Tappan Zee Bridge, Carrying Interstate 87 and 287 on the New York Thruway spanning the Hudson River, Tarrytown

Tappan Zee Bridge, Carrying Interstate 87 and 287 on the New York Thruway spanning the Hudson River, Tarrytown, Westchester County, NY. Surveyed as HAER NY-556, with a 14,714-word written history.

From the record

“The Tappan Zee Bridge is significant in engineering history as the longest bridge in New York state and the world s ninth largest cantilever span Designed by engineer Emil H.”

Written record, HAER NY-556 survey. Machine-read text.

Surveyed by the federal HAER program as HAER NY-556 · the record runs 14714 words · one of 80 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Location

123 words

Source document Quoted word for word from HAER NY-556. Not written, edited or summarised by this site.

Spanning the Hudson River and carrying Interstate from the villages of South Nyack and Grand View-on-Hudson in Rockland County, New York (west), to the village of Tarrytown in Westchester County, New York (east). The west terminus of the bridge is located at latitude: longitude: and the east terminus is located at latitude: longitude: The center point of the Tappan Zee Bridge is at latitude longitude Terminus points were determined as center points of the roadway at the location of the inner face of the abutment walls at either end of the bridge. Coordinates were obtained May 2, using desktop ArcGIS mapping software. Coordinates are based on North American Datum The Tappan Zee Bridge location has no restriction on its release to the public.

Present Use

56 words

Source document Quoted word for word from HAER NY-556. Not written, edited or summarised by this site.

Seven-lane vehicular bridge serves as a 3.1-mile component of the 570-mile New York State Thruway system. In the NYSTA began construction of a replacement bridge just north of the historic Tappan Zee Bridge. It is estimated that the existing bridge will be decommissioned and demolished in fall after the completion of the new Tappan Zee Bridge.

Significance

169 words

Source document Quoted word for word from HAER NY-556. Not written, edited or summarised by this site.

The Tappan Zee Bridge is significant in engineering history as the longest bridge in New York state and the world s ninth largest cantilever span Designed by engineer Emil H. Praeger of Madigan-Hyland, Consulting Engineers, it was the first permanent bridge in the United States to be supported, in part, by buoyant caissons. This caisson design made it possible to construct the bridge at a wide Hudson River crossing, reducing the load on the steel piles supporting the Main Spans and the easternmost span of the West Deck Truss. Steel piles do not reach bedrock until below the river bottom. The steel cantilever truss bridge is unique for its S-shaped configuration integrating five distinct components: a long west Causeway, the Main Spans, West and East Deck Trusses, and the East Trestle.

The bridge has undergone few modifications since it opened. Historians: Jeanne Barnes, Chad Blackwell, Ann Keen, Megan Mueller, Marjorie Nowick, Kathryn Plimpton, Hilary Retseck, Paul Weishar, and Melissa Wiedenfeld, all of Inc. completed this narrative report in May

Written history

12275 words

Source document Quoted word for word from HAER NY-556. Not written, edited or summarised by this site.

This documentation was prepared for the NYSTA, New York State Department of Transportation, and the Federal Highway Administration as partial mitigation for the demolition of the Tappan Zee Bridge. HDR staff participating in the preparation of this document, in addition to the historians listed above, include: Adrian Quintana (measured drawings); Nancy Jepsen (technical editing); and TAPPAN ZEE BRIDGE HAER No. (Page 2) Kathy Lemberg (GIS data). Rob Tucher and Richard Casella of Historic Documentation Company, Inc., completed the large-format and digital photography of the bridge. Christopher H. Marston, HAER Architect, reviewed the documentation and assisted in the development of the drawings. TAPPAN ZEE BRIDGE HAER No. (Page 3) Part I. Historical Information A. Physical History: 1.

Date of construction: Bridge opened December 15, 2. Engineer: Madigan-Hyland, Consulting Engineers, New York; Emil H. Praeger, chief design engineer. 3. Primary Builders/Contractors: Merritt-Chapman & Scott Corporation, New York (foundation); American Bridge Company, New York (superstructure fabrication); Corbetta Construction Company, New York (caissons). 4. Original plans and construction: The bridge is constructed primarily of steel and concrete and it comprises five distinct segments spanning approximately 3.1 miles. Proceeding from west to east, the bridge starts at the Causeway (or West Trestle), which is long. Its concrete deck is supported by a substructure of steel stringers and reinforced concrete piers resting on timber pilings.

The West Deck Truss (approximately incorporates seven Warren truss spans set on steel stringers and reinforced concrete piers that rest either on circular cofferdams or buoyant caissons (four eastern piers) above steel piles and rock. The Main Spans section has two anchor spans and two cantilevers flanking a suspended center span The trusses are supported by steel piers and buoyant caissons on steel piles. The East Deck Truss (approximately while longer than the West Deck Truss (thirteen spans versus seven), uses similar structure and materials with the exception of buoyant caissons, which are not used on the east approach. The East Trestle (approximately like the Causeway, has a concrete deck supported by steel stringers and concrete piers on rock. 5.

Alterations and additions: The Tappan Zee Bridge has had modifications for maintenance, including replacement of its roadway deck, but its essential character-defining features remain intact. Deterioration of the roadway due to salt prompted the resurfacing of the deck. Also due to salt, the bridge s open gutter system was eventually closed to prevent the salts from draining onto the steel members. In December a steel guide rail was added to the median for additional safety. 1 In the center median was removed in order to add a seventh traffic lane, configured to provide an additional southbound lane. At the same time, the number of toll booths increased from ten to thirteen, all on the southbound side.

In the west approach expanded to four lanes, again by reconfiguring the median, reducing or removing shoulders, and reducing lane width. 2 1 New York State Thruway Authority, Annual Report (Albany, NY: New York State Thruway Authority, 14. 2 James Brooke, On the Tappan Zee, Time to Unclog the 3-Mile Jam, New York Times, April 11, B1. TAPPAN ZEE BRIDGE HAER No. (Page 4) In February a movable barrier was installed on the bridge that allowed for changing the direction of the center lane. This required demolition of the existing median, construction of a garage for the movable barrier vehicle, electrical upgrade, and reconfiguring the center lane crown and joints.

Between June and December portions of the concrete deck on the Rockland County side of the bridge were replaced, as was the Westchester County portion on the Main Spans section. In the remaining Westchester County deck was also replaced. B. Historical Context: 1. Pre-construction: Ideas for a Hudson River crossing from Rockland County to Westchester County were mentioned in the when bridges like the Hudson River Bridge at Albany and the Poughkeepsie Bridge were built. Proposals began to take solid form during the in part related to the formulation of the Regional Plan for New York. Politicians like Ferdinand (Fred) Horn, State Assemblyman for Rockland County, who was a local realtor, tied construction of a bridge to Rockland County s modernization.

Horn proved to be a formidable booster for a Hudson River crossing. During the early Horn introduced several bills in the New York State Assembly for a Hudson River crossing, although the locations varied and structures ranged from bridges to tunnels to tunnel-bridge combinations. In Horn proposed a bridge between Nyack and Tarrytown, and the project advanced through the state legislature farther than any of his previous proposals. The Rockland-Westchester Causeway and Tunnel Authority (RWCTA) was established in July to oversee planning and funding for construction of the bridge. RWCTA and the state s Department of Public Works sought federal Public Works Administration funding for the project. In August Congress approved a bill funding the bridge, and surveys began thereafter.

The location Horn proposed was in the area known as the Tappan Zee, from the early Dutch settlers name for the local Lenape habitants, Tappaen, and the Dutch word for sea or open water, zee. 3 This site was controversial among local residents, with opposition to the proposal proving to be only a little less controversial on the east side of the Hudson in Tarrytown than in South Nyack and Grand View-on-Hudson (Grand View) on the west side. Leading the opposition were Elmer Hadar, Grand View s zoning manager, and his wife Berta, both successful authors and illustrators of children s books.

In response to discussion of locating the west side of the bridge at Grand View, named for its view over a particularly beautiful stretch of the Hudson, local artists and writers spearheaded protests and galvanized other citizens groups and women s groups to join the cause. With the support of local leaders, they blocked bridge surveyors, held demonstrations, and engaged in large-scale letter-writing campaigns. 4 At the same time, various bridge site alternatives for the eastern side of the Hudson were considered, including in North Tarrytown (now Sleepy Hollow), which was rejected as being too close to Kykuit, John D. Rockefeller, Jr. s estate in North Tarrytown.

5 In November the Authority officially dropped the Grand View location, citing construction cost increases due to geological conditions that required deep borings to support the bridge. The projected cost of bridge 3 Tappan Zee Bridge Dedication Committee, Tappan Zee from the Half Moon to the Bridge (Tarrytown, NY: Tappan Zee Bridge Dedication Committee, 4 Rockland Women Rout Bridge Aides, New York Times, September 12, 19; Bridge War Grows in Hudson Valley, New York Times, September 13, Bridge Fight Organized, New York Times, October 11, 5 Nyack Bridge Plan Dropped by Board, New York Times, November 20, 25. TAPPAN ZEE BRIDGE HAER No.

(Page 5) construction had jumped from $7 million to $10 million, and there were serious concerns that tolls from motorists would not be able to make up the cost difference.6 Attention then turned to a proposal by the Rockland-Westchester Hudson River Bridge Authority for a bridge combining a low causeway (raised road over water) with a high span over the Hudson River s main channel from Nyack on the Rockland County side to Tarrytown in Westchester County. 7 However, management at the Port of New York Authority (established in and renamed the Port Authority of New York and New Jersey in argued that the proposed location was within its jurisdiction and that the Port Authority had exclusive rights to build a bridge there.

8 In the wake of the ongoing location disputes for the proposed bridge, the establishment of the New York State Thruway system provided the means for further consideration of a Hudson River crossing. In Assemblyman Abbot Low Moffat of New York City and Senator William H. Hampton of Utica sponsored legislation for the New York State Thruway, as yet unnamed but referred to as a cross-state superhighway. This highway was added to the state highways map in after Governor Herbert H. Lehman signed a bill (Chapter 914 of the Laws of that allowed for the planning, design, and construction of the super highway across the state. 9 At that time, the state had plus miles of roadway, but only 117 miles were divided highways and only percent of paved highways had more than two lanes.

10 The new road was envisioned as a limited access, high-speed thoroughfare to be modeled after the Pennsylvania Turnpike, which opened in A limited-access thruway offered needed increased speeds and safety to counter the crowded roads.11 The proposed state thruway was to have no intersections, no steep inclines, divided lanes, and access only at designated locations. These features were included to decrease the risk of accidents and increase the maximum capacity of the roads. The original route was to extend from Buffalo to State Route 17 at the New York/New Jersey state line and then send traffic into New York via the George Washington Bridge in Fort Lee, New Jersey. This plan would have kept superhighway traffic on the west side of the Hudson River.

Governor Thomas Dewey recommended work begin on the superhighway as funds permitted and signed additional legislation determining the routes of what were referred to as the Berkshire Section (24 miles in Rensselaer and Columbia Counties) and the New England Section (15 miles in Bronx and Westchester Counties) of the Thruway. Ground was broken on the first section of the Thruway, a portion of road near Syracuse in Liverpool, New York, in July 12 As the governor 6 Nyack Bridge Plan Dropped by Board ; Charles Grutzner, Over the Hudson: Tappan Zee Bridge Has Had Checkered Past, New York Times, June 20, 7 Donald E. Wolf, Crossing the Hudson: Historic Bridges and Tunnels of the River (New Brunswick, NJ: Rivergate Books, 178 79.

8 Wolf, Crossing the Hudson, 9 The New York State Thruway: The Beginning, The Upstate New York Roads Site, accessed October 10 New York State Thruway Authority, First Annual Report of the New York State Thruway Authority (Albany, NY: New York State Thruway Authority, January 31, 1. 11 State Thruway, New York Times, April 26, New York State Thruway Authority, First Annual Report, 12 Thruway Work to Start, New York Times, April 26, Thruway Near Reality, New York Times, July 7, Work on Thruway Started by Dewey, New York Times, July 12, TAPPAN ZEE BRIDGE HAER No. (Page 6) recommended, construction commenced under the aegis of the New York State Department of Public Works.

13 Highway proponents planned on using the New York Postwar Reconstruction Fund (later known as the Capital Construction Fund) to bankroll the new highway s construction, but post-World War II labor and material prices pushed the Thruway s projected cost to almost double of the original million construction cost estimate. 14 In the State Department of Public Works and the U.S. Bureau of Public Roads issued The Cooperative Highway Needs Study, which highlighted the urgency for improved roads throughout the state.

The report called for the creation of a governing body that could oversee the planning and construction of the expressway as well as a financing plan to supplement state funds and quicken construction.15 On March 21, Governor Dewey signed the Thruway Law (Chapter Laws of which created the NYSTA and allowed it to issue bonds and construct the highway on a self-liquidating basis through the use of tolls collected from Thruway users. 16 A year later, voters approved a state constitution amendment by a margin of four to one allowing the NYSTA to use state credit to back its bonds, which enabled the group to secure lower interest rates on funds borrowed for the project.17 As the project continued into the federal money also contributed to the Thruway s construction.

Despite the earlier difficulties of finding an acceptable bridge site, there was growing consensus that a Hudson River bridge was needed north of the George Washington Bridge, particularly as progress was being made on the Thruway at upstate locations. The increased popularity of the automobile triggered safety and capacity problems on the roads, and there was growing impatience with the local Hudson River ferry service, especially during winter when the river froze. While many locations for the bridge had been considered, the South Nyack/Grand View Tarrytown location remained the Governor s and the NYSTA s primary choice. Yonkers was rejected because it already was heavily developed and a bridge to the south would add to New York City traffic and congestion.

North of Nyack, a bridge in the vicinity of the Ramapo Mountains and Bear Mountain- Harriman State Parks would force travelers to detour to reach the rest of the Thruway. In addition, there was already a Hudson River crossing at Bear Mountain State Park, albeit at its northern end. A bridge between Rockland and Westchester Counties, between the George Washington Bridge and the Bear Mountain Bridge, offered a crossing that could connect numerous population centers and regional highways while still avoiding congested areas near New York City. Westchester County, the site of the eastern approach to the proposed bridge, developed earlier and had already become a New York commuter suburb by the but Rockland County, the western approach, remained relatively isolated and rural.

18 13 Predicts Thruway Will Enrich State, New York Times, April 25, 25. State Thruway, New York Times, April 26, 26. 14 New York State Thruway Authority, First Annual Report, 15 New York State Thruway Authority, First Annual Report, A Self-Financed Thruway, New York Times, February 14, New Thruway Study is Ordered by State, New York Times, March 28, 16 The New York State Thruway: The Beginning. 17 New York State Thruway Authority, Second Annual Report (Albany, NY: New York State Thruway Authority, 13. 18 Wolf, Crossing the Hudson, 185 TAPPAN ZEE BRIDGE HAER No. (Page 7) A May 8, New York Times article announced Governor Dewey is Adamant on Thruway Span.

The Port Authority s announcement that it was exploring a Hudson River crossing south of Dobbs Ferry at the north end of its jurisdiction had convinced the Governor that the Thruway should have a Hudson River crossing that would integrate with the expressways in Westchester County and bring traffic directly into New York City. The governor and Thruway advocates were determined to modify a agreement between New Jersey and New York that protected the Port Authority s exclusive right to river crossings within 25 miles of the Statue of Liberty, a distance that included Nyack. 19 With the Port Authority s announcements, Dewey hardened his resolve for a Thruway crossing of the Hudson.

One of the first acts of the NYSTA was to hire Madigan-Hyland, Consulting Engineers to study the economic feasibility of a financially self-supporting Thruway system. It also commissioned the firm to study the feasibility of a Hudson River bridge crossing at South Nyack and Tarrytown. New York City master planner and power-broker Robert Moses visited the proposed bridge site at the invitation of Westchester County leaders, reinforcing the likelihood of a South Nyack Tarrytown crossing for the Thruway. Of interest to Moses, this location would facilitate connections with the Saw Mill Parkway and Major Deegan Parkway at the Westchester-Bronx line to bring Thruway traffic into New York City.

20 By April Madigan-Hyland s engineers had conducted borings of the river bottom at Grand View-South Nyack to determine the feasibility of a Thruway bridge. In December the NYSTA selected the South Nyack Tarrytown site for the Hudson River bridge. 21 A December 8, New York Times article announced that the Thruway would cross the Hudson River on a bridge at the Tappan Zee, specifically between South Nyack/Grand View and the south end of Tarrytown. The proximity of regional expressways and avoiding a major increase in traffic on the George Washington Bridge helped justify the location decision. The article also presented Madigan-Hyland s conceptual plan for the bridge: a long, tied-arch main span and a long west causeway.

The bridge would be supported by buoyant caissons, a new type of foundation for a bridge, to overcome the geological challenges at this location. 22 The major opponents to the plan were the Port of New York Authority and New Jersey Governor Alfred E. Driscoll, who wanted to construct a bridge across the Hudson River near Dobbs Ferry, New York, or at a crossing narrower than Tappan Zee at Hastings-on-Hudson. Both parties favored these locations because either site would allow for easier connection to highways that New Jersey was building, and the Port Authority would receive the revenues from bridge tolls within its jurisdiction.

Governor Dewey, a former New York City district attorney, bridled at the objections from across the Hudson River and worked out a solution for the Thruway bridge that ultimately thwarted Driscoll s and the Port Authority s plans. 23 19 That Thruway Bridge, New York Times, May 10, Site is Selected for Thruway Span, New York Times, December 8, 31. 20 Tappan Zee Span for Thruway Seen, New York Times, April 17, 44. 21 Site is Selected for Thruway Span. 22 Site is Selected for Thruway Span ; Tappan Zee Bridge: Historic Overview, NYCRoads.com, accessed October 14, 23 Wolf, Crossing the Hudson, TAPPAN ZEE BRIDGE HAER No.

(Page 8) The New York State Legislature authorized the Tappan Zee Bridge as part of the Thruway in March 24 By this time, the total estimated cost of the bridge had escalated to $50 million. The bill was the first step in removing legal obstacles that had prevented the NYSTA s construction of the bridge, as it reduced the northern boundary of the Port Authority s jurisdiction under the Bridge Authority Act, and removed the bridge location from Port Authority s jurisdiction. The NYSTA then sent the Department of the Army its application for a permit to build the bridge.

With the public announcement of the passage of the Bridge Authority Act, residents in South Nyack and Tarrytown again resumed their protest, arguing that construction would condemn and destroy much of their business and residential sections.25 Local planners also voiced concern. Paul Windels, president of the Regional Plan Association said that the bridge constitutes a basic error in the entire superhighway and that the bridge had a poor design that had never been tested to that scale, it was unsightly and more expensive than a conventional bridge, and it was an overall menace to navigation.

He predicted that it would cause needless dislocations in the affected towns.26 In May the Department of the Army approved construction of the tier-arch bridge and issued the required permit, which was the last regulatory step needed prior to construction. The Department of the Army required the design to be modified, including replacing a earthen causeway with a series of all-steel bent spans for improved river navigation. The Army feared the earthen causeway would have been a navigation hazard on the river, causing eddies and ice jams along the west bank.

With the addition of approximately tons more steel, the estimated cost of the bridge itself did not go up but the budget for the entire span increased to $60 million.27 Bertram Tallamy, the head of the NYSTA, had hoped that defense mobilization in Korea would not interfere with obtaining the steel when it was needed in 28 In June of workers drove the initial test pilings for the bridge, but construction was delayed until because of steel shortages caused by the Korean War. 29 2. Construction: Initial construction finally began on the bridge pilings in March with Madigan-Hyland overseeing construction. 30 Construction Aggregates Inc. won the bid for the pilings work.

31 In November of newspapers reported that the bridge would have ten caissons and that the scheduled completion date was projected as October 1, 32 On December 10, the New York State Department of Public Works advertised in the New York Times for contractor bids for the 24 Hudson River Bridge for Thruway Voted, New York Times, March 15, 25 Hudson River Bridge for Thruway Voted. 26 Tappan Zee Bridge: Historic Overview; Tappan Zee Bridge Called Error : Span Held Unsightly, Costly , New York Times, January 2, 27 Wolf, Crossing the Hudson, 28 Warren Weaver, Big Thruway Span Approved by Army: Action Clears the Last Legal Obstacle to Construction of Bridge Over Hudson, New York Times, May 3, 29 Tappan Zee Bridge: Historic Overview. 30 Tappan Zee Bridge: Historic Overview.

31 Wolf, Crossing the Hudson, 32 Bert Pierce, Automobiles Thruway: Buoyant Caissons to Be Used to Support Three-Mile Bridge Across Hudson, New York Times, November 2, TAPPAN ZEE BRIDGE HAER No. (Page 9) construction of the bridge superstructure. Construction bids for the tied-arch, deck girders and I- beams, and the steel towers were requested, but no bids were received. 33 No firm had the capabilities to build a tied-arch bridge of that size, and the state s estimated cost for a tied-arch bridge of that size was too low. Under these conditions, insurance companies refused to insure the construction.

Madigan-Hyland s chief engineer, Emil Praeger, quickly worked up a substitute design for a cantilever-truss for the tied-arch main span without needing to make substantial changes to the rest of the bridge design. 34 In April of a low bid of from the American Bridge Company, a division of the U.S. Steel Corporation, was accepted for the construction of the bridge s steel superstructure with a cantilever main span. Bertram Tallamy predicted the receipt of the bid would allow for completion of the span by fall of With the announcement of the bid acceptance, all other major contracts would be let and as well as minor contracts for the roadway, sidewalks, and lighting. To date, the superstructure contract was the largest single award let for the Thruway work.

With the announcement of bid, a drawing of the revised design was released, and Madigan-Hyland called it one of the ugliest bridges in the East, and bemoaned the loss of the more attractive tied-arched design. 35 Construction of the bridge s substructure began in including pilings, caissons, cofferdams, and ice breakers. On August 7, the NYSTA reported that work would start soon on the construction of the nineteen reinforced concreted bents. Merritt, Chapman & Scott Corporation would do the work, which was estimated to cost and were required to complete the bents by the end of January 36 On October 13, the first of the eight concrete caissons were transported to the work site via barge.

The caissons had been constructed in a drained clay pit at Grassy Point, approximately 10 miles north of the construction site.37 The construction of the caisson-piles began mid-stream, moving east and tying into other foundations. However, by June 20, almost a year later, bridge construction was nineteen months behind schedule and new completion dates were pushed to late Foundation work was 90 percent complete and the reinforced concrete bents were in place.38 Eight months before the completion of the bridge, the Engineering News-Record hailed the bridge as a foundation triumph for its use of the concrete caissons, which proved to be quite economical at approximately one-third of the total price.

39 Emil Praeger presented a paper for the Municipal Engineers Journal on the bridge, discussing its foundation, design, and structural features. In the paper, Praeger gave the reasons for the caissons and the changes made before the initial bidding process, and then focused on the actual final design 33 Proposals, New York Times, December 10, 34 Although not specifically addressed in historical documentation, the new design called for eight caissons instead of the ten required by the original design. 35 Low Bid Received on Thruway Span: Tallamy Predicts Completion of Disputed Tappan Zee Bridge by Fall of New York Times, April 17, 36 Thruway Span Gains: Work to Begin Soon on Section of Tappan Zee Bridge, New York Times, August 8, 37 Tappan Zee Bridge: Historic Overview.

38 Grutzner, Over the Hudson. 39 Tappan Zee Bridge: A Foundation Triumph, Engineering News-Record, April 14, TAPPAN ZEE BRIDGE HAER No. (Page 10) and construction. 40 In September the bridge itself was completed and the two anchor spans had been secured. In order to finish before the end of the year, construction crews had to finish paving, painting, lighting, and other systems. 41 The bridge was completed in late 3. Opening and dedication: On December 15, the bridge, span, and all support systems were finally completed at a final cost at The completion of the bridge also meant a completion of the New York-Buffalo Thruway, an event worthy of celebration.

42 The Thruway was officially dedicated on December 15, during a formal ceremony celebrating the opening of the Tappan Zee Bridge and the completion of the last toll link on the highway. 43 That day, a dedication ceremony took place in South Nyack led by Governor Harriman. Unfortunately, Praeger was not present for the ceremony, nor was he mentioned in any of the speeches.44 After five years of controversy, a small group of picketers were present, but they caused no problems since Governor Harriman invited them to join him in the dedication. A bronze plaque was installed as part of the dedication. Prominent people present at the ceremony included Governors Dewey and Harriman, Chairman Tallamy, and staff members of Madigan-Hyland, Consulting Engineers.

Three days after the opening celebration, traffic problems were evident on the newly completed bridge. On December 18, the first Sunday that the bridge was open to the public, there was a minor accident that caused a twenty-minute delay and confusion on how to turn west on the bridge.

New traffic signs were fabricated to eliminate future confusion.45 This final toll link provided access into Rockland and Westchester Counties, and completed the New York City-Buffalo portion of the New York State Thruway, increasing the Thruway s length to 423 miles and making it the longest operating toll expressway in the nation.46 During the first two hours of operation, vehicles made the trip across the Hudson River.47 In total, the NYSTA earned gross revenue totaling over $13 million from tolls in its first year of operation. Additionally, over annual permits were sold at $20 each.48 In May trips were made over the 40 Emil H.

Praeger, The Nyack-Tarrytown Bridge: Foundation Problems, General Design and Structural Features Nyack-Tarrytown Bridge, The Municipal Engineers Journal 41 137 43. 41 Wolf, Crossing the Hudson, 42 Joseph C. Ingram, Thruway Opened With Dedication of Last Toll Link, New York Times, December 16, 43 Ingram, Thruway Opened with Dedication of Last Toll Link. 44 Wolf, Crossing the Hudson, 45 New Bridge Crowded: Tappan Zee Span Gets First Sunday Traffic Workout, New York Times, December 19, 46 New York State Thruway Authority, Fifth Annual Report (Albany, NY; New York State Thruway Authority, January 31, 3; New York State Thruway Authority, Sixth Annual Report (Albany, NY: New York State Thruway Authority, January 31, 44.

47 Michael Risinit, Tappan Zee: A Bridge to a New Era, Lohud.com, accessed April 9, 48 New York State Thruway Authority, Sixth Annual Report, 40. Permits were valid for travel on the controlled section of the Thruway, from Spring Valley in Rockland County and Buffalo. TAPPAN ZEE BRIDGE HAER No. (Page 11) Tappan Zee Bridge, accounting for in toll revenue.49 By the end of all 559 miles of the original New York State Thruway system were open, with annual revenue totaling over $52 million on 70 million toll transactions.50 4. Post-opening though Newspapers continued to publish articles on the Tappan Zee Bridge after it opened. According to a New York Times article, the span had the most concentrated over-the- water lighting installation in the world.

51 Within the first year of operation, the bridge averaged vehicles per day. 52 In addition to the ongoing local interest, completion of the bridge project helped NYSTA accomplish its mission of creating a statewide superhighway. On August 31, when construction ended on a 3-mile section between Yonkers and the Bronx, the Thruway mainline was complete. 53 In the bridge was re-designated Interstate replacing its previous designation as part of Interstate 54 From to the number of vehicles passing through the bridge tolls rose from to 55 In there was one waterway accident at the bridge. A marine crane s aerial boom hit the Main Spans on December 6, Vehicular traffic was not affected on the day of the accident, but the span was closed for two hours for repair.

56 As reported in the NYSTA annual report, the record revenue day for the bridge was on August 13, when the NYSTA earned from tolls from vehicles. Bridge revenues for were from passenger vehicle tolls and from commercial vehicles, totaling 57 In the Tappan Zee Bridge experienced the most traffic of any location on the Thruway system, with a record trips that year. NYSTA, in an effort to improve overall Thruway safety, installed 1 mile of steel guide railings on the west end of the span to prevent oncoming traffic collisions. The median construction cost and installation was completed in December. At the same time, the pavement was roughened to control vehicle skidding, and new eastbound signs were installed warning drivers to keep in line.

58 A new daily record was set on July 29, with 49 Thruway Tolls for May Increased by Nearly 60 Per Cent, The Times Record [Troy, New York], June 14, pg. 34. 50 New York State Thruway Authority, Annual Report (Albany, NY: New York State Thruway Authority, 20. 51 Photo Standalone 4 No Title, New York Times, December 21, 52 Tappan Zee Bridge: Historic Overview. 53 New York State Thruway: Historic Overview, NYCRoads.com, accessed April 17, 54 Tappan Zee Bridge: Historic Overview. 55 New York State Thruway Authority, Ninth Annual Report (Albany, NY: New York State Thruway Authority, 28. 56 New York State Thruway Authority, Annual Report (Albany, NY: New York State Thruway Authority, 42. 57 New York State Thruway Authority, Annual Report, 31 34.

58 New York State Thruway Authority, Annual Report, 14. TAPPAN ZEE BRIDGE HAER No. (Page 12) vehicles paying in tolls. Revenues for were from passenger vehicles and from commercial vehicles, totaling 59 Basic maintenance for the year included cleaning and painting. In crews were able to repaint all 6 miles of railings and approximately 6 miles of fascia beams. 60 In the superhighway system across the state was named The Governor Thomas E. Dewey Thruway in recognition of Dewey s contributions to the Thruway s planning and construction. 61 Although the number of annual permits dropped through the overall usage of the Thruway increased.

In annual revenue totaled more than million on 143 million toll transactions.62 These numbers skyrocketed by which resulted in total revenue on the 559-mile system of over million. 63 In Thruway maintenance crews removed the unused northbound toll booths at the bridge. The booths were removed because no bids were submitted for a major rehabilitation job at the toll plazas. The associated concrete islands were also removed and new pavement was installed. Beginning on August 12, only southbound tolls were collected. Other maintenance activities that year included replacing 250 wooden piles in the ice-breaker system. 64 In its annual report, NYSTA outlined its work on a major rehabilitation project for the Tappan Zee Bridge.

Contracts were issued for nine projects totaling Nab Construction Corporation received a contract for nearly $1 million for the removal and repair of expansion joints on the Main Spans, which led to lane closures and traffic delays. Other projects included deck resurfacing in the area of the expansion joints. To help alleviate traffic congestion, work was done at night with all six lanes open. 65 Yearly revenues for the bridge increased to from tolls from passenger vehicles and for commercial traffic with a total of The twentieth anniversary of the opening of the Tappan Zee Bridge was marked in Newspaper coverage included positive commentary on the bridge s economic impact on South Nyack and Tarrytown.

John Nagle, who was in favor of the plans in the noted that the bridge attracted businesses, such as General Foods and Hilton Inn, to Tarrytown and extended the city s tax base. 67 59 New York State Thruway Authority, Annual Report, 36 and 40. 60 New York State Thruway Authority, Annual Report, 59. 61 New York State Thruway Authority, Annual Report (Albany, NY: New York State Thruway Authority, 5. 62 New York State Thruway Authority, Annual Report (Albany, NY: New York State Thruway Authority, 20. 63 New York State Thruway Authority, New York State Thruway Authority Annual Report (Albany, NY: New York State Thruway Authority, 1. 64 New York State Thruway Authority, Annual Report (Albany, NY: New York State Thruway Authority, 40 42.

65 New York State Thruway Authority, Annual Report (Albany, NY: New York State Thruway Authority, 32. 66 New York State Thruway Authority, Annual Report, 27. 67 Bridge [clipping from unidentified newspaper], no date, Warner Library Tappan Zee Bridge Vertical File. TAPPAN ZEE BRIDGE HAER No. (Page 13) Comments about the bridge s merits remained largely positive in at the twenty-fifth anniversary of the bridge. An article from the Tarrytown Daily News echoed Governor Dewey s comments that the bridge would prove to be a symbolic span over which Westchester and Rockland Counties will move, virtually overnight, twenty years to the future. Since the bridge was built, the population in Rockland County had increased 150 percent and new shops and houses were built.

The article also noted increasing bridge congestion, ongoing maintenance, the issue of people jumping from the bridge, and increasing numbers of vehicle breakdowns on the bridge. 68 By to help alleviate ongoing traffic congestion, the central median section was converted to an additional Tarrytown-bound lane at an estimated cost of $20 million. 69 In a movable barrier system was installed, which allowed the central lane to accommodate either northbound or southbound traffic, based on traffic volume. If the additional lane was needed for northbound traffic during evening rush, for example, the barrier system would be engaged and the transition would take approximately forty-five minutes.

70 On June 14, the bridge was renamed the Governor Malcolm Wilson Tappan Zee Bridge in honor of the former governor twenty years after he left office. 71 Traffic congestion necessitated bridge modifications in the During the planning stages of the bridge, NYSTA estimated traffic would average approximately cars a day. However, by an average of cars crossed the bridge during each rush hour alone. Inspections revealed that some bridge components were nearing the end of their structural lives, and the bridge location and configuration restricted expansion beyond seven lanes.

72 More than million had been spent on bridge maintenance between and with an estimated million more needed for future maintenance and repairs.73 Evaluating feasible options, the NYSTA opted to increase toll charges to help pay for necessary repaving, electrical component replacements, new bearings, bearing oil changes, corroded brace restoration, and deck rail repairs. 74 In Governor George Pataki publicly commented that NYSTA officials were considering replacing the Tappan Zee Bridge. 75 With four times as much traffic crossing the bridge as originally projected, congestion and structural concerns were prompting widespread discussion. In state and local officials called for an impact study to consider replacing the Tappan Zee Bridge. 76 One 68 Neil S.

Martin, The Rockland Connection, Tarrytown Daily News, December 14, 69 Tappan Zee Bridge: Historic Overview. 70 Tappan Zee Bridge: Historic Overview. 71 Risinit, Tappan Zee: A Bridge to a New Era. 72 Melissa Klein and Greg Clary, A Bridge too Crowded: Region s Biggest Span Struggles under Red Tape, Population Growth, Tappan Zee Bridge: A Weakening Link [Gannett Newspapers], October 29, from Warner Library Tappan Zee Bridge Vertical File. 73 Klein and Clary, A Bridge too Crowded.

74 Tappan Zee Bridge by the Numbers, Tappan Zee Bridge: A Weakening Link [Gannett Newspapers], October 29, 75 Tappan Zee Bridge May Be Replaced, New York Times, July 17, 76 Rails Could Make New Tappan Bridge Acceptable at the Same Location, [clipping from unidentified newspaper], July 20, Warner Library Tappan Zee Bridge Vertical File. TAPPAN ZEE BRIDGE HAER No. (Page 14) major investigation was the feasibility of a dual vehicle/train bridge. Another consideration was the potential impact of increasing tolls and whether it would incentivize drivers to use mass transportation. 77 In transportation and government officials renewed the discussion of replacing the Tappan Zee Bridge and proposed a $16 billion new bridge with room for commuter trains and bus lanes.

The bridge itself would cost billion. 78 The New York State Department of Transportation, NYSTA, and the Metropolitan Transportation Authority commissioned an analysis of rehabilitation and replacement alternatives in that concluded that bridge replacement would most satisfy needs and goals at a lower cost than rehabilitation. In a thirty-eight-member review panel and NYSTA selected a billion design by Tappan Zee Constructors that includes eight general traffic lanes, four lanes for disabled and emergency vehicles, and an extra-wide shoulder to accommodate express buses. In construction on the new bridge commenced. 5. Resultant Growth and Development: Following completion of the Tappan Zee Bridge in the surrounding communities experienced significant residential and commercial growth.

In five years after construction, the population of Rockland County had increased 50 percent.79 Businesses seeking to escape rising Manhattan real estate prices moved to Westchester and Rockland Counties, now easily accessible from New York City. Commercial construction in Rockland County included hotels and motels, shopping centers, office parks, and office towers, and more than square feet of industrial floor space all built within ten years of the bridge s opening. 80 At the same time, the residential market was also experiencing rapid growth. By Rockland County averaged more than new residential units each year with more than homes under construction that year.

Rising population numbers in the Tarrytown and South Nyack areas necessitated construction of more than sixteen schools, as well as new post offices and other public services, and infrastructure improvements of roads, sidewalks, and sewers. 81 In retrospective newspaper articles, Rockland and Westchester County residents stated that they view the construction of the Tappan Zee Bridge as both a blessing and a curse. It brought money to the local area by virtue of taxes and tolls million in twenty-five years and more than million by the bridge s thirty-five year anniversary and provided jobs for hundreds of thousands of people. At the same time, the bridge also transformed the economic and cultural landscape of the counties, especially Rockland County.

82 With the extensive coverage of railroad lines east of the Hudson River, Westchester County s increased development had been seen as inevitable. However, Rockland County, because of the Tappan Zee Bridge, was transformed from small communities surrounded by rural landscape into a mature suburb by the end of the twentieth century, a transportation hub with more than cars passing through the area each day. 83 77 Bill Varner and Greg Clary, TZ Opposition Swells on Both Sides of Hudson, Journal News, January 17, 78 William Neuman, State to Replace, Not Rebuild, Tappan Zee Bridge, New York Times, September 26, 79 Nadene Hazell, Rockland Finds Bridge Is a Help and Hindrance, Journal News, July 13, A1. 80 Businesses Thriving in Rockland, New York Times, January 24, 70.

81 Businesses Thriving, 70. 82 Martin, A Rockland Connection ; Suzanne DeChillo, Lights on Tappan Zee Celebrate 35 Years, New York Times, December 16, 83 Randi Weiner, Bridge Ended Tarrytown s tranquillity, Journal News, October 29, 8A. TAPPAN ZEE BRIDGE HAER No. (Page 15) 6. Madigan-Hyland, Consulting Engineers: Madigan-Hyland, Consulting Engineers, headed by Michael John Jack Madigan and Richard Dick V. Hyland, was once described as the foremost public-works firm in New York, perhaps in the country. 84 During the in particular, Madigan- Hyland distinguished themselves as the engineering authority for high-profile projects in and around New York City.

The firm served as chief engineers for the Henry Hudson Bridge the Marine Parkway-Gil Hodges Memorial Bridge and the Bronx-Whitestone Bridge for which they were awarded the American Iron and Steel Institute Award. The firm also oversaw construction of the World s Fair site. Michael Madigan was born in in Danbury, Connecticut. By the age of 13, Madigan had dropped out of school and began working as a water boy on construction sites in Pennsylvania. By his mid- twenties, through hard work and determination, Madigan was hired as a labor foreman on small jobs. A few years later, he was promoted to construction superintendent. In Madigan was working on a project for the Long Island Commission, which was building an American Riviera at Jones Beach State Park.

When a key contractor went bankrupt, the president of the Commission, Robert Moses, quickly became impressed by the young Madigan s knowledge of the project as well as his personality, and relied upon him to complete the project. Forged from this was a business relationship that saw Moses commission Madigan for large-scale projects for more than thirty years, projects that transformed New York City s infrastructure and made both men rich and well connected.85 During World War II, Madigan served as a special assistant to the Under Secretary of War, Robert Patterson. Keenly aware of construction processes, Madigan successfully convinced the U.S. government to consolidate responsibility for constructing military facilities with the Army Corps of Engineers.

For his effort, Madigan was award a Medal of Merit. 86 Richard Dick V. Hyland was born on February 22, in Penn Yan Village, located in the Finger Lakes region of New York. In while a student at Notre Dame, Hyland was appointed a Second Lieutenant in the U.S. military and assigned to Camp Taylor, Kentucky. Less than four months later, Hyland was honorably discharged and returned to Notre Dame, graduating in with a degree in civil engineering. Following graduation, Hyland worked in general contracting and then for the Pennsylvania Railroad for six years. In Hyland and Madigan joined forces to establish Madigan-Hyland, Engineering Consultants in Rockville Centre, Long Island. 87 Despite the founders humble beginnings, the company grew quickly to occupy a building in Long Island City.

Shepherded by Robert Moses, the company won multiple Long Island Commission contracts, netting the business much needed capital and garnering prestige. Through this early success the company was able to hire a talented cadre of engineers, many of whom were graduates of Rensselaer Polytechnic Institute (RPI) and Ivy League schools. Whereas Hyland provided the engineering credentials, Madigan lent a penchant for developing rewarding business relationships (none more so than with Moses) and an eye for identifying, and hiring, talented engineers. 84 Spotlight Alumni, The Notre Dame Alumnus 21, no. 4 (April 85 Robert E.

Murphy, After Many a Summer: The Passing of the Giants and Dodgers and a Golden Age in New York Baseball (New York: Sterling, 86 Historical Vignette 001 How the Military Construction Mission Began for the Corps of Engineers, U.S. Army Corps of Engineers, accessed April 7, 87 Spotlight Alumni. TAPPAN ZEE BRIDGE HAER No. (Page 16) Thanks in large part to Madigan s relationship with Moses, the firm was able to secure favor with the forty-seventh Governor of New York, Thomas E. Dewey. Madigan-Hyland was selected as a primary contractor for the ambitious project of building a high-speed, limited access highway between New York City and Buffalo, the New York State Thruway. Spearheaded by Governor Dewey, the project was overseen by the newly created NYSTA.

Immediately, the firm was employed to conduct a survey of existing traffic along the proposed 550-mile highway and create estimates of the volume of future traffic. Ultimately, Madigan-Hyland won the contract to be the chief consulting engineers for the construction of the entire Thruway. This contract propelled Madigan-Hyland to receive their most famous commission, the design of an approximately 3-mile span across the Hudson River known as the Tappan Zee Bridge. 88 The man in charge of the day-to-day construction of the Tappan Zee Bridge was Harold W. Knox. A graduate of RPI with a degree in civil engineering, Knox was Madigan-Hyland s chief field engineer.

An advocate for the use of cutting-edge technology in the construction phase of the new bridge, Knox utilized a theodolite to ensure precision in locating the buoyant concrete caissons so the bridge s steel super structure would fit properly across the long span. 89 Madigan-Hyland s chief designer was engineer Emil H. Praeger, also another RPI graduate and one- time head of RPI s civil engineering program. Praeger also was acquainted with Robert Moses, and worked on bridge and expressway projects throughout New York State and New York City through the connections made with Moses and Madigan-Hyland.

He is best known for his innovative buoyant concrete caisson design for the Tappan Zee Bridge, which further developed the use of buoyant caissons from his Pier 57 along the Hudson River in Manhattan, another Madigan-Hyland project. 90 On the Tappan Zee Bridge project, Praeger worked closely with Harold Knox in particular. Praeger also operated his own company, Praeger & Maguire, which was responsible for the Truman administration s renovation of the White House, as well as construction of the United Nation s General Assembly Hall and underground parking structure In September of Hyland died at the age of 57, three years before the first automobile crossed the Tappan Zee Bridge.

Madigan continued as the firm s principal, while also devoting his talents as the World Bank s chief engineer for much of the and 91 Following completion of the Tappan Zee Bridge, Madigan-Hyland served as consulting engineers for the Brooklyn Sports Center Authority in conjunction with the president of the Brooklyn Dodgers, Walter O Malley. The firm prepared a report comparing the improvement of a site for a new baseball stadium in New York City versus two potential sites in Los Angeles.

In following their report, as well as a political fracas between Moses and O Malley, the Brooklyn Dodgers moved to Los 88 Wolf, Crossing the Hudson, 185 89 Engineers Receive Rare Survey Instrument, The Times Record [Troy, New York], March 8, 90 Praeger was granted a patent in for an apparatus for molding concrete walls. Emil H. Praeger, Apparatus for molding concrete walls, U.S. Patent 2598830A, filed December 29, and published June 3, 91 Alfred E. Clark, Michael J. Madigan, 86 Dies; Was a Robert Moses Engineer, New York Times, October 26, TAPPAN ZEE BRIDGE HAER No. (Page 17) Angeles to become the Los Angeles Dodgers. 92 The designer of the new Dodger Stadium in Los Angeles as well as Shea Stadium in Queens was Emil Praeger.

By this point, Praeger s firm had changed its name to Praeger-Kavanagh-Waterbury. Praeger s firm also worked on the Hawkins Point Floating Bridge over the St. Lawrence River and the Gowanus Expressway expansion Praeger s son, Richard, a Princeton and New York University graduate with a degree in civil engineering, served as the company s supervisor of construction. 93 Madigan and Emil Praeger joined forces once again in a joint business named Madigan-Praeger, Inc., formed from Madigan-Hyland and Praeger-Kavanagh-Waterbury. In Madigan retired, leaving Richard Praeger to serve as the principal partner of the engineering conglomerate, which in acquired Coverdale & Colpitts, Inc., a firm specializing in financial and economic studies in transportation and heavy industry.

94 Madigan-Praeger was affiliated with, and subsequently acquired by URS Corporation in During the URS/Madigan-Praeger (later dissolved into URS) was awarded a million contract for the design and technical supervision of a major addition to the New York subway system. 95 The firm also constructed a large water pollution facility in New York. In URS was acquired by AECOM. 7. Emil Praeger, Chief Design Engineer: Emil Praeger was a notable early to mid twentieth-century civil engineer responsible for many engineering innovations and landmarks, several involving concrete and caisson construction. Praeger was born in in New York City. After graduating from RPI in with a degree in civil engineering and serving as an officer of the U.S.

Navy Civil Engineer Corps during World War I, Praeger worked as chief engineer with the noted architecture firm of Bertram Goodhue during the He contributed his structural engineering expertise to many projects, including the Nebraska State Capitol the Central Branch Building of the Los Angeles Public Library the University of Chicago Rockefeller Chapel and the Church of the Heavenly Rest in New York City 96 In he joined the firm of Madigan-Hyland, focusing on bridge and road projects.

For Madigan-Hyland, he served as chief engineer for the Henry Hudson Parkway He also served as the chief engineer for the New York City Department of Parks when the boroughs merged their park programs into a city-wide department in 97 Praeger was associated with master builder Robert Moses, who was head of the New York City Parks Department under Mayor Fiorello H. La Guardia and with whose influence Praeger completed many projects. Along with his engineering work for Madigan-Hyland, Praeger acted as the head of RPI s civil engineering department from to 92 The New York Giants also relocated from New York City, moving to San Francisco to become the San Francisco Giants. O Malley encouraged the Giants majority owner, Horace Stoneham, to relocate to the West Coast.

93 Vincent Butler, All-Purpose Stadium Being Built in New York, Chicago Tribune, January 12, 94 URS Reports Stock Deal, The Times [San Mateo, California], November 25, 95 New York Transit Concern Adds Black Vice President, JET, November 25, 18. 96 Dorothy O Keeffe, Brooklyn s Man of the Week: Fulfills Classmates Prophecies, Brooklyn Daily Eagle, September 20, 97 Elizabeth Mitchell and Kathrine Reed, Henry Hudson Parkway, HAER No. Historic American Engineering Record (HAER), National Park Service, U.S. Department of the Interior, p. 55. 98 Emil H. Praeger, Foundation Problems, General Design and Structural Features Nyack-Tarrytown Bridge, Municipal Engineers Journal 41, no. 137 Alpha Chapter of Theta Xi, Emil H. Praeger, accessed October TAPPAN ZEE BRIDGE HAER No.

(Page 18) At the outbreak of World War II, Praeger was commissioned as a Navy captain and headed the Design Section of the Civil Engineer Corps. While aiding the British and American forces, Praeger took part in OPERATION MULBERRY, the ambitious operation that created portable artificial harbors off Omaha Beach and Gold Beach to move Allied troops and supplies for the Battle of Normandy. 99 Praeger was Design Manager for the Navy Bureau of Yards and Docks and was part of the team that created the Phoenix units, floating concrete caissons that provided the foundation for the temporary harbors. 100 This work served as the foundation for his use of buoyant caissons in his Pier 57 and Tappan Zee Bridge designs.

He also served as part of the Navy group that surveyed the damage caused by atomic bombs in Nagasaki and Hiroshima. Praeger s service earned him the Legion of Merit Medal. 101 In Praeger also started his own engineering firm, Praeger & McGuire. He served as consulting engineer for the Truman administration White House renovation and the United Nations General Assembly Hall and underground parking structure 102 During the early Praeger adapted the concept of floating or buoyant caissons from the Phoenix units at Normandy for substructures for piers and bridges.

With a specialty for concrete construction, he applied for a patent for an apparatus for molding concrete walls in December which was issued as Patent in June 103 His New York City Pier 57 and the Tappan Zee Bridge incorporated the buoyant caisson technology from the Phoenix units.

Pier 57 on the Hudson River between and Streets in Manhattan was a passenger/freight pier that rested on three massive concrete caisson boxes which in turn rested on timber piers and gravel from the previous Pier 47 that had burned in The Pier 57 design was announced in and its construction was completed in September That same year, Praeger, as engineer with Madigan- Hyland, took the buoyant caisson design further in his design for the Tappan Zee Bridge across the Hudson River between South Nyack/Grand View and Tarrytown, New York. The buoyant caissons supported the majority of the weight of the bridge s main span, and thereby solved the location s problematic geology and also lowered the overall bridge construction costs.

The Pier 57 design earned Praeger the first annual Metropolitan Engineer of the Year Award in from the New York City Metropolitan Section of the American Society of Civil Engineers and the Architecture League s Gold Medal for Engineering. He also received honorary Doctor of Engineering degrees from RPI, Manhattan College, and St John s University. 104 With the addition of structural engineer Thomas Kavanaugh in Praeger s own firm changed its name to Praeger-Kavanaugh and eventually became Praeger-Kavanaugh-Waterbury when architect John Waterbury joined the firm in the early As a partner in Praeger-Kavanaugh-Waterbury, Praeger worked on the Hawkins Point Floating Bridge over the St.

Lawrence River and the 99 Alfred Stanford, Force Mulberry: The Planning and Installation of the Artificial Harbor off U.S. Normandy Beaches in World War II (New York: William Morrow and Co., 100 Wolf, Crossing the Hudson, 181 101 Praeger, Engineer, Dead at 81, Watertown Daily News (Watertown, October 17, 102 Donald M. Burmister, Foundation Studies for the White House, Columbia Engineering Quarterly, March Praeger, Engineer, Dead at 81. 103 Emil H. Praeger, Apparatus for molding concrete walls, U.S. Patent 2598830A, filed December 29, and published June 3, 104 E. H. Praeger to Receive RPI Award, Times Record (Troy, January 29, TAPPAN ZEE BRIDGE HAER No.

(Page 19) Gowanus Expressway expansion He applied his expertise and interest in concrete construction to baseball stadium design, and established himself as an important baseball stadium designer. 105 In he patented a moveable roof system for stadiums and designed Dodger Stadium in Los Angeles and Shea Stadium in New York 106 In Praeger-Kavanaugh- Waterbury merged with URS, the same year Praeger received RPI s Distinguished Service Award. 107 Emil Praeger died on October 16, at the age of 81 in Manhasset, New York. 108 He was posthumously named one of ten inductees in the inaugural class of the RPI Hall of Fame, created in to recognize RPI graduates who made outstanding contributions to their field or humanity as a whole. 109 Part II. Structural/Design Information A. General Statement: 1.

Character: The Tappan Zee Bridge stands as an innovative design solution to a number of challenges: geology, geography, cost, and politics. Madigan-Hyland s chief designer, Emil Praeger, adapting techniques he used in World War II as part of the U.S. Navy s Civil Engineer Corps, designed a system of buoyant caissons to help alleviate stress on piers that did not meet bedrock until below the Hudson River. Dividing the 3.1-mile-long bridge into five sections addressed geologic demands, and also allowed the NYSTA to build the bridge at its chosen location: at a very wide crossing, and beyond the Port of New York Authority s jurisdiction. Because the NYSTA was able to incorporate the bridge into its Thruway system, tolls collected were able to help fund the bridge s ongoing maintenance.

Initial construction costs were also reduced by opting for a conventional cantilever truss central section, as opposed to the more traditionally aesthetic but also more expensive, tied-arch span design initially proposed. The cantilever span is the ninth largest of its type in the world. 2. Condition of fabric: Due to the ever-increasing volume and weight of traffic crossing the Tappan Zee Bridge, maintenance and repairs since its opening in have been considerable. Ongoing scheduled inspections revealed girder corrosion and buckling, cracks in reinforced concrete piers, and footing deterioration on steel bearings, up to 40 percent loss in areas.

The cumulative effects of traffic volume, age, and functional and economic efficiency predicated the decision to replace the original Tappan Zee Bridge. Construction on the new bridge just to the north of the original bridge began in 105 Renowned Engineer to Receive Distinguished Service Award, Rensselaer Alumni News, August 3. 106 Emil Praeger, Roof system for stadia and the like. U.S. Patent Filed October 28, and published July 20, 107 E. H. Praeger to Receive RPI Award. 108 Praeger, Engineer, Dies at 81 ; This Month in Walter O Malley History - October 16, Walter O Malley Official Website, accessed October 109 The Rensselaer Alumni Hall of Fame, Rensselaer Alumni Magazine, June 10 13. TAPPAN ZEE BRIDGE HAER No. (Page 20) B. Description: 1.

General description: The Tappan Zee Bridge is an approximately 3.1-mile-long bridge that spans the Hudson River from South Nyack/Grand View, Rockland County, on its west to Tarrytown, Westchester County, on its east. It has an S-shape configuration and carries I-87/287, the New York State Thruway. With a roadway width of the bridge currently has seven traffic lanes. The center lane can be configured to accommodate traffic in either direction, based on traffic volume during peak usage. The bridge was designed originally with six traffic lanes and a 10' curb-height median. Initial reconfiguration of the lanes took place in with a movable barrier installed in to facilitate the center-lane transition between eastbound and westbound flow.

Proceeding from west to east, the bridge has five sections. The Causeway (West Trestle) is an long concrete deck supported by a substructure of steel stringers and reinforced concrete piers resting on timber pilings. The West Deck Truss (approximately long) incorporates seven Warren truss spans each) set on steel stringers and reinforced concrete piers that rest either on cylindrical cofferdams or buoyant caissons (four eastern piers) above steel piles and rock. The Main Spans long) include two cantilever spans each) flanking a suspended center span with two side spans each), all supported by steel piers and buoyant caissons on steel piles.

The East Deck Truss (approximately long) has thirteen Warren truss spans each) supported by steel stringers and reinforced concrete piers on circular cofferdams. The comparatively short East Trestle (approximately long) has six spans each) supported by steel stringers and concrete piers on rock. Continuing past the east abutment, the Tarrytown-bound lanes open to a ten or twelve lane toll plaza, depending on the time of day and traffic volume. 2. Substructure: The substructure of the Tappan Zee Bridge consists of west and east concrete abutments, reinforced concrete bents, steel piers, cofferdams, and buoyant caissons, in addition to timber and steel pilings.

Bents (including the Main Spans steel piers) are numbered west to east, Bents 1 through with no Bent 174 or The Causeway includes the reinforced concrete west abutment and Bents 1 through with each bent spaced 50' apart and resting on timber friction piles. The height of each bent unit varies with geology of the river bottom and the slight incline of the Causeway deck. Each unit is supported by seventy-five untreated, peeled piles of Douglas fir that extend to approximately 85' below mean low water levels. These piles have a total load of approximately tons. Each pile is protected by timber fenders and icebreakers composed of piles wrapped with steel sheeting and wire rope reinforcing.

Each West Deck Truss bent comprises two hollow reinforced concrete box piers joined at the top by a reinforced collar. Spans are approximately 250 . Each pier varies slightly in height to accommodate the 3 percent grade increase of the roadway and the depth of the river bottom. Bents 166 through 168 are supported by solid concrete, circular cofferdams, anchored either directly to rock or steel H-piles that are then anchored to rock. Steel sheet piling used to enclose the cofferdams during construction remains in place. Bents 169 through 172 have buoyant caisson foundations to relieve most of the load on the piers in this area of the river, due to the depth of the bedrock.

Each caisson is a reinforced concrete, hollow box x 56' x 40' (length x width x height) with a solid slab floor and top. The walls of the caissons, both exterior and interior, have round fittings into which the 14" H-piles were installed after the caissons were sunk. The piles extend to solid rock, and help to stabilize the caisson and support the pier weight. The caissons and piers are protected by timber fenders and icebreakers. For more information on how caissons work and caisson construction, see Section 5: Significant Engineering and Construction Processes. TAPPAN ZEE BRIDGE HAER No. (Page 21) The Main Spans include Bents 173 through all of which have buoyant caisson foundations. Supporting the massive cantilever and suspended trusses, piers in this section of the bridge are steel.

The two smaller anchor bents at the side spans (Bents 173 and sit on mid-sized buoyant caissons, approximately x 77' x 40' each. The cantilever sections of the Main Spans (Bents 175 and are supported by steel piers (or towers) that sit on large-sized buoyant caissons, x x All caissons in the Main Spans section were secured using steel pipe piles inserted through the caisson walls and driven into rock. To stabilize the caissons even further, the pipes were cleaned and filled with concrete, and then concrete was poured into the caisson walls at the pipe insertion point. Caissons and piers are also protected with a pile fender system and icebreakers, updated in The East Deck Truss includes Bents 179 through each spaced approximately apart.

The East Deck Truss has the same type of substructure components as the West Deck Truss, described above. The East Trestle comprises Bents 192 through 197 and the reinforced-concrete east abutment. East Trestle bents feature both round and rectangular reinforced concrete piers, all anchored into the rock escarpment at the river s edge. 3. Superstructure: The bridge s superstructure consists of the cantilever through truss spans, simple Warren deck truss approaches, and the steel girder-supported concrete deck, as well as guardrails, lighting, and drainage systems. The cantilever trusses have diagonal chord members that echo a subdivided Warren-type truss form.

The center span including the cantilevers is long, and its anchor spans are each approximately for a total length of approximately making it the ninth largest span of its type in the world. Each cantilever arm is long, and the suspended span has a length of A hinge and pendulum connect the suspended arm to the cantilever sections. The upper and lower chords of this center span are made of carbon steel. There is of vertical clearance above the mean low water from the center of the low cantilever truss. Two hundred roadway expansion joints allow for movement of the bridge. The concrete and asphalt roadway of the Tappan Zee Bridge is 91' wide. 4.

Modifications: The Tappan Zee Bridge has had modifications for maintenance, including replacement of its roadway deck, but its essential character-defining features remain intact. The original roadway surface was constructed as a concrete slab covered with small slabs of asphalt assembled like a tile floor. Because salts were seeping into the concrete slab, in the west half of the roadway was resurfaced with asphalt concrete and topped first with a sealing coat of tar, then with rough sand for traction. 110 The east half of the bridge was resurfaced thereafter. The bridge s open gutter system was eventually closed to prevent the salts from draining onto the steel members. In December a steel guide rail was added to the median for additional safety.

111 110 Tappan Zee Bridge to be Resurfaced, New York Times, April 8, 23. 111 New York State Thruway Authority, Annual Report, 14. TAPPAN ZEE BRIDGE HAER No. (Page 22) In the center median was removed in order to add a seventh traffic lane at a cost of more than $28 million. 112 The southbound lanes accounted for of the roadway with four 12' wide traffic lanes, and the three northbound lanes accounted for also with 12' wide lanes. A center barrier remained. 113 At the same time, the number of toll booths increased from ten to thirteen, all on the southbound side. In a $20 million project expanded the west approach to four lanes, again by reconfiguring the median, reducing or removing shoulders, and reducing lane width.

114 In February a movable barrier was installed on the bridge that allowed for changing the direction of the center lane to accommodate the direction of the morning or evening rush hour. This required demolition of the existing median, construction of a garage for the movable barrier vehicle, electrical upgrade, and reconfiguring the center lane crown and joints. During the morning rush hour, there would be four eastbound lanes, and then the barrier would move to the south and create four westbound lanes during the afternoon rush hour. That August, an E-Z Pass electronic toll-collection system was installed.

In June a million project was initiated to replace and rehabilitate portions of concrete bridge deck between Rockland and the Main Spans, completed in December In August a two-year, million project was initiated to replace the Westchester County-side deck. In October the NYSTA announced a two-year, million project to replace a large portion of the Rockland County-side deck in 5. Significant Engineering and Construction Processes: The eight buoyant caissons were designed by Emil Praeger to carry 70 to 80 percent of the dead load of the bridge, with the remainder carried by the piers. Corbetta Construction Company (Corbetta) fabricated the caissons in a construction pit at West Haverstraw about 12 miles north of the bridge site.

Corbetta also worked with Praeger on his Pier 57 design in New York City, which was his earlier civilian use of buoyant caisson foundations, after building temporary harbors for the U.S. Navy during World War II. Corbetta constructed the caissons for Merritt-Chapman & Scott, general contractor for the Tappan Zee Bridge s east and deep water foundations. Merritt-Chapman & Scott was responsible for installing the caissons, which included floating the boxes downriver from their fabrication location to their bridge site, flooding them, and then inserting the piles through the caissons down to solid bedrock.

115 As the Hudson River channel between the fabrication pit upriver and the bridge site had a limiting depth of the roofs and top sections of the caisson walls were installed at their permanent locations at the bridge site rather than in the construction pit. 116 The bridge superstructure was fabricated and erected by the American Bridge Company, a division of U.S. Steel. It was erected without any additional temporary foundation supports. Large steel falsework structures, each 16' high, supported construction of the cantilever span, anchor spans, and the steel tower piers tall). The cantilever trusses and one-half of the suspended span were 112 Dimensions given are from outside curb to outside curb according to Drawing TANY-85-49B-18R.

113 Reconfiguration of the roadway for the seventh traffic lane was carried out under NYSTA contract TANY-85- Dimensions are from Drawing TANY-85-49B-18R by N. H. Bettigole, PC. Consulting Engineer, New York, New York, dated October 31, 114 Brooke, On the Tappan Zee, Time to Unclog the 3-Mile Jam. 115 Building Big Buoyant Boxes for Bridge Substructure, Engineering News-Record, July 11, 33 37. 116 Praeger, Foundation Problems, General Design and Structural Features. TAPPAN ZEE BRIDGE HAER No. (Page 23) erected continuously from each tower until they reached the center. The suspended span was disconnected from the top chord of the cantilever trusses once the truss system was joined.

Construction methods that proved advantageous in the earlier caisson construction at Pier 57 were incorporated into the Tappan Zee Bridge construction process. Similar concrete materials and quantities were used and, with only six bags of cement, strengths up to at seven days and up to at twenty-eight days were obtained. Emphasis was placed on uniformity, density and general quality, however, rather than strength alone. Concrete was placed with low slumps, vibrated, cured with water, and then a curing compound consisting of asphalt and aluminum was applied.

(The aluminum was mixed with the asphalt before applying and served to reflect the heat of the sun.) Both vertical and horizontal pours terminated in cold joints and these, as well as shrinkage cracks, were sealed with a Neoprene process that was developed specifically for the Tappan Zee Bridge project. Reinforcing steel up to 2" square bars were spliced by the Thermit Weld process (exothermic, chemical), often used for railroad construction, instead of the Union Melt method (electrical current) that was used at Pier 57. 117 C. Site Information: The site of the bridge was determined and defined by history and politics, regional transportation infrastructure, and unusual geology, as discussed in the Historical Context.

Since the bridge has been a prominent component of the Hudson River viewshed. Crossing the river at its second-widest point, the bridge serves as a visual landmark for water, road, rail, and air traffic, as well as those traveling along both east and west banks of the river. The Tappan Zee Bridge carries I-87/287 and crosses the Hudson River between South Nyack, Rockland County, New York, and Tarrytown, Westchester County, New York. In that vicinity, the river is approximately 2.8 miles wide. 118 On its west side, the bridge is approximately 0.3 mile south of South Nyack s town center. On its east side, the bridge is 0.4 mile south of downtown Tarrytown and 1.8 miles north of the village of Irvington.

The jurisdictional line between Rockland County and Westchester County is the middle of the Hudson River, thus the west half of the bridge is in Rockland County and the east half is in Westchester County. The Main Spans are entirely in Westchester County. The banks on both sides of the Hudson River at the bridge crossing have a grade of less than 15 percent. West of the Thruway, the grade rises to 15 to 25 percent. Further west, the topography rises sharply to the Palisades ridge, with an elevation of approximately at a distance of approximately mile from the river. East of the river, the grade increases to approximately 26 percent. The depth of the river bottom varies along the bridge. At the main crossing, the river bed is 40' below the river surface.

119 The river bed surface is composed primarily of organic silt and silty clay with thickness varying from 10' to to underlying bedrock. The channel deposits contain inclusions of sand, shell, and decayed organic deposits. The western portion of the riverbed consists of an ancient channel of the Hudson filled with thick deposits of glacial till. The eastern portion consists of silty 117 Praeger, Foundation Problems, General Design and Structural Features. 118 Grutzner, Over the Hudson: Tappan Zee Bridge Has Had Checkered Past. 119 Praeger, Foundation Problems, General Design and Structural Features. TAPPAN ZEE BRIDGE HAER No. (Page 24) clay over thick deposits of glacial silts and clays. Bedrock is located 60' below mean sea level at the west shore, but drops to under the Causeway.

Bedrock is approximately 220 below at the center of the river. 120 On the west side of the Hudson River, the bridge s Causeway section extends above the west river bank and Piermont Avenue/River Road in the northernmost section of Grand View-on-Hudson to the west abutment. Piermont Avenue/River Road is a paved, two-lane road that runs along the river and accesses a wooded residential neighborhood of single-family houses south and west of the bridge (pre-dating the bridge). At the river s edge immediately north of the bridge and just east of Piermont Avenue is a service area with maintenance equipment and the Tappan Zee Bridge s service boat.

Farther north of this service area are three three-story apartment buildings and four eight-story apartment towers (all built post-bridge construction) surrounded by asphalt parking lots and landscaping. West of Piermont Avenue, the Thruway heads northwest and passes under South Broadway, the Raymond G. Esposito Memorial Trail (gravel path), and U.S. 9W. The large and circular U.S. 9W/Thruway interchange has on-ramps and off-ramps that also pass above the Thruway. From this interchange, the Thruway continues northwesterly to the village of Suffern along a natural cut in the high Palisades.

On the east side of the Hudson River in Tarrytown, the bridge extends approximately 70' above the east bank of the river, spanning the tracks constructed by the New York Central Railroad, operated by New York s Metropolitan Transportation Authority as part of the Metro North commuter line since A small access road north of Van Wart Avenue passes under the bridge approach just west of the east abutment. East of the bridge s ten-lane southbound toll plaza, the Thruway passes under South Broadway/U.S. 9. In this vicinity, on- and off-ramps transition traffic between the bridge, South Broadway, and other local streets. The NYSTA s service area is located immediately northeast of the toll plaza. This paved area includes the bridge headquarters and a small maintenance building.

Barracks for the New York State Police s Troop T barracks were located in this area, but were demolished in April so the area could be used as a staging area for the new Tappan Zee Bridge construction. Northwest of the headquarters building is a small building that houses traffic monitoring equipment and other bridge-related operations. Farther north, beyond the bridge s service area is a commercial office complex and multifamily residential buildings (built post-bridge construction). South of the toll plaza is a neighborhood of single-family houses (most pre-date bridge construction). Approximately 1.4 miles east of the toll plaza, the Thruway splits into I-87 South and I-287 East.

The New York State Thruway ends at the Westchester County line in Yonkers and I-87 becomes the Major Deegan Expressway, extending south through the Bronx. Both roads provide access to the Saw Mill River Parkway. I-287 becomes the Cross Westchester Expressway and provides access to the Sprain Brook Parkway and the Hutchinson Parkway before terminating at Interstate 95/New England Thruway in Rye, New York. 120 Federal Highway Administration, Topography, Geology, and Soils, chap. 14 in Final Environmental Impact Statement and Final 4 (f) Statement for the Tappan Zee Hudson River Crossing, Interstate Rockland and Westchester Counties, New York (Washington, Federal Highway Administration, TAPPAN ZEE BRIDGE HAER No. (Page 25) Part III. Sources of Information A. Archival

Sources

2011 words

Source document Quoted word for word from HAER NY-556. Not written, edited or summarised by this site.

Benezra, Karen. Tarrytown Officials Vow Bridge Fight. [clipping from unidentified newspaper.] June 16, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Bridge. [clipping from unidentified newspaper.] no date. Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Brooke, James. On the Tappan Zee, Time to Unclog the 3-Mile Jam. New York Times, April 11, B1. Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Clary, Greg. 100 in Tarrytown Protest Tappan Zee Plan. Journal News, April 16, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. . Experts Join Forces to Study TZ Options. Journal News, April 24, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. . Tappan Zee Bridge Proposal Criticized Again.

Journal News, May 19, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Clary, Greg, and Bill Varner, Panel Favors New TZ Bridge. Journal News, January 12, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Fitz-Gibbon, Jorge, and Bruce Golding. 6 Plans Vie for TZ Future. Journal News, September 30, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Gallagher, Jay, and Cara Matthews. State Eyes Feds to Share TZB Cost. Journal News, September 28, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Hazell, Nadene. Rockland Finds Bridge Is a Help and Hindrance. Journal News, July 13, A1. Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Incalcaterra, Laura.

$4B TZ Bridge Plans Delivered to Governor. Journal News, April 20, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Journal News. Hints of a future TZB/I-287 corridor take shape. March 2, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. . Still No Money. November 24, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Martin, Neil S. The Rockland Connection. Tarrytown Daily News, December 14, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Merchant, Robert. Neighbors Rally in Opposition to Replacing Tappan Zee Bridge. The Journal News, April Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. TAPPAN ZEE BRIDGE HAER No.

(Page 26) Rails Could Make New Tappan Bridge Acceptable at the Same Location. [Clipping from unidentified newspaper.] July, 20, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Saeed, Khurram. Deadline Nears for Opinions on TZB Plans. Journal News, March 30, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. . Paterson Called on to Reverse TZB Process. Journal News, April 1, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Train Station under TZ Toll Barrier Could Ease Thruway, Tarrytown Traffic. [Clipping from unidentified newspaper.] April 18, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Varner, Bill, and Greg Clary. TZ Opposition Swells on Both Sides of Hudson.

Journal News, January 17, Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. Weiner, Randi. Bridge Ended Tarrytown s Tranquility. Journal News, October 29, 8A. Tappan Zee Bridge Vertical File. Warner Library, Tarrytown, New York. B. Newspapers: Butler, Vincent. All-Purpose Stadium Being Built in New York. Chicago Tribune, January 12, Accessed via Chicago Tribune Archives Clark, Alfred E. Michael J. Madigan, 86 Dies; Was a Robert Moses Engineer. New York Times, October 26, Accessed via ProQuest Historical Newspapers: The New York Times DeChillo, Suzannne. Lights on Tappan Zee Celebrate 35 Years. New York Times, December 16, Accessed via ProQuest Historical Newspapers: The New York Times Grutzner, Charles. Over the Hudson: Tappan Zee Bridge Has Had Checkered Past.

New York Times, June 20, Accessed via ProQuest Historical Newspapers: The New York Times Ingram, Josheph C. Thruway Opened With Dedication of Last Toll Link. New York Times, December 16, Accessed via ProQuest Historical Newspapers: The New York Times Neuman,William. State to Replace, Not Rebuild, Tappan Zee Bridge. September 26, Accessed via ProQuest Historical Newspapers: The New York Times New York Times. A Self-Financed Thruway. February 14, 24. Accessed via ProQuest Historical Newspapers: The New York Times . Big Thruway Span Approved by Army. May 3, 31. Accessed via ProQuest Historical Newspapers: The New York Times . Bridge Fight Organized. October 11, Accessed via ProQuest Historical Newspapers: The New York Times TAPPAN ZEE BRIDGE HAER No. (Page 27) .

Bridge in Port Area Urged for Thruway. March 13, Accessed via ProQuest Historical Newspapers: The New York Times . Bridge War Grows in Hudson Valley. September 13, Accessed via ProQuest Historical Newspapers: The New York Times . Businesses Thriving in Rockland. January 24, ProQuest Historical Newspapers: The New York Times Accessed via ProQuest Historical Newspapers: The New York Times . Dewey is Adamant on Thruway Span. May 8, Accessed via ProQuest Historical Newspapers: The New York Times . Hudson River Bridge for Thruway Voted. March 15, ProQuest Historical Newspapers: The New York Times Accessed via ProQuest Historical Newspapers: The New York Times .

Low Bid Received on Thruway Span: Tallamy Predicts Completion of Disputed Tappan Zee Bridge by Fall of April 17, Accessed via ProQuest Historical Newspapers: The New York Times . New Bridge Crowded: Tappan Zee Span Gets First Sunday Traffic Workout. December 19, Accessed via ProQuest Historical Newspapers: The New York Times . New Thruway Study is Ordered by State. March 28, Accessed via ProQuest Historical Newspapers: The New York Times . Nyack Bridge Plan Dropped by Board. November 20, 25. Accessed via ProQuest Historical Newspapers: The New York Times . Photo Standalone 4 No Title. December 21, Accessed via ProQuest Historical Newspapers: The New York Times . Predicts Thruway Will Enrich State. April 25, 25. Accessed via ProQuest Historical Newspapers: The New York Times . Proposals.

December 10, Accessed via ProQuest Historical Newspapers: The New York Times . Rockland Women Rout Bridge Aides. September 12, 19. Accessed via ProQuest Historical Newspapers: The New York Times . Site is Selected for Thruway Span. December 8, 31. Accessed via ProQuest Historical Newspapers: The New York Times . State Thruway. April 26, 26. Accessed via ProQuest Historical Newspapers: The New York Times . Tappan Zee Bridge Called Error : Span Held Unsightly, Costly . January 2, Accessed via ProQuest Historical Newspapers: The New York Times TAPPAN ZEE BRIDGE HAER No. (Page 28) . Tappan Zee Bridge May Be Replaced. July 17, Accessed via ProQuest Historical Newspapers: The New York Times . Tappan Zee Bridge to be Resurfaced . April 8, 23.

Accessed via ProQuest Historical Newspapers: The New York Times . Tappan Zee Span for Thruway Seen. April 27, 44. Accessed via ProQuest Historical Newspapers: The New York Times . That Thruway Bridge. May 10, Accessed via ProQuest Historical Newspapers: The New York Times . Thruway Near Reality. July 7, Accessed via ProQuest Historical Newspapers: The New York Times . Thruway Span Gains: Work to Begin Soon on Section of Tappan Zee Bridge. August 8, Accessed via ProQuest Historical Newspapers: The New York Times . Thruway Work to Start. April 26, Accessed via ProQuest Historical Newspapers: The New York Times . Work on Thruway Started by Dewey. July 12, Accessed via ProQuest Historical Newspapers: The New York Times O Keeffe, Dorothy.

Brooklyn s Man of the Week: Fulfills Classmates Prophecies. Brooklyn Daily Eagle, September 20, Accessed via Brooklyn Newstand (joint initiative between Brooklyn Public Library and Newspapers.com). Pierce, Bert. Automobiles Thruway: Buoyant Caissons to Be Used to Support Three-Mile Bridge Across Hudson. New York Times, November 2, Accessed via ProQuest Historical Newspapers: The New York Times Times [San Mateo, CA]. URS Reports Stock Deal. November 25, Accessed via Newspapers.com. Times Record [Troy, E. H. Praeger to Receive RPI Award. January 29, Accessed via Newspapers.com. . Engineers Receive Rare Survey Instrument. March 8, Accessed via Newspapers.com. . Thruway Tolls For May Increased by Nearly 60 Per Cent. June 14, 34. Accessed via Newspapers.com.

Watertown Daily News [Watertown, Praeger, Engineer, Dead at 81. October 17, Accessed via Newspapers.com. Weaver, Warner, Jr. Big Thruway Span Approved by Army: Action Clears the Last Legal Obstacle to Construction of Bridge Over Hudson. New York Times, May 3, Accessed via ProQuest Historical Newspapers: The New York Times TAPPAN ZEE BRIDGE HAER No. (Page 29) C. Books and Journals: Burmister, Donald M. Foundation Studies for the White House. Columbia Engineering Quarterly 5, no. 3 (March 13. Engineering News-Record. Tappan Zee Bridge: A Foundation Triumph. April 14, . Building Big Buoyant Boxes for Bridge Substructure. July 11, Federal Highway Administration. Final List of Nationally and Exceptionally Significant Features of the Federal Interstate Highway System. Issued November 1, .

Topography, Geology, and Soils. Chapter 14 in Final Environmental Impact Statement and Final Statement for the Tappan Zee Hudson River Crossing, Interstate Rockland and Westchester Counties, New York. Klein, Melissa, and Greg Clary. A Bridge too Crowded: Region s Biggest Span Struggles under Red Tape, Population Growth. Tappan Zee Bridge: A Weakening Link, October 29, JET. New York Transit Concern Adds Black Vice President. November 25, 18. Murphy, Robert E. After Many a Summer: The Passing of the Giants and Dodgers and a Golden Age in New York Baseball. New York: Sterling, New York State Thruway Authority. New York State Thruway Authority Annual Report Albany, NY: New York State Thruway Authority, . New York State Thruway Authority Annual Report.

Albany, NY: New York State Thruway Authority, . First Annual Report of the New York State Thruway Authority. Albany, NY: New York State Thruway Authority, . Second Annual Report. Albany, NY: New York State Thruway Authority, . Fifth Annual Report. Albany, NY: New York State Thruway Authority, . Sixth Annual Report. Albany, NY: New York State Thruway Authority, . Ninth Annual Report. Albany, NY: New York State Thruway Authority, . Annual Report. Albany, NY: New York State Thruway Authority, . Annual Report. Albany, NY: New York State Thruway Authority, . Annual Report. Albany, NY: New York State Thruway Authority, . Annual Report. Albany, NY: New York State Thruway Authority, . Annual Report. Albany, NY: New York State Thruway Authority, TAPPAN ZEE BRIDGE HAER No. (Page 30) . Annual Report.

Albany, NY: New York State Thruway Authority, . Annual Report. Albany, NY: New York State Thruway Authority, The Notre Dame Alumnus. Spotlight Alumni. Volume 21, No. 4 (April Rensselaer Alumni News. Renowned Engineer to Receive Distinguished Service Award. August Rensselaer Alumni Magazine. The Rensselaer Alumni Hall of Fame. June Praeger, Emil H. Foundation Problems, General Design and Structural Features Nyack-Tarrytown Bridge. The Municipal Engineers Journal 41, no. 3 137 Stanford, Alfred. Force Mulberry: The Planning and Installation of the Artificial Harbor off U.S. Normandy Beaches in World War II. New York: William Morrow and Co., Tappan Zee Bridge: A Weakening Link. Tappan Zee Bridge by the Numbers. October 29, Tappan Zee Bridge Dedication Committee.

Tappan Zee from the Half Moon to the Bridge. Tarrytown, New York: Tappan Zee Bridge Dedication Committee, Wolf, Donald D. Crossing the Hudson: Historic Bridges and Tunnels of the River. New Jersey: Rivergate Books, D. Online Alumni of the Alpha Chapter of Theta XI. Emil H. Praeger; Alpha Accessed October NYCRoads.com. New York State Thruway: Historic Overview. Accessed April 17, . Tappan Zee Bridge: Historic Overview. Accessed October 14, New York State Thruway. Frequently Asked Questions (FAQs). Accessed October Risinit, Michael. Tappan Zee: A Bridge to a New Era. Lohud.com. Accessed October The Upstate New York Roads Site. The New York State Thruway: The Beginning. Accessed October U.S. Army Corps of Engineers.

Historical Vignette 001 How the Military Construction Mission Began for the Corps of Engineers. Accessed April 7, sofEngineers.aspx. TAPPAN ZEE BRIDGE HAER No. (Page 31) Walter O Malley The Official Website. This Month in Walter O Malley History - October 16, Accessed October E. Additional Mitchell, Elizabeth, and Kathrine Reed. Henry Hudson Parkway. HAER No. Historic American Engineering Record (HAER), National Park Service, U.S. Department of the Interior, Praeger, Emil H. Apparatus for molding concrete walls. U.S. Patent 2598830A, filed December 29, and published June 3, Praeger, Emil H. Roof system for stadia and the like. U.S.

Patent Filed October 28, and published July 20, Shaver, Peter D., Historic Preservation Program Analyst, New York State Office of Parks, Recreation and Historic Preservation. Correspondence to Christopher A. Waite, Executive Project Manager, Tappan Zee Bridge, New York State Thruway, dated October 30,

In context

Tarrytown, New York The place record: every map, photograph and survey of this town.
Westchester County, New York 236 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Tarrytown

11 records

The federal surveyors worked through Tarrytown building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
LyndhurstHABS NY,60-TARY,1A-497 words
LyndhurstHABS NY,60-TARY,1B-493 words
Old Croton AqueductHAER NY,60-TARYN,3A-204 words
Old Croton AqueductHAER NY,60-TARYN,3B-161 words
LyndhurstHABS NY,60-TARY,1C-128 words
Old Dutch Reformed ChurchHABS NY,60-TARYN,1-77 words
SunnysideHABS NY,60-TARY.V,1-37 words
Requa HouseHABS NY,60-TARY,3-33 words
LyndhurstHABS NY,60-TARY,1E-32 words
LyndhurstHABS NY,60-TARY,1F-25 words
LyndhurstHABS NY,60-TARY,1D-23 words

Provenance

  • Written history. Quoted verbatim from HAER NY-556. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.