • Written history. Quoted verbatim from HAER NY-463. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.