Main Street Lift Bridge in Brockport, located on the Erie Canal, is a component of the nationally significant New York State Barge Canal. It is one of sixteen such bridges constructed between Fairport and Lockport. Description: The sixteen vertical-lift bridges on the Erie Canal are Warren pony trusses raised by an electrically-driven system of cables, counterweights, and sheaves. As described in the New York State Barge Canal National Register nomination, the moveable truss is supported by vertical lifting frames at either end. When the bridge is down the lifting frames retract into the pits located behind the bridge abutments.
The bridge is raised by cables that run from fixed anchor points at the top of the pits, down around sheaves at the bottom of the lifting frame, back up to sheaves at the top of the pit, and down to cast concrete counterweights. When the counterweights sink into the pits the cables pull the lifting frames upward by the sheaves at their lower corners. Each bridge has a control tower, with the motors and gearing generally located in the pit nearest to the tower.1 The steel Warren pony truss with open-grate decking carries Main Street across the Erie Canal.2 The bridge is long and between curbs and is classified as a heavy lift bridge. Steel stairways at either end of the west side of the bridge provide access to a pedestrian walkway that is separated from the roadway by steel lattice.
The machinery pits are covered with cross-hatch plates. The bridge plate reads: Built by the McMyler-Interstate Co. Cleveland, OH The bridge is in good condition. The control tower is located on the west side of the bridge at the north end. It is a two-story concrete building on a concrete foundation. The roof is flat, and the walls are pierced by one- over-one-light wood and two-over-two-light wood windows as well as pane-and-panel doors. The tower features the historic warning bell and is in good condition. History: The Main Street Lift Bridge was built as part of Contract awarded to Cooper Company of Cleveland, Ohio, on May 4, although it appears the steelwork was subcontracted to McMyler-Insterstate Co. based on the bridge plate.
The contract included the 1 Duncan Hay, New York State Barge Canal, National Register of Historic Places Registration Form, Section 7, Pages 2 Description of current conditions is based on a site visit made by the HAER recording team in summer NEW YORK STATE BARGE CANAL, MAIN STREET LIFT BRIDGE (BROCKPORT) HAER No. Page 2 construction of four lift bridges, including the one in Brockport. The work on this bridge began in June with excavation of the north counterweight pit, along with necessary sheeting and bracing, completed that year. Alteration No. 1, approved September 10, called for changing the north approach to Main Street. An extra work order, dated November 23, required the contractor to erect a timber trestle for use by pedestrians while work continued on the lift bridge.
By October the retaining walls and flush tank at the north approach had been constructed, and the excavation and sheeting for the north counterweight were also complete. The concrete work for the north pit was about 40 percent complete. Work progressed steadily until completion in October The superstructure may have been rehabilitated under Contract which called for the replacement of the steel truss at three bridges: two in Brockport and one in Holley.4