The Swimming Pool was constructed at the U.S. Naval Station, Orange, Texas, in to support the needs of men attached to the Texas Group, Atlantic Reserve Fleet. Architect for the project was the Beaumont firm of Stone and Pitts; the contractor was W. L. James & Son of Port Arthur, Texas. Description: The Swimming Pool, designated on original drawings as Building was designed by Stone and Pitts, Architects & Engineers, for the Department of the Navy, Bureau of Yards and Docks, District Public Works Office, 8th Naval District, New Orleans. Dated January 9, the drawings bear Yard and Dock Drawing No. and Specification No. As a component of the U.S. Naval Station, the pool was located between Destroyer Row and Pier Road near Cooper's Gully.
The Swimming Pool was found to be an elevated, cast-in-place concrete structure surrounded by an elevated concrete walkway. Built above grade due to soil conditions and a high water table, the structure represents an astute technical solution to site constraints. The pool pan is 70 feet long and 28 feet wide and is surrounded by a cast-in-place, integral, continuous gutter. A 5 '-6 wide 11 cantilevered walkway surrounds the pool and gutter. The pool pan slopes from a depth of 3 ' - 6 on 11 the south end to a depth of about 1O' - 0" on the north end, adjacent to the diving board. Concrete stairs with metal pipe rails are located at the north and south ends of the structure and lead up to the elevated walkway.
The pool and walkway are enclosed by a 5'- 0 -high chain-link, galvanized metal 11 fence. On the north end of the pool, the walkway was widened to to accommodate a diving 11 board, and below the deck, a mechanical room, water elevation control chamber, showers, and a foot wash. The swimming pool was equipped with both underwater and site lighting, metal ladders, and a sophisticated water recirculation and purification system. The pool's above-grade superstructure was supported by a grid of wooden piles that were capped with corrugated metal shells filled with concrete. The piles were extended upwards to accommodate the change of elevation of the concrete floor of the pool. The wooden piles were driven to a depth where friction-bearing capacity was achieved for the design loads.
According to Sheet 8 of the drawings, "Piles shall have an ultimate capacity of 40 tons. The required ultimate capacity of piles is based on dead load plus 100 % live load with a factor of safety of two." Therefore, the entire pile matt (79 piles) achieved a combined loading capacity of over tons. The requirement for loading to such a capacity can be attributed to the need to resist the weight of the pool structure when filled with water. U.S. NAVAL STATION, ORANGE, SWIMMING POOL (TEXAS GROUP, ATLANTIC RESERVE FLEET) HAER No. (Page 2) The mechanical room located under the diving board at the north end of the pool housed a circulating water pump and chlorinator and associated piping, fittings, gauges, valves, and filters.
Due to the polio epidemic that was an important public concern in the early the details of the water purification system are of technical importance. The pumping system was powered from the installation's electrical network. A power pole assembly to the north of the pool contained three 15-kVa transformers and a meter for the pool. Conduits ran underground from the meter to a 200-amp load center located in the mechanical room from which power was distributed to equipment and lighting. The water level in the pool was controlled by a sophisticated system that utilized the continuous, integral gutter at the edge of the pool, a vertical screen chamber, and a float valve.
The pool was found to be in fair condition structurally, although mechanical, plumbing, and electrical fixtures, equipment, and fittings were in disrepair and, in some cases, missing. Thick vegetation has grown up around the perimeter of the pool and has obscured it from view from the adjacent roads. History: Texas Group, Atlantic Reserve Fleet, was established at Orange, Texas, in for the purpose of inactivating and maintaining naval vessels that had been transferred to the reserve fleet. At the same time, the Navy established a naval station adjacent to the reserve fleet berthing area for the purpose of providing logistical support to the reserve fleet.
Officers and men who were attached to the vessels of the reserve fleet used the naval station facilities, which included not only administrative and other offices, housing, utility and other infrastructure elements, warehouses, and supply areas, but also basic support services for recreational activities. In the Navy Department decided to expand the naval station's recreational opportunities by funding construction of a swimming pool. The department hired the Beaumont architectural and engineering firm of Stone and Pitts.
The pool represented one of the last projects designed by Stone and Pitts, a firm that began in Beaumont in Comprised of Fred Carroll Stone and Llewellyn William Pitts, Stone and Pitts was the most prominent firm in the Beaumont area for almost two decades and had been responsible for the design of the Orange naval station in Plans for the naval station swimming pool were approved on January 9, and the Navy Department called for bids in The Orange Leader on January 31. Seven contractors submitted bids on the job, which was awarded to W. L. James and Son, a Port Arthur firm comprised of William L. James and his son, William Frederick James (January 4, 1908-June 7, W. F. James, who executed the contract for the swimming pool at the U.S.
Naval Station, Orange, was a native of Port Arthur who graduated with a degree in architectural engineering from Texas A&M in He returned to Port Arthur and worked simultaneously for his father and for the city, where he was responsible for the construction of a concrete water tower and the central pumping station. After terminating his employment with the city, W. F. James began to work full-time with 2 U.S. NAVAL STATION, ORANGE, SWIMMING POOL (TEXAS GROUP, ATLANTIC RESERVE FLEET) HAER No. (Page 3) his father, constructing a courthouse in Welsh, Louisiana (Jefferson Davis Parish); a school in Sabine Pass; Methodist, Lutheran, and Church of Christ sanctuaries in Port Arthur; an addition to the high school at St.
Mary's Catholic Church in Port Arthur; the central fire station in that city; and numerous private residences. The partners also completed many small projects for the Gulf Oil and Texaco Refineries. During World War II, work continued under the direction of W. L. James while W. F. James served as a lieutenant-commander, Navy Seabees, in the Pacific theater. Work done by the firm for the government during the and included the Corps of Engineers area office and naval academy in Port Arthur, and Coast Guard projects in Sabine Pass. Construction of the swimming pool at the U.S. Naval Station, Orange, was followed by numerous renovation contracts at the same facility.