This document was prepared as part of the Yosemite National Park Roads and Bridges Recording Project, conducted by the Historic American Engineering Record in summer Richard H. Quin, Historian BRIDALVEIL CREEK BRIDGE HAER No. CA-103 (page 2) II.
This is one in a series of reports prepared for the Yosemite National Park Roads and Bridges Recording Project. HAER No. CA-117, YOSEMITE NATIONAL PARK ROADS AND BRIDGES, contains an overview history of the park roads. In addition, HAER No. GLACIER POINT ROAD, contains more specific information on the road on which the structure is located.
Bridalveil Creek Bridge carries the Glacier Point Road over Bridalveil Creek, 2.5 miles east of Badger Pass. The short span appears to be of rough log construction, but the logs conceal a steel I-beam frame and reinforced concrete substructure. This naturalistic treatment is typical of the National Park Service's proclivity for rustic style structures in the and The bridge was built as part of the reconstruction of the Glacier Point Road. The Washburn-controlled Yosemite Stage and Turnpike Company completed the Wawona Road [HAER No. CA-117d] from Mariposa via the South Fork of the Merced to Yosemite Valley on 22 July Hoping to entice more visitors to use the toll road, in the late the company opened up a saddle trail from the road to Glacier Point for its splendid view of Yosemite Valley.
The rough saddle trail proved popular, and the Washburn cartel hired John Conway to reconstruct the trail as a wagon road to Glacier Point. Conway completed the fourteen-mile wagon road in at a cost of Travelers on saddle horses could continue from Glacier Point to the Valley floor via the Four-Mile or Ledge trails. 1 No information was located concerning the first crossing at Bridalveil Creek; a bridge probably crossed the creek, although there may have been a ford. A bridge did cross the creek by the early twentieth century; this span was replaced by four 24' culverts in October 2 Plans for a reconstructed Glacier Point Road were prepared in and by the Bureau of Public Roads, an agency of the United states Department of Agriculture.
The BPR also designed the new rustic style bridge across Bridalveil Creek and let the contract to contractors Nelson and Wallace of Escondido, California, who submitted the low bid of 3 The bridge designers estimated that the following materials would be used in its construction: Class A concrete 9 cu. Class o concrete 25 cu. Reinforcing steel Structural steel Masonry 335 cu. Structure excavation (removed) 315 cu. Log rails 125 lin. ft. Log stringers 68 lin. ft. 4 Classes of concrete refer to the amount of Portland cement used in the mixture, with Class A having the highest proportion and so on. BRIDALVEIL CREEK BRIDGE HAER No.
CA-103 (page 3) The contractors established a construction camp on Bridalveil Creek near the bridge site, and crews began work on the excavation for the bridge' s footings on 23 June Work went quickly; by the end of July, the west abutment was finished, and work on the east abutment was underway. All the masonry work, including the construction of the wing walls, was finished by the end of August, and the steel was set in place. In September, the roadway was surfaced, and the 36 diameter redwood log stringers were affixed to the sides of the bridge. The bridge was completed on 4 October fifteen days ahead of schedule.
(Most other Yosemite road and bridge projects were subjected to considerable delays.) 5 The bridge was originally fitted with a timber guard rail of yellow and lodgepole pine, with two horizontal logs supported by six squat log pylons on each side of the bridge. Later, these guard rails were replaced with large logs bolted to the sides. The Bridalveil Creek Bridge is 35' long, with 20' approaches on either side; the clear span is The structure is 29' wide, with ends flaring to 37' apart. The bridge is built on a 15 skew. The structure rests on cement rubble masonry abutments constructed from granite boulders. The reinforced Class D concrete deck slab rests on five steel I-beams resting on four cross girders. The bridge seats and back ~alls are of Cla~s A concrete construction.
Debarked yellow pine log stringers, 36 in diameter, conceal the structural steel from view. More logs, bolted to the deck on the sides, form the present guard rail. 6 The structure is rated for a live load of two fifteen-ton trucks plus 30 percent allowance for impact. The structure is one of two take log rustic style bridges in the park. The El Capitan Bridge [HAER No. CA-101} across the Merced River in Yosemite Valley is a larger span of the same general design. The bridge appears to be in good condition; however, the Federal Highways Administration is now urging that the Glacier Point Road be widened and reconstructed, and the bridge may face replacement. BRIDALVEIL CREEK BRIDGE HAER No. CA-103 (page 4) III. ENDNOTES 1.
Notes from Big Tree Station, Mariposa Gazette, 16 August 3; New Saddle Train Route, Mariposa Gazette, 12 April 3; Linda Wedel Greene, Yosemite, The Park and Its Resources: A History of the Discovery, Management, and Physical Development of Yosemite National Park, California. 3 vols. (Washington, National Park Service, 2. Charles Goff Thomson, Superintendent's Monthly Report, October 4. 3. T. M. Roach, Final Construction Report, Project Yosemite E S-Al, Bridalveil Creek Bridge, Glacier Point Road, (San Francisco, CA: United States Department of Agriculture, Bureau of Public Roads, 21 March 4. United States Department of Agriculture, Bureau of Public Roads, aridge Over Bridal Veil Creek, Glacier Point Road, Yosemite National Park Proj. 5-Al, construction drawing RG-384-A, October 5.
Thomson, Superintendent's Monthly Report, June 9; Superintendent's Monthly Report, July 9; Superintendent's Monthly Report, August 7- 8; Superintendent's Monthly Report, September 8; Superintendent's Monthly Report, October 9; BPR construction drawing RG-384-A. 6. Construction information taken in part from BPR construction drawing RG-384-A. Measurements confirmed by HAER field survey, August BRIDALVEIL CR~EK BRIDGE HAER No. CA-103 (page 5) IV. BIBLIOGRAPHY PUBLIC DOCUMENTS Greene, Linda Wedel. Yosemite, The Park and Its Resources: A History of the Discovery, Management, and Physical Development of Yosemite National Park, California. 3 vols. Washington, o.c.: National Park Service, Roach, T. M. Final Construction Report, Project Yosemite E S-Al, Bridalveil Creek Bridge, Glacier Point Road.
San Francisco, CA: United States Department of Agriculture, Bureau of Public Roads, 21 March Thomson, Charles Goff. Superintendent' s Monthly Report, October --superintendent' s Monthly Report, June --superintendent' s Monthly Report, July --Superintendent' s Monthly Report, August --Superintendent' s Monthly Report, September --superintendent' s Monthly Report, October
United States Department of Agriculture, Bureau of Public Roads. Bridge Over Bridal Veil Creek, Glacier Point Road, Yosemite National Park Proj. 5-Al. Construction drawing RG-384-A, October OTHER PRIMARY SOURCE DOCUMENTS New Saddle Train Route. Mariposa Gazette, 12 April 3. Notes from Big Tree Station. Mariposa Gazette, 16 August 3.