Fluor-BWXT Portsmouth LLC photographed the site in August Gray & Pape, Inc., Cincinnati, Ohio, served as the primary author of the historical narrative and resource descriptions drawing from numerous historical records and reports, drawings, photographs and plans. For additional contextual information, see Portsmouth Gaseous Diffusion Plant, PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 2) HAER no. OH-142. This Process Building HAER was completed in PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 3) Part I. Historical Information In support of this report, there are three appendices that are provided: Appendix A through C, which consist of survey photographs, historical photographs, and historical drawings, respectively.
Construction History of the Process Building: The Process Building was built under a lump-sum subcontract. Peter Kiewit Sons Construction Company awarded subcontracts for foundation work and underground installations, structural steel, roofing, siding, exterior doors, freight elevators, acoustic tile, refrigeration systems, glass and glazing, and numerous other tasks necessary for the building s operations. The Eichleay Corporation began installation of the concrete footings, piers, grade beams, and walls in October Approximately cubic yards of concrete were used in this work. The concrete floor was poured by October and required approximately cubic yards of concrete and 548 tons of reinforcing steel. Column-encasement forming began in March and completed in September later that year.
Column-encasement required over cubic yards of concrete and 240 tons of reinforcing steel. Final pouring of the cell floor slab was in November which required approximately cubic yards of concrete and tons of reinforcing steel. Concrete pouring for the process equipment foundations was completed in December requiring approximately cubic yards of concrete and 160 tons of reinforcing steel. Bethlehem Steel Company erected the structural steel, which began in January and was complete by early September of that year. Approximately tons of structural steel was erected. Brown and Kerr installed the metal roof deck, roof insulation, built-up roofing, gravity ventilators, and related sheet metal.
These activities began in March and were complete by October Furnishing and installation of all corrugated cement-asbestos siding and related work was performed by Corrugated Asbestos Constructors. This work was completed during March through November Peter Kiewit Sons Company laid masonry blocks, face tiles, and ceilings from June through January Subcontracts were awarded for tasks such as lathing, plastering, painting, and the installation of tile ceilings, ceiling suspension systems and exterior doors. Installation of interior electrical systems, plumbing, heating and ventilation, air conditioning and alarm systems was complete by November as was the installation of air drying equipment, compressors, motors, converters, process gas and auxiliary piping, and instrumentation.
The building was completed and turned over to the AEC in November Historical photographs of the building s construction are located in Appendix B (Figures 10 through Historical architectural drawings are located in Appendix C (Figures 22 through Part II. Site Information A. Description of the Process Building: The Process Building is located immediately east of the Process Building. The Process Building housed the initial phase of the uranium enrichment process and then continued in series to the and Process Buildings. The Process Building was used for the initial phase of the uranium enrichment process, low assay withdrawal, production and distribution of plant dry air, and the cold recovery system.
Uranium was enriched at PORTS until May From the end of the Cold War in until production ceased in PORTS produced only low enriched uranium (LEU) for commercial power plants. PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 4) The building measures wide by long, stands 82' tall, and covers 32 acres. It is comprised of eight, connected building units, and constitutes the largest building at the PORTS reservation. The equipment and systems within the Process Building are similar to those of the former Building at the Oak Ridge Gaseous Diffusion Plant. The Process Building, however, does not include the surge volume area or the feed vaporization facilities found within the facility.
Designed specifically for housing gaseous diffusion equipment, the Process Building is purely functional in its design and appearance (Appendix A, Figures 2 through 5). There are no stylistic details found anywhere on the building. From the outside, the building appears much like an immense box with no windows. The building is covered with large, white, corrugated cement asbestos panels, also known as transite panels. All interior finishes were kept to a minimum, as cleaning and sanitation took priority over appearance (Figures 6 through 9). There are truck entrances in the north and south sides of the building, and railroad spurs within the depressed truck alleys in the east and west ends of the building.
The east spur was used largely for construction purposes, while the west spur was required for the movement of converters and other equipment during the operation of the Process Building. Like the other two process buildings and the equipment in the Process Building is on two floors, with the auxiliary equipment, support equipment, and control rooms on the first floor, also known as the operating floor or ground floor. Process auxiliaries (e.g., steam, nitrogen and dry air distribution; coolant transport and recovery; heating and ventilation; electrical power) are ancillary systems used to facilitate the primary enrichment process.
Support equipment (e.g., computer and communication equipment, sanitary and sewage utilities, security equipment) assist in process building operations, but are not directly associated with the enrichment process. The diffusion process equipment is located on the second floor, known as the cell floor. The height between the ground floor and the cell floor allows for 12' of clearance for ground floor operations, as well as clearance for the installation of electrical work, mechanical duct work, and piping. The extreme height of the first floor enabled the numerous trades of construction workers to proceed with their tasks simultaneously.
The building s height between the cell floor and the roof structure provides for clearance for the cell housings, which required the use of overhead cranes for changing out converters and supporting equipment. Part III. Operations and Process A. Operations: At PORTS, uranium was enriched using a process called gaseous diffusion. Through the process of diffusion, gaseous uranium hexafluoride (UF6) is passed through a conversion system to produce enriched, or diffused, uranium-235 and undiffused uranium-238. The process of uranium enrichment increases the proportion of uranium-235 to that of uranium-238. Enriched uranium contains uranium-235 at approximately 4 to 5 percent of the total uranium mass.
The gaseous diffusion process requires the use of UF6 to separate the uranium-238 and uranium-235 isotopes. During diffusion, UF6 gas is forced through a series of porous membranes, or "barriers" with microscopic openings. Barriers are used to achieve separation in the gaseous diffusion process. To maximize the amount of separation achieved, the porous PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 5) barrier material must meet exacting standards so that "diffusive" flow occurs. Uranium-235 moved through the barriers more easily, increasing the concentration of uranium-235 as it moved through the process. The tendency for uranium-235 to pass through the barrier more quickly is the basis for the gaseous diffusion process.
The basic separation equipment for gaseous diffusion is a "stage." At PORTS, a stage consisted of a converter that contains porous separation media, a gas cooler, a compressor to move the UF6 gas through the converter, and interconnecting piping and control valves to contain and control the gas flows. One stage was capable of only very slight enrichment. Stages operated in a cascading system, and thousands of stages in the process buildings were connected in series to produce HEU. The Process Building contains 640 stages. Stages were grouped into "cells," which were the smallest groups of stages that could be removed from service, bypassed, and shut down for maintenance or other purposes.
There are eight stages per cell in the cells in the Process Building, and the building housed 80 cells. Cells were further grouped into "units," which were groups of cells that shared common auxiliary systems. Each operating unit within the building was divided into two groups of 10 cells. The 80 cells in the Process Building are grouped into eight units. The process equipment, piping, and instrument lines that contained process gas were enclosed by cell housing and bypass housing. The cell housing for the process equipment has a steel frame and transite siding. The tops of the housings have removable hatches that allow for equipment removal. Feed material entered the uranium enrichment process at the Process Building.
The Process Building contains the largest pieces of gaseous diffusion equipment at PORTS. The size of process equipment in the Process Building was referred to as the size (i.e., 000 ). The purge and product area is located in the Process Building. Purging separated and removed light gas contaminants that leaked into the system during the diffusion process. The waste, or tails stream, of the enrichment process was withdrawn from the gaseous diffusion cascade and packaged into storage cylinders. In the Process Building, one unit with sized equipment and two units with sized equipment served as the stripping section of the cascade. The stripping section consists of the stages located below the feed point of the cascade.
From the sized unit, waste material was withdrawn from the cascade at the PORTS Tails Withdrawal Station. The PORTS Tails Withdrawal Station is located in the Process Building. The waste, or tails, from the gaseous diffusion process consisted of depleted process gas. Depleted process gas from the enrichment process was withdrawn from the gaseous diffusion cascade, compressed, and condensed into a liquid that flowed by gravity to cylinders located on scales. Cranes were used to move these cylinders to cooling areas and load them for transport. PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 6) B. First Floor: All of the auxiliary systems, electrical power substations, and control centers are located on the first floor of the Process Building.
In addition to these supporting systems, the first floor also contains numerous enclosed areas for operating purposes. The building s unit substations and auxiliary equipment are located to the north and south of these enclosures. There are eight of these areas, each corresponding to one of the building s eight units. Each side of the building includes an air intake or filter room for each of the eight units. Louvers on the exterior walls of the building provide for movement of air into the building. The louvers themselves comprise an entire wall of the filter room. Each room has a removable filter set in a steel frame. Air movement was performed by large intake fans. Air drawn in at the first floor supplied air to both the ground and cell floors.
The majority of the first-floor enclosures, as well as the stairwell enclosures, consist of cinderblock construction. Glazed structural tile was used in areas with specific sanitation requirements. Metal decking was used for the roofs of the maintenance, control area, and filter rooms. Concrete slabs were used for a number of the other Process Building enclosures. Finishes within the interior of the Process Building reflect the need for sanitation and ease of cleaning and maintenance. Most floor surfaces consist of chemically hardened, smooth- finished concrete. The control areas are the only locations within the building that feature asphalt tile floors. All ferrous metal surfaces, such as exposed steel framing and doors, are painted.
All the piping within the building is color-coded and marked for quick identification. The design of the enclosures for the various rooms within the Process Building follows the same basic plan as that for the and Process Buildings. All building finishes were designed for cleanliness and sanitation. C. Second Floor (Cell Floor): The Process Building s primary processing equipment is located on the cell floor. The equipment has eight units (80 cells and 640 stages). The cells extend across the width of the building and are located within a central bay. The housing for the process equipment was designed to maintain operating temperatures during the gaseous diffusion process. This was accomplished by erecting a cement-asbestos-covered steel frame around the compressors and converters.
The booster stations, evacuation station, and outside tie-lines feature similar enclosures. Access to the equipment is provided by a network of ladders, platforms, and catwalks. There are eight stairways that provide access to the roof, and 39 stairways that facilitate movement between the ground and cell floors. Each of the building s 21 bays contains its own overhead, electric crane. The process units in the Process Building are very similar to those in the Building at Oak Ridge and consist of two types. The difference relates to the size of the compressor motors and their electrical switchgear. The overall system is divided into units of cells arranged in series and could accommodate different types of feed material from the feed plant.
Originally, the X-342A Feed, Vaporization, and Fluorine Generation Facility served as the solitary source of feed for the gaseous diffusion cascade. However, the Feed, Vaporization, and Sampling Facility took over as the primary feed source for the cascade after it was completed in PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 7) Process gas removal for maintenance was accomplished via the evacuation system. This system enabled operators to remove gas from any of the cells and main piping system. Gas evacuated from the system entered into a recovery process. The gas recovery system (Cold Recovery) solidified the UF6 while venting the light gas impurities.
The recovered UF6 was returned to a gaseous state to be held in drums and later returned to the diffusion cascade. The uranium enrichment process was initiated in and continued in series to and Materials were withdrawn from the cascade at the following three locations: Product Withdrawal Station (90 to 97 percent uranium-235 during HEU production, 2.0 to 5.0 percent uranium-235 during LEU production) Extended Range Product Station to 5.0 percent uranium-235) Low Assay Withdrawal Station to 5.0 percent uranium-235) Tails Withdrawal Facility to 0.3 percent uranium-235 and 1.0 to 5.0 percent uranium-235). A diagram showing the gaseous diffusion "cascade" at PORTS is shown below. PORTS Gaseous Diffusion "Cascade" PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No.
OH-142-E (Page 8) D. Structural Design: The structural framing of the Process Building was based on the design used for the Building Unit within the at Oak Ridge, and the Building at Paducah. Some minor alterations to the design were necessary for the building s foundations, which engineers tailored specifically for soil conditions at PORTS. In addition, the Process Building would feature an interior instrumentation tunnel, as well as auxiliary facilities specific to the The immense size of the building created unique conditions with regards to expansion and contraction. To accommodate movement, engineers divided the steel framing into 40 structural units, each separate from the other.
The roof structure rests atop purlins (horizontal boards supporting roof rafters), which in turn rest atop trusses and beams. The ground floor of the Process Building is comprised of a 6'' thick, floating concrete slab that was designed for wheel loads of pounds per square foot. In areas that were designed to support heavy transformers, engineers specified 8'' concrete. The floor was built with methods and equipment typically used for highway construction, with reinforced, highway-type joints. This type of construction permitted heavy load transfers between expansion joints in the slab. The cell floor is supported by steel columns that have been encased in a minimum of 1'' thick concrete.
The cell floor (the 2nd floor) itself was designed to withstand the effects of the cell equipment, which operated at generating a frequency of 20 cycles per second. The exterior framing for the cell floor is comprised of light, steel beams and struts, which support the transite tiles on the side of the building. PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 9) Part IV. Sources of Information Benedict, Mason and Clarke Williams. Engineering Developments in Gaseous Diffusion Process. New York: McGraw-Hill Books Company, Inc., Department Of Energy. The Role of the Portsmouth Gaseous Diffusion Plant in Cold War History. Piketon, OH: U.S. Department of Energy, Department Of Energy.
Record of Decision for the Process Buildings and Complex Facilities Decontamination and Decommissioning Evaluation Project at the Portsmouth Gaseous Diffusion Plant, Piketon, Ohio. Piketon, OH: U.S. Department of Energy, Department Of Energy. Remedial Investigation and Feasibility Report for the Process Buildings and Complex Facilities Decontamination and Decommissioning Evaluation Project at the Portsmouth Gaseous Diffusion Plant, Piketon, Ohio, DOE/PPPO/03-0245&D3, Piketon, OH: U.S. Department of Energy, Department Of Energy. Engineering Evaluation/Cost Analysis for the Plant Support Buildings and Structures at the Portsmouth Gaseous Diffusion Plant, Piketon, Ohio, DOE/PPPO/03-0207&D4. Piketon, OH: U.S. Department of Energy, October Department Of Energy.
National Historic Preservation Act Section 110 Survey of Architectural Properties at the Portsmouth Gaseous Diffusion Plant in Scioto and Seal Townships, Piketon, Ohio, DOE/PPPO/03-0147&D1. Piketon, OH: U.S. Department of Energy, January Department Of Energy. Highly Enriched Uranium: Striking a Balance, A Historical Report on the United States Highly Enriched Uranium Production, Acquisition, and Utilization Activities from to September 30, Revision 1. Washington, National Nuclear Security Administration, U.S. Department of Energy, Giffels & Vallet, Inc. Gaseous Diffusion Plant at Portsmouth, Ohio, Project History and Completion Report (Redacted). Washington, U.S.
Atomic Energy Commission, Portsmouth Gaseous Diffusion Plant Virtual Museum accessed at operated and managed by Fluor-BWXT Portsmouth for DOE. PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 10) Appendix A: Survey Photographs Figure 1: Location and Orientation of Exterior and Interior Photographs (A-2 through A-9) PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 11) Figure 2: North Side of the Process Building, August Facing Southwest Figure 3: North Side of the Process Building, August Facing Southeast PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No.
OH-142-E (Page 12) Figure 4: South Side of the Process Building, August Facing Northwest Figure 5: South Side of the Process Building, August Facing Northeast PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 13) Figure 6: Interior View of the Process Building, August Facing West Figure 7: Interior View of the Process Building, August Facing South PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 14) Figure 8: Interior View of the Process Building, August Facing East Figure 9: Interior Staircase Leading to the Cell Floor Inside the Process Building, August PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No.
OH-142-E (Page 15) Appendix B: Historical Photographs Figure 10: Site of the Process Building, Looking East, August Figure 11: Overview of the Process Building Site, January PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 16) Figure 12: Steel Framework for the Process Building, April Figure 13: Bethlehem Steel Company Iron Workers, June PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 17) Figure 14: Bethlehem Steel Company Foremen and Managers, June Figure 15: View of Ground Floor of the Process Building, June PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No.
OH-142-E (Page 18) Figure 16: View of Cell Floor of the Process Building, July Figure 17: Looking Northeast at the Process Building, September PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 19) Figure 18: View of Mechanical Maintenance Room in the Process Building, December Figure 19: View of the Cell Floor of the Process Building, January PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 20) Figure 20: Looking South at the Process Building, May Facing West Figure 21: Interior View of the Process Building, October PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 21) Appendix C: Historical Drawings Figure 22: Change House Modifications PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No.
OH-142-E (Page 22) Figure 23: West Elevation PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 23) Figure 24: East Elevation PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 24) Figure 25: South Elevation PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 25) Figure 26: North Elevation PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 26) Figure 27: Cell Floor Plan PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 27) Figure 28: Cell Floor Plan PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No. OH-142-E (Page 28) Figure 29: Ground Floor Plan PORTSMOUTH GASEOUS DIFFUSION PLANT, PROCESS BUILDING HAER No.
OH-142-E (Page 29) Figure 30: Ground Floor Plan