The Dam is located within the Area of Potential Effects (APE) of the proposed Argonaut Mine Tailings Site Superfund Project in Jackson, Amador County, California. In October the United States Environmental Protection Agency (EPA), Region 9, prepared a stability evaluation report about the Dam, with assistance from the EPA s Office of Research and Development and the United States Army Corps of Engineers (USACE), to assess the Dam s stability and the impact of possible failure. According to the report, the Dam is structurally unstable and requires reinforcement.
2 In response, the California Department of Toxic Substances Control will reinforce the Dam by encapsulating the entire dam front with a composite embankment buttress of cellular concrete fill and earth, covering the top of the Dam with soil, and adding a concrete flood wall to allow for 200-year flood protection. The area within the existing dam arches and buttress will be filled with cellular concrete with a sand filter separating it from the earth buttress and creating a drain. The earth buttress will be placed in front of the concrete and sand as a soil embankment, covering most of the area between the Dam and Argonaut Drive. The filter/drain will flow into a new spillway pipe under the soil embankment and connect to the City of Jackson s stormwater system.
To reduce flow during a peak 200-year 2United States Environmental Protection Agency, Region IX, Area of Potential Effects, Argonaut Mine Eastwood Multiple Arch Dam (EMAD) Retrofit, October 5, United States Army Corps of Engineers, Argonaut Mine Dam Phase II Technical Report Stability and Retrofit Alternative Investigation, Jackson, CA, December 18, Sacramento District. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 3 discharge, a 5.3 -tall L-shaped cantilever concrete floodwall will be constructed on the crest of the soil embankment on top of the Dam to provide an additional 8.5 acre-feet of storage and achieve a safe discharge rate.3 Part I. Historical Information A. Physical History 1.
Date of Construction: Construction on the Eastwood Multiple Arch Dam (Dam) was completed in 2. Architect/Engineer: John S. Eastwood.
Eastwood, who was hired to develop the Dam design, gained notoriety for designing 19 dams throughout the West, including the world s first reinforced concrete multiple arch dam at Hume Lake, California in (HAER CA- As a result of his success designing and building the Kennedy Mine tailing dam in Jackson, California, Eastwood received a commission from the Argonaut Mining Company in to design an additional multiple arch dam for the tailings associated with the Argonaut Mine.5 Born in Minnesota in Eastwood attended the University of Minnesota as an engineering student before moving west to work on railroad construction projects during the early In he began working as a civil engineer/surveyor in Fresno, California, and for the next 29 years worked in the Central Valley.
During the and early Eastwood held jobs ranging from Fresno city engineer to surveyor for lengthy lumber flumes in the Sierra Nevada mountain range. As chief engineer for the San Joaquin Electric Company in the mid-1890s, Eastwood directed construction of a sophisticated hydroelectric power system that transmitted 11,000-volt alternating current to Fresno over a 34-mile-long transmission line. At the time operations began in April this constituted the longest commercial power system in the world. During the early twentieth century, Eastwood planned a new hydroelectric power system for the main stem of the San Joaquin River. Today this development is known as Big Creek and is operated as part of Southern California Edison Company s power grid.
Eastwood s development of the reinforced concrete multiple arch dam resulted directly from efforts to devise an inexpensive means of storing water for the Big Creek system 3 URS, Argonaut Dam Basis of Design Report, Argonaut Mine Site (February, 4 Another example of his work was the Little Rock Dam located near Palmdale, California (HAER CA-8). 5 Donald Jackson, Building the Ultimate Dam: John S. Eastwood and the Control of Water in the West (Lawrence: University Press of Kansas, Charles Allen Whitney, John Eastwood: Unsung Genius of the Drawing Board, The Magazine of Western History 19, no. 3 (Summer 49. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 4 (HAER CA-167), and he sought a design to reduce the amount of material necessary for stability.
Although Eastwood was unable to implement his innovative multiple arch dam technology at Big Creek, he had the opportunity to design and build the 64 -high Hume Creek Dam. Completed in this structure was the world s first reinforced concrete multiple arch dam. In he began work on the 92 -high Big Bear Valley Dam to be used by irrigation farmers to increase crop production in the Redlands/San Bernardino region. In the Great Western Power Company hired Eastwood to work on a project that helped him publicize and promote his dam design. The result was the large multiple arch storage dam at the Big Meadows reservoir site, which was specifically designed to regulate water flow through hydroelectric power plants along the lower part of the river.
6 Eastwood would later characterize the structural challenges associated with his multiple arch dams by noting that: The design of the Multiple Arched Dam was the result of the necessity of getting some form of structure in which the dangers of overturning and sliding could be minimized. The problem was to get at the design that would at once have the fewest objections, and would be free from the upward pressure of the water under the foundations, danger from sliding, danger from overturning, that would be evenly and lightly loaded on its foundations, and that would be safe from derangement from any extraneous causes, and strong enough to resist any one of them, and at the same time would be most economical to build.7 After completing the Big Meadows Dam, Eastwood biographer Donald C.
Jackson wrote that Eastwood continued incorporating deep arches into dam designs to limit the effect of secondary stresses.8 With the Los Verjels Dam he employed arches with an arc of over 144 degrees, the deepest of any of his structures. 9 For the Kennedy Mine tailing dam, erected in he adopted the new three-hinge design, which allowed the arches to adjust themselves (by minute internal rotation) in response to any rib shortening or temperature stresses that might cause cracking. 10 Following the 6 Donald C. Jackson, Considering the Multiple Arch Dam: Theory, Practice and the Ethics of Safety in a Case of Innovative Hydraulic Engineering, Natural Resources Journal 32, no. 1 (Winter 88. 7 John S. Eastwood, Stresses in the Multiple Arch Dam, John S.
Eastwood Papers, Water Resources Collections and Archives, University of California, Riverside, California. 8 Jackson, Considering the Multiple Arch Dam, 91. 9 Ibid. 10 Ibid. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 5 construction of the Kennedy Mine tailing dam, the three-hinge design was applied to reinforced concrete bridges to prevent similar stressing issues. In Eastwood designed the 150 -high Mountain Dell Dam in Salt Lake City using the three-hinge method. However, after designing the Mountain Dell Dam, Eastwood demonstrated a preference for rigid, [i.e. non-hinged] arches with shallow arcs 11 over the use of the three-hinge design.
Although other engineers advocated for the use of 180-degree arcs in multiple arch dam design, Eastwood openly challenged the prevailing assumptions surrounding structural elasticity.12 Before Eastwood died, he worked closely with French engineers who incorporated his designs into French dams. A Life magazine cover once featured a multiple arch dam constructed in France, but failed to credit Eastwood as the originator of the design. 13 On August 10, at the age of 67, Eastwood drowned while bathing with friends in the Kings River.14 3. Builder/Contractor/Supplier: The Argonaut Mining Company contracted to construct the Dam. The contractor was Bent Brothers of Los Angeles, a firm organized by Arthur Bent and H. Stanley Bent.
The Argonaut Mining Company The Argonaut Mining Company, incorporated in was headquartered in San Francisco, California, at 404 Humboldt Bank Building at 785 Market Street. The on-site mine office was located in Jackson, California. San Francisco attorney and businessman Jesse W. Lilienthal served as company president from to and was president during the Dam s construction. Virgilio S. Garbarini served as master mechanic from to The Argonaut Mining Company was the operating company of the Argonaut Consolidated Mining Company, located at 43 Cedar Street in New York City.
Control of Argonaut Consolidated Mining Company was held by the White Knob Copper & Development Company, Limited, which owned a majority of its capital stock.15 The Argonaut Mining Company ran one mining operation aside from the Argonaut: the Plymouth Consolidated Mine, located 10 miles from the Argonaut. After purchasing the Plymouth in the company directed most of its efforts toward operating a combined flotation and cyanide plant, which the Argonaut Mining Company had erected to treat the tailings. The Plymouth Mine was closed in and reopened briefly in but insufficient ore was discovered to justify further work. In early the 11 Ibid., 92. 12 Ibid., 95. 13 Whitney, 49.
14 Noted Engineer Drowned Bathing, San Francisco Chronicle, August 12, 15 California, World Mines Register 13 ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 6 Argonaut Mining Company halted operations, dissolved, and disposed of all company property. Both the Argonaut Mine property and Plymouth Consolidated were sold to Bernard Monte Verda and E.C. Taylor in Monte Verda, owner of Mines Engineering & Equipment Company, planned to install new machinery and reopen the mines when the market improved.16 Jesse Lilienthal President of Argonaut Mining Company Jesse Lilienthal began serving as president of the Argonaut Mining Company in July after being elected at a meeting held in San Francisco, and was president during the Dam s construction.
Lilienthal was born in New York City on August 2, He moved his family to California in and became a partner in the San Francisco law firm of Lilienthal, McKinstry & Raymond. Lilienthal became nationally known as an attorney and street railway expert. He served as vice president and later president of the San Francisco Bar Association. He became president of the United Railroads of San Francisco in Lilienthal died in in San Francisco.17 Virgilio S. Garbarini, Superintendent of Argonaut Mine Company The Argonaut Mine operations were supervised by Superintendent Virgilio S. Garbarini, a self-taught engineer and master mechanic who designed the Argonaut Mine s tramway and cable system, and ventilation system.
After his mining career, he was mayor of Jackson.18 Garbarini was born in Philadelphia in and first worked in the mining industry framing timber at the Coney (later Zeile) Mine. After working at the Zeile Mine for 10 years, Garbarini worked as a carpenter in Jackson. He then moved to Calaveras County to help dismantle the Ilex Mine and rebuild it in Amador County s Sutter Creek. Garbarini began working in the Kennedy Mine in as a master mechanic and then transferred to the Argonaut Mine in for 18 months. There, he installed the hoist, gallows, frames and crushing plant, and the 40-stamp mill. After working at other mines, Garbarini returned as the Argonaut Mine s master mechanic from to a period of peak production for the mine.
In he designed and supervised construction of the mill, tramway, steel headframe, and electric hoist for the station. He was 16 Jack R. Wagner, Gold Mines of California: An Illustrated History of the Most Productive Mines with Descriptions of the Interesting People Who Owned and Operated Them (Berkeley, California: Howell-North Books, Mark K. Walker and Dana Ogo Shew, A Cultural Resources Inventory and Evaluation of the Argonaut Mine Cyanide Plant and Tailings Site, Jackson, Amador County, California. Prepared for U.S. Environmental Protection Agency Region 9, San Francisco, California (April 29, 27. 17 The Mining Summary, Mining and Scientific Press 109 (July 25, Ancestry.com. Who's Who on the Pacific Coast, [database on-line]. Provo, UT, USA: Ancestry.com Operations, Inc., Martin A.
Meyer, The Jews in California in Western Jewry: An Account of the Jews and Judaism in California (San Francisco, California: Emanu-el, 11- 12; Lillie Bernheimer Lilienthal, In Memoriam: Jesse Warren Lilienthal (San Francisco: John Henry Nash, (accessed November 16, 18 Ray Jones and Joseph Lubow, Disasters and Heroic Rescues of California: True Stories of Tragedy and Survival (Guilford, Connecticut: Globe Pequot, 73. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No.
CA-2330 Page 7 eventually promoted to superintendent, a position he held until Garbarini was laid off after the Argonaut fire due to operational costs.19 The Bent Brothers of Los Angeles, Dam Contractors The Bent Brothers, a nationally known construction company, focused on building dams throughout the West, including Morris Dam, Devil s Gate Dam, Pacoima Dam, Lake Hodges Dam, and Bull Run Dam in Portland.20 Company president Arthur Bent began construction work in Los Angeles in the late receiving a commendation from William Mulholland, Chief Engineer of the Los Angeles Aqueduct, for a pipeline the Bent Brothers laid in By 6 years after incorporation, the Bent Brothers averaged $1 million in business annually.21 Upon completion of the Dam, the firm was hired to raise the nearby Kennedy Dam, originally completed in by the Eastwood Construction Company, an additional 20 .22 Arthur Bent was born in California in As a teen, he worked as a reporter for the Los Angeles Times then became city editor of the Express (now part of the Los Angeles Herald-Examiner).
In Bent s father bought a half interest in a concrete pipe business, putting his son in charge. For the first 10 years, the firm focused on concrete pipe work for irrigation systems, then expanded into other projects involving concrete. The demand for hydroelectric power in California brought large projects such as dams, pipelines, and reservoirs.23 The Bent Brothers first large dam construction was the Sweetwater Dam in San Diego County. The firm also constructed the Lake Hodges Dam, which was a multiple arch dam designed by John S. Eastwood, and the Devil s Gate Dam.24 They partnered with the Griffith Company to build the Friant Dam, near Fresno, California.
25 The Bent Brothers also laid the largest concrete pipeline at that time: 110 miles of 12" to 30" pipe, sometimes at a rate of per day. During the early the firm began building concrete roads. The Bent Brothers advertised their firm and their work by issuing 19 Mel D. Axtell, Biographys [sic] of Kennedy Mine Notables (Jackson, California: Amador County Historical Society, (accessed on November 16, 20 Bernard Johnson, Arthur Samuel Bent, Find A Grave, (accessed on November 16, 21 Arthur Bent of Los Angeles, Successful Methods: A Magazine of Construction Services, December ge&q&f=false (accessed on November 16, 22 Jackson, Building the Ultimate Dam, 23 Arthur Bent of Los Angeles, 24 Ibid. 25 David P. Billington and Donald C.
Jackson, Big Dams of the New Deal Era: A Confluence of Engineering and Politics (Norman: University of Oklahoma Press, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 8 monthly postcards highlighting their jobs to construction workers throughout the country. Arthur Bent was well-regarded in his industry, serving as director of the Associated General Contractors and president of the Southern California chapter. 26 In he was president of the Associated General Contractors of America.
He also served as president of the Los Angeles Chamber of Commerce in and was a director of the California State Chamber of Commerce until his death in He was chairman of a special State Chamber of Commerce committee responsible for standardizing state earthquake building code construction requirements. A trustee of Pomona College, he was also a member of the prestigious California Club of Los Angeles.27 4.
Original Plans and Construction: The Dam was designed to impound tailings from the Argonaut Mining Company s reconstructed 60-stamp mill for 25 years and retain a half-mile backup of water and tailings.28 By spring construction of a gravity system for tailings disposal, including the Dam, was already in progress.29 The Argonaut Mining Company selected a dam site in a ravine situated downslope (approximately 0.5 miles) from the operation s main head frame. Engineer Lewis Eddy noted in that the Argonaut owns sufficient acreage of land of ideal topography for just such storage basin and for conservation of tailings for future re-treatment.
30 The Dam and impoundment area slopes downward toward the southeast, allowing mining debris to be moved by channel and/or flume from the cyanide plant to the tailings piles. The topographic feature would provide adequate storage space for mining debris, and the mouth of the gully was relatively narrow. Historic maps indicate that the ravine was the closest such topographic feature downstream of the mine location, thus providing a reasonable opportunity for storage of mining debris near the cyanide plant but out of the immediate main channel of North Fork Jackson Creek.
The California Debris Commission approved the design plans, and the Dam was completed in December for The 420 -long Dam was originally designed to be 80 high; however, it was built to a height of 46 and never raised above this level. The design allowed it to be raised an additional 30 when needed, although such an alteration never occurred.32 It is possible that the mine closed before the need for raising the Dam occurred. The Dam was designed with 14 arches with spans of 32 , but appears 26 Arthur Bent of Los Angeles, 27 Johnson, Arthur Samuel Bent. 28 Argonaut Co. s Tailings Dam, Mining and Engineering World 45 (November 11, 29 Lewis H. Eddy, The Argonaut Mine, California, Engineering and Mining Journal no. 6 (August 5, 30 Ibid., 31 Jackson, Building the Ultimate Dam, 32 Argonaut Co.
s Tailings Dam, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 9 to have been built with 13 arches.33 The Dam s foundation was made of concrete, with materials obtained locally from the dumps of hydraulic diggings, which supplied large amounts of gravel from a river wash. The gravel was screened, washed, and crushed.34 During construction, concrete was poured, and tons of hoisting cable was used for reinforcing the concrete by passing it through the arches. The Dam was scheduled for completion before any water or tailings were turned in to give the concrete sufficient time to set. A storage basin was formed from two large ravines.
During the rainy season, a large volume of water was expected to move through the ravines, requiring construction of a lateral system to bypass the flood water and maintain storage area that would otherwise be decreased by debris washed into the basin behind the Dam. A simple spillway was placed at the end of the Dam, which made the impounded tailings available for re-treatment.35 In when the Dam s construction was completed, the Argonaut Mining Company began using cyanide vat leaching techniques to process tailings to extract additional gold not previously extracted at the stamp mill. The mine used at least three on-site cyanide plants at separate times during its operation.
Once ore extracted from the Argonaut main shaft was processed in the stamp mill, the tailings were transported by flume and treated at the cyanide plants located a short distance from the mill.36 At the mine s nearby tailings area, covering approximately 48 acres, mine tailings from the cyanide plant (gray sands) were impounded and stored behind the Argonaut s containment system of two earthen dams, the Dam, a 5-acre ore storage area, and an additional 0.39-acre tailings disposal site. 5. Alterations and Additions: Alterations to the Dam include the partial removal of one arch at the north end caused by the road widening of Argonaut Drive, which likely occurred in the during development of the nearby Jackson View Estates and Sierra View Estates residential subdivisions.
No other alterations appear to have been made to the Dam. A wire fence with two metal gates encloses the Dam and surrounding area. Approximately 67 west of the upstream face of the Dam, a new gravel berm passes north-south through the impoundment. Evidence of an underground water main is also present upstream of the Dam. 33 Jackson, Building the Ultimate Dam, 34 Eddy, 35 Ibid. 36 Walker and Shew, 27. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 10 B. Historic Context 1. Pre-Contact: Ethnographic literature indicates that the Dam is within the territory of the Eastern Miwok, who have been divided into five distinctive language and cultural groups: Bay Miwok/Saclan, Plains Miwok, Northern Sierra, Central Sierra, and Southern Sierra Miwok.
The Eastern Miwok inhabited four distinct biotic areas: the valleys of the inner Coast Range, the delta-plains region of the Central Valley, the Sierra foothills, and the Sierra Nevada.37 The Eastern Miwok were organized into independent and sovereign tribelets, each of which may have had its own defined and bounded territory. They were semi-sedentary hunters and gatherers and used the bow and arrow as their primary weapon for hunting and war.38 They produced both twined and coiled basketry and fashioned cordage from a variety of sources, such as milkweed and hemp.39 Eastern Miwok dwellings were either conical structures of bark slabs with no internal support or thatched buildings with a conical pole structure. Some used semi-subterranean earth- covered dwellings in winter.
Acorns were the dietary stable, and wild game included deer, antelope, elk, rabbits, and squirrels. Many of the Plains Miwok worked as agricultural laborers for the big land-grant ranchos during the Spanish and Mexican periods. When the gold rush began, many Miwoks became heavily involved in gold mining. Many individuals of Eastern Miwok descent eventually lived on rancherias in the Sierra foothills, subsisting on hunting, gathering, and seasonal work on farms and ranches. During the early twentieth century, the United States government purchased small parcels of land as reservations for some rancherias for the Plains Miwok, Northern Sierra, and Central Sierra Miwok.
Reservations were not established in Southern Sierra Miwok territory, and federal recognition of other Eastern Miwok individuals and rancherias were and remain inconsistent.40 2. Early Mining in the Americas Until the late western mining used traditional Spanish methods. Spanish mining traditions developed from the Carthaginian and Roman exploitation of Iberian gold and other precious metals. The Spanish later brought those traditions to modern day Mexico and Peru before mining began in America. The act of working a placer or lavaderos remained consistent between the beginning of mining in Mexico and South America and the discovery of gold in North America.
The process involved a batea (shallow conical washing bowl), a sluice, and dams and flues for controlling water flow.41 37 Richard Levy, Eastern Miwok, in Handbook of North American Indians, vol. 8 California, ed. William C. Sturtevant and Robert F. Heizer (Washington Smithsonian, 38 Ibid., 39 Ibid., 40 Levy, 41 Otis E. Young, Western Mining, 5th ed. (Norman: University of Oklahoma Press, 58. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 11 In Central America, the first large-scale mining activity began in at the Espiritu Santo Lode near Compostela, northwest of modern day Mexico City. The mine, which was designed to extract silver, initiated a silver rush that spread throughout Central America. The mining operations utilized immense amounts of indigenous slave labor.
During the sixteenth century, crushing techniques, used to extract minerals from the ore, advanced, and the process of stamping ore was developed. A stamp mill is a machine that crushes material by pounding rather than grinding, either for further processing or for extraction of metallic ores. The stamping process evolved with advancements in hydraulic and electrical stamping. During the early mining days in the Americas, other advancements developed, including the use of gunpowder to blast through large areas, a technique that German technicians may have brought to Mexico ca. Political instability associated with the Mexican Revolution led to a drastic decline in Mexican mining activity from to After Mexican mining nearly ceased, but resurged in the late twentieth century.
Today, Mexico is the largest producer of silver in the world.42 Miners began extracting gold from North America s southern Appalachian region as early as and as early as in southern California.43 By five main mineral discoveries launched the United States into an era of industrialization, including gold in California, high-grade iron and copper ore in Michigan, major lead deposits in the Mississippi Valley, and petroleum.44 Soon after the discovery of gold at Sutter s Creek, California in the Nevada Comstock Lode was discovered in the Colorado began mining gold in and Alaska gold mining had begun by Though gold mining activities evolved and spread across the United States during the nineteenth century, mining had the most impact in California.
California s status as a Spanish and Mexican territory until its annexation by the United States in enabled early Spanish and Mexican exploration in the region. As a result, California s proximity to Mexico greatly affected the development of its mining activities.45 3. Early Mining in California Between and mining occurred in the San Gabriel Mountains near Los Angeles, within Castaic, Paloma, Placerita, Santa Feliciana, and San Francisquito canyons.46 In Spanish settlers discovered placer deposits near the Mission of San Fernando, and the same location was mined again in The Spanish located gold in 42 Young, 82, 89. 43 Harold Kirkemo, William L. Newman, and Roger P. Ashley, Gold (U.S. Geological Survey: U.S. Department of the Interior), 18, (accessed on November 16, 44 Cedric E.
Gregory, A Concise History of Mining, rev. ed. (Lisse, The Netherlands: Swets & Zeitlinger 67. 45 Kirkemo, Newman, and Ashley, 18. 46 California Department of Transportation, Historical Context and Archaeological Research Design for Mining Properties in California (Sacramento, California: Division of Environmental Analysis, Sacramento, California, 11. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 12 but conflict with Native Americans made extraction impossible.47 Spanish soldiers had been finding and bartering with gold by and by a gold rush had begun. The first miners arrived from modern day Sonora, Mexico in upon hearing that Francisco Lopez, head of the San Fernando Rancho, had found gold.
Those first substantial placer mines were located in the present Los Angeles area and earned an estimated to during the first 2 years of operation.48 The discovery of gold at Sutter s Mill in California sparked the gold rush of Pioneer John Augustus Sutter settled along California s Sacramento River in to establish an agricultural empire. He employed James W. Marshall to build a sawmill 40 miles north of Sutter s Fort (New Helvetia). On January 24, Sutter and his workers erected the first water wheel to generate electricity.
When earth began to accumulate at the tailrace, Sutter noticed gold particles in the sludge.49 The California territory was to be ceded from Mexico under the Treaty of Guadalupe Hidalgo only 9 days after the discovery; however, neither of the signatories w as aware of the discovery at that time.50 Soon, hundreds of mining camps were established near newly discovered deposits.51 Most early miners had little to no knowledge of mining. They shoveled gravel from the bedrock under streambeds and some developed crude sluice boxes, rockers, or cradles to separate the gold from the lighter gravels.
By hydraulic sluicing with high-pressure nozzles had greatly advanced.52 Gold production increased rapidly, and gold and silver mines pumped millions of dollars into California during the mid- to late nineteenth century, which sparked the great movement westward and propelled the state s development.53 Although America invested $15 million in the treaty, the value of gold excavated in the following 11 years was million.54 The discovery of quartz veins in and around the Grass Valley district in marked the beginning of hard rock mining.
Large companies were formed and mining camps became more settled and organized.55 While minerals were mined throughout the state, the Mother Lode region was the center of gold production.56 The Mother Lode region refers to a five-county strip of the Sierra Nevada foothills beginning at Mariposa at the southern end and extending to Georgetown in the north. This region included mining 47 Wagner, 12. 48 Ibid., 49 Ibid., 50 Gregory, 68. 51 California Department of Transportation, 9. 52 Gregory, 69. 53 California Department of Transportation, 9. 54 Gregory, 68. 55 William J. Davis (ed.), Northern California and Builders, The Argonaut, San Francisco, California, 15. 56 California Department of Transportation, 10. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No.
CA-2330 Page 13 districts in Grass Valley and Nevada City. Less significant mining districts also formed farther north in Butte, Sierra, Trinity, and Siskiyou Counties.57 During the prospectors discovered deposits in California s Mother Lode districts and in Nevada s Comstock Lode. By United States gold production exceeded 4 million troy ounces a year a level maintained until With the declining availability of surface gold, miners began to implement more labor-intensive extraction methods, including hydraulicking, damming, and lode mining. Soon, mining was accomplished primarily by companies that could afford expensive machinery to deeply penetrate the earth, or build huge dredges to sift through riverbeds or tear up dry-land gravel beds to remove gold from fossil rivers.
These types of operations required large investments of machinery and skilled labor and ushered in an era of underground mining, also called hard-rock, quartz, or lode mining.59 As the gold ore was mined, it was first crushed in a Mexican arrastra (rudimentary mill for grinding and pulverizing gold or silver ore) and later in steam-driven stamp mills. The gold was collected by amalgamation, the mercury having been produced from ore mined elsewhere in California. By vaporizing and distilling the mercury in cast-iron retorts, or heating vessels, the gold was recovered from the amalgam. Only about a quarter of the vein gold was free milling, amenable to amalgamation. To facilitate amalgamation, the chlorination process was introduced in and the cyanidation process in 4.
Jackson and Amador County: Mining and Community Development Gold mining was the principal economic activity in Amador County from to the early twentieth century and led to the area s development of logging, water systems, agriculture, communication, and transportation. Jackson Gate was one of the earliest settled areas around present-day Jackson, and the roadway provided a major link to Sutter Creek.61 Jackson was founded around near a spring at the current site of the National Hotel in downtown.62 Miners congregated at the spring en route from Sacramento to the Mokelumne River mines. The number of bottles they left around the spring resulted in 57 Wagner, 12. 58 Kirkemo, Newman, and Ashley, 18. 59 Mary Hill, Gold: The California Story (Berkeley: University of California Press, 3.
60 Gregory, 70. 61 R. Scott Baxter and Kimberly J. Wooten, Breweries of the Gold Country (Charleston, South Carolina: Arcadia Publishing, 50. 62 John Poultney, Amador County (Charleston, South Carolina: Arcadia Publishing, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 14 the name Bottileas (a misspelling of the Spanish word botellas At that time, travelers used American Indian trails, which were too narrow for wagons.64 In the town was renamed for self-proclaimed Colonel Alden M. Jackson, a popular local lawyer, miner, merchant, and former Indian fighter.
By the next year, after gold was found along Jackson Creek, Jackson became a mecca for gold seekers, and the population grew to about The diggings in Jackson s immediate vicinity were not rich, but the town was within a large mining area and was a convenient stop between Sacramento and the southern mines. Consequently, Jackson grew and prospered in the early The area s richest location was below the forks of Jackson Creek. Quartz mining kept Jackson prosperous after other forms of mining, such as placer mining, were no longer profitable.66 During the gold rush, an influx of newcomers displaced the native peoples from their land. Gold seekers from around the world settled in and around Jackson, building a community with a diverse ethnic population.
Many worked in the mines, some provided goods and services, and others became farmers and ranchers. Agriculture thrived with the cultivation of fruit trees and grape vines and the raising of livestock. 67 Jackson became the Calaveras County seat in When the county seat moved 2 years later, Jackson residents successfully campaigned to create a new county from the northern third of Calaveras. Amador County, named after early miner Jose Amador, was formed on June 11, by an act of the California legislature. A small portion of Alpine County was originally part of Amador, but was ceded to Alpine in 68 Once Jackson became the Amador County seat, the town was platted, and a new courthouse was constructed.
Brick buildings replaced Jackson s early canvas and log structures, and forty new businesses opened in the commercial district, including stores, hotels, restaurants, gambling houses, and dance halls. A stagecoach line to Sacramento began operating in and the telegraph arrived a few years later.69 During that time, the settlement grew to several hundred residents.
The main business district initially extended farther southeast across the creek on Broadway, but much of the business district was rebuilt in brick due to flood and fire destruction in the early 63 History of Amador County, California with Illustrations and Biographical Sketches of its Prominent Men and Pioneers (Oakland, California: Thompson & West, 167 64 Ibid., 65 Phillip Varney, Ghost Towns of Northern California (Stillwater, Minnesota: Voyager Press, Inc., 24. 66 Mildred Brooke Hoover, Hero Eugene Rensch, and Ethel Grace Rensch, Historic Spots in California, 3rd ed. (Stanford, California: Stanford University Press, 67 Deborah Coleen Cook, Jackson (Charleston, South Carolina: Arcadia Publishing, 7. 68 Poultney, 8; Davis, 27. 69 Donald S.
Napoli, Jackson Downtown Historic District (National Register of Historic Places Nomination, United States Department of the Interior, 70 Ibid., ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 15 Despite the flooding and fire, local mining activities bolstered the economy.71 Most of the remaining stone and brick buildings on Main and Court Streets were constructed immediately after the fire.72 By Jackson boasted the National Hotel and vineyards on the town outskirts.73 Although the Gold Rush ended by Jackson maintained a population of about and placer mining remained the foundation of local commerce. Nearby mines produced steadily, while more distant mines relied on the district for supplies.
In addition, Jackson businesses, such as saloons, gambling halls, and brothels, catered to the miners.74 Local development peaked during Jackson s hard rock mining period. The town s first bank, the Bank of Amador, opened in Commercial development increased as the National and the Globe Hotels each added a third story and became the tow n s tallest buildings. The county government outgrew its courthouse facilities and erected the Hall of Records, a similarly sized auxiliary building, next door.75 Gas lamps, which had arrived in the gave way to electric lights around By the twentieth century, the California Division of Mines listed 251 quartz mines, 44 placer mines, and 96 miscellaneous, from coal to marble, for a total of 391 separate mining operations in Amador County.
Mining was the chief industry for many years, followed by logging and agriculture, primarily stock raising.77 5. The Argonaut Mine: The Argonaut deposit was first discovered in by two freed slaves, James Hager from Missouri and William Tudor from Tennessee. Hager and Tudor worked the claim, known as the Negro Claim on Negro Hill until the when they sold it to the Pioneer Gold & Silver Mining Company, which renamed it the Pioneer Claim.78 From to exploration was confined to surface trenching and the driving of an adit 71 Varney, 24. 72 Hoover, Rensch, and Rensch, 33. 73 Poultney, 74 Napoli, 75 Ibid., 76 Ibid., 77 Wagner, 93. 78 Sierra Nevada Geotourism, Argonaut and Kennedy Mines, No.
786 California Historical Landmark, landmark/sie54EDF3804B79CF17C (accessed on November 16, Larry Cenotto, Logan s Alley: Amador County Yesterdays In Picture And Prose vol. 1 (Jackson, California: Cenotto Publications, 78. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 16 on the claim s north end to cut the vein at a depth of several hundred feet.79 By the mine had reached only 150 along the 18 -wide Pioneer ore-shoot.80 Hard rock mining near Jackson formally began in when the Kennedy Mine dug its first deep shaft.
The Kennedy Mine was discovered in by Andrew Kennedy, organized as the Kennedy Mining and Milling Company in and mined almost continuously from to Jackson s third main hard rock mine was the Eureka.82 Smaller hard rock mines also expanded, and gold production increased dramatically. The need for workers burgeoned too, as mines operated around the clock, causing the local population to increase by a third between and The Argonaut Mine s significant development began in when it was purchased by the Argonaut Mining Company and the first deep shaft was dug.84 The Argonaut claims covered along the Mother Lode.
The Argonaut Mining Company explored the deeper portions of the ore body by sinking an inclined shaft in the hanging wall of the vein with crosscuts and inserting drifts driven from the main shaft. Shallow ores, which were rich and highly profitable, were crushed in a 40-stamp mill, completed in However, exploratory work could not occur too long before actual mining operations because the interim maintenance expenses would have been prohibitive.85 From the to the height of mining activity along the Mother Lode, the Amador County quartz mines, particularly the Argonaut and Kennedy, were the deepest and most productive.
In those mines, the ore continued to be excavated from a depth of vertical feet without a significant change in its nature.86 The Argonaut Mining Company sought to exploit this deep ore by sinking the mine shaft progressively deeper. In the Argonaut shaft sunk deep and continued sinking at rate of 2.5 per day. In the shaft was deep, although mining was confined to the level. The shaft reached the level in and the level in By the time the 79 W.O. Vanderburg, Mining Methods and Costs at the Argonaut Mine, circular (Amador County, California: Bureau of Mines Information), 15. 80 Clarence August Logan, Mother Lode Gold Belt of California, Bulletin No. 108 (San Francisco, California: State Division of Mines, November 67, (accessed on November 16, 81 Sierra Nevada Geotourism; Clark, 69.
82 Sierra Nevada Geotourism. 83 Napoli, 84 Amador Gold, Argonaut Mine, Jackson, Amador County, (accessed on November 16, 85 Vanderburg, 15. 86 Wagner, 93; William B. Clark, Gold Districts of California, Bulletin 193 (Sacramento, California: California Division of Mines and Geology, 69, (accessed on November 17, 87 Wagner, 94. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 17 gold mines closed, the value of production in the Jackson-Plymouth district ranged from $2 million to $4 million annually.88 The Argonaut employed stamp mills to process the ore. The first mills in the Plymouth- Jackson lode region were rudimentary arrastras.
Small, 2- to 5-stamp mills operated in the with larger, 10- to 20-stamp mills in the and and 80- to stamp mills in the Power for the hoists and mills was first provided by water and steam. The Argonaut (and Kennedy) operated with Pelton wheels and steam power. Water from the Amador Canal and Jackson (Kennedy) Ditch supplied the power. During the late the mills began switching to electric power, provided by the Blue Lakes Powerhouse (located downstream from the present Electra Powerhouse).89 Several thousand miners were employed, many of whom were of Italian, Austrian, and Serbian ancestry.90 Laboring in the mines was extremely difficult and dangerous.
At the Argonaut, a three-compartment shaft allowed the ore to be removed for processing as well as water pipes, electricity, and telephone wires to be laid at the mining levels. The shaft also transported miners from the surface to the mining levels. 91 About 75 men ordinarily worked 8-hour shifts in the mines. With the exception of occasional closures, the mine operated 24 hours a day, every day of the year.92 By the Argonaut was regularly employing over 200 men.93 The Kennedy and the Argonaut had been connected at various underground points before being closed off completely (after the Argonaut s fire).
94 These connected underground workings spurred two lawsuits during the in which the Argonaut alleged that owners of the Kennedy facility was mining its property.95 By the shaft had reached , but work at the mine was temporarily halted as a result of an injunction issued during the lawsuit between the Argonaut and the Kennedy over claims that each was mining on the other s property. When they reopened, 140 men were employed in the Argonaut mine, the mill, and a slime plant below the mill. Ore recovery at the plant involved treating the pulp from the mill using hydraulic separators and tables set at a declined angle to separate out and wash down the sulfide concentrates, which were then agitated to resize the material.
Recovery was roughly 35 percent, with 65 percent remaining in the tailings. In plans were developed to expand a small 88 Jackson-Plymouth, Gold Districts of California (Oakland Museum of California, (accessed on November 17, 89 Walker and Shew, 18. 90 Jackson-Plymouth, 91 Ibid., 70. 92 Ibid., 73. 93 Review of Mining, Mining and Scientific Press 118 (June 28, 94 Jones, 75. 95 Clark, 70. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 18 experimental plant to process the Argonaut tailings, a practice that continued until the mill closed in By waste rock was being deposited on the east side of a road north of the shaft, via a 50 -high trestle.
At the north end of the waste rock dump, near the Kennedy Mine property, an outbuilding was constructed and the 40-stamp mill had been remodeled to include concentrators for better gold recovery. A tunnel extended between the northwest wall of the quartz mill heading west and underneath the old highway. By operations were powered by both water and electricity.
97 The value of gold production in Amador County more than doubled between and The value subsequently fluctuated, hitting new highs in (and later in Transportation to the region improved, and by the California State Mining Bureau reported that railroad service to Amador County was especially good, the mines being within easy communications with San Francisco, Stockton, and Sacramento by means of the Southern Pacific Railroad from Galt to Ione and then over the Amador Central Railroad to Martel, which is within 2 miles of Jackson on the south and Sutter Creek on the north. By then, automobile and wagon roads had been established between the stations at Martell, 2 miles northwest of Jackson, and Carbondale, 13 miles northwest of Jackson.98 6.
Lode Mine Tailings Management: Lode sites like the Argonaut Mine complex produced waste rock (excavated rock that is not ore) and tailings (the discharge of unwanted processed material from mills and separators). Unlike placer gold, extracted ore requires chemical processing to free its minerals.99 The first step in ore processing is crushing the rock into a powder that can be treated. This was commonly accomplished with stamp mills, where ore was fed into a cast-iron mortar box located under a battery of heavy vertical rods.
100 The undesired portion of the ore discharged from the mills the tailings was generally in slurry form.101 Tailings were routinely discarded where convenient and most cost effective, often in flowing water or directly into drainages.102 Before construction of the Dam, the Argonaut Mining Company deposited tailings in the North Fork Jackson Creek.103 To correct the improper disposal of tailings, the U.S. Congress established a California Debris Commission in to regulate mining operations that might affect stream flow 96 Walker and Shew, 21. 97 Walker and Shew, 23; Sanborn Fire Insurance Company, Jackson, Cal. Jan. revised May sheet 9.
98 William Burling Tucker, Mines and Mineral Resources of Amador County, Calaveras County, Tuolumne County (San Francisco, California: California State Mining Bureau, September 3. 99 California Department of Transportation, 92. 100 Ibid., 99. 101 Ibid., 102 United States Environmental Protection Agency (EPA), Office of Solid Waste, Special Waste Branch, Technical Report: Design and Evaluation of Tailings Dams (August 1. 103 Walker and Shew, 23. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 19 along the Sacramento and San Joaquin Rivers and oversee the construction of debris dams specifically designed to contain detritus.104 Enforcement was lax until when litigation compelled gold mine operators to control their debris.
105 In response to the mandate, mills began constructing impound areas or tailings ponds by constructing a dam across a downstream ravine and allowing the tailings to build up behind it. 106 The Argonaut Mine discontinued dumping of tailings in piles adjacent to the mill and constructed a large earthen debris dam across the gulch north and west of the present Jackson Junior High School. The Argonaut also hired John S. Eastwood to design the Dam to prevent the mill waste from eroding into Jackson Creek and eventually into valley agricultural lands in Ione, Jackson, and Dry Creek Valleys.
To move the waste to the new reservoir behind the Dam, the Argonaut liquefied the tailings in the new mill to create the slime, which flowed by gravity through a flume and ditch almost 1 mile into the reservoir.107 Rather than install an expensive system to elevate and transport the tailings to the larger impoundment area from the original mill site, the Argonaut built a new mill on the hilltop above the old mill. From this point, a gravity system sent tailings to the impoundment basin, away from the nearby Jackson Creek fork.108 The new mill, located over the ridge from the mine, on the west slope, began operation in with the capacity to crush 200 tons of ore daily with 40 stamps.
From the mercury amalgamating plates, the pulp flowed to sixteen Frue vanners, equipment used for automated mineral processing. Tailings went to hydraulic classifiers and the overflow concentrate using a Darrow rotary concentrator, resulting in an 83 percent recovery rate. An electric hoist was installed underground. The mill employed 150 men.109 7. Construction and Operation of the Dam The Dam is a multiple arch buttress dam constructed of reinforced concrete. America s first dams were small, crude, timber crib-and-stone diversion dams, but mid-nineteenth century development of large water power sites prompted evolution in dam design.
During the late nineteenth century, as the arid West opened to settlement, dam construction became necessary to store water for mining, irrigation, and hydroelectric projects in isolated, remote western locations. Interest grew in more innovative and less expensive designs.110 In a multiple arch buttress dam like the Dam constructed by Eastwood, as opposed to a flat slab buttress dam, the upstream side consists of a series of arches supported on the buttresses. The buttress dam s downstream side appears as a series of parallel walls rather than as a solid monolith. During the early twentieth century, 104 Jackson, Building the Ultimate Dam, 105 Clyde R.
Berriman, Kennedy Tailing Wheels, National Register of Historic Places, 106 California Department of Transportation, 107 Walker and Shew, 25. 108 Eddy, 109 Walker and Shew, 25. 110 Donald C. Jackson, Great American Bridges and Dams (New York, New York: John Wiley & Sons, 51. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 20 both multiple arch and flat slab buttress dams were constructed with reinforced concrete. However, multiple arch dams allowed for wider spaces between the buttresses, using less material than a flat slab design of comparable size. John S.
Eastwood gained recognition for building the West s first major multiple arch dams.111 Although Eastwood s most well-known dams were constructed to control water flow, he also employed the multiple arch design for mine tailing impoundment. At the time of its construction, the Argonaut Dam was one of the largest debris dams in California, measuring approximately 420 long and 46 tall at its highest point. It ranged in thickness from 30 at the base to 12 at the top, with 13 full arches with bases on the end. Tons of hoisting cable was used to reinforce the concrete. The Dam was designed to back up water for a half mile and be raised to stand an additional 30 when needed.112 It was estimated to provide 25 years storage capacity for tailings from 40 stamps, crushing a total of 200 tons per day.
The operation would increase tonnage to nearly 300 tons a day by the addition of 20 stamps to the mill, and thereby reduce the duration of storage. During the first few years, the basin bottom was intended to fill quickly, leaving the upper basin portions to provide the longest storage.113 According to Engineering and Mining Journal in This arch type dam is approved by the California state engineering department. It has the best possible foundation, made of concrete, the material being obtained locally from the dumps of hydraulic diggings, which supply large amounts of gravel from ancient river wash. The gravel is screened, washed and crushed.114 Since the Kennedy tailings dam construction only 2 years earlier, John S. Eastwood s multiple arch dam design had evolved.
When Eastwood designed the Kennedy tailings dam, he adopted a new three-hinge design, with hinged joints where the arches met, to eliminate secondary stresses in the arches. Eastwood employed the three-hinge design in the Kennedy tailings dam in and as a key part of his 150 -high Mountain Dell Dam (Salt Lake City) design in After Eastwood observed how the Kennedy and Mountain Dell Dams three-hinge arches performed, he realized that environmental variances, not accounted for by the elastic theory s design assumptions, affected the dams structural performances. Donald Jackson describes these variances as including conditions such as: 111 Jackson, Great American Bridges and Dams, 112 Argonaut Co. s Tailings Dam, Eddy, 113 Eddy, 114 Ibid. 115 Jackson, Considering the Multiple Arch Dam, 91.
ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No.
CA-2330 Page 21 a) the hydrostatic loadings on the arches are not uniform because the upstream face of most multiple arch dams are built on a slope; b) the supports for the arches (i.e., the buttresses) are not rigid and inelastic, but are similar in elasticity to the arches themselves; and c) with the reservoir filled, the upstream side of the arches are saturated with water, which causes the arches to expand in volume; this expansion will consequently help counteract any rib-shortening stresses caused by the hydrostatic loading.116 In response to the uncertainty that these variances posed, Eastwood decided to employ thin arches that provided relatively good compatibility with the theoretical assumptions underlying the elastic arch formula.
117 Soon thereafter, he began using rigid, non-hinged arches with shallow arcs, which he then used in the Argonaut Mine Dam s design.118 The San Francisco Chronicle documented the Dam s construction and, in April noted that the Argonaut Mining Company was constructing a large restraining dam to prevent the escape of mill tailings to neighboring streams. The Chronicle reported that the impounded tailings would later be treated by the cyanide process for recovery of their gold content and that the company was disbursing substantial quarterly dividends. In conjunction with the mill s relocation and reconstruction, the company installed a powerful electric hoist on the level. The new equipment enabled the company to operate to a depth of beyond the previous deepest workings.
119 Later in April the Chronicle reported that Argonaut Mine s new mill was nearing completion. The new mill plant contained 60 heavy stamps and was equipped with the most modern gold saving appliances to facilitate a closer gold recovery than was possible with the old 40-stamp mill. From the final set of gold-saving devices the mill tailings will flow to the impounding basin, guarded by a dam 400 -long x 40 -high at the lowest point. Later on this material will be treated for recovery of the low gold content, formerly sluiced to waste.
Development in the mine continues highly satisfactory, with the outlook favorable for a long era of remunerative operations.120 In July the Chronicle reported that construction of the reinforced concrete dam for restraint of tailings from the Argonaut mill had been completed, and that tailings storage would commence in the fall. In the mill, the rock crusher had been placed, and installation of machinery in the main plant was proceeding rapidly. Ore of excellent grade was transported to the old 40-stamp plant from the levels above the 116 Jackson, Considering the Multiple Arch Dam, 93. 117 Jackson, Considering the Multiple Arch Dam, 118 Ibid., 91.
119 Argonaut Mining Company Installs Powerful Hoist, San Francisco Chronicle, April 24, 120 New Argonaut Mill Nearing Completion, San Francisco Chronicle, August 28, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 22 point.121 Tailings were carried to a controlled deposition area and impounded by the dam.122 Meanwhile, the Kennedy Mining Company planned to increase the height of its nearby tailings dam from 40 to 60 to ensure against any escape of tailings from the impounding pond in the wet season (done by Bent Brothers). 123 During the operation of the Argonaut Mine, the Dam held the overflow water and slimes in a series of earthen dams and tailings piles from the mill and cyanide plant.
When the cyanide plant became part of the mine s operations, its tailings were likely stored to the south of the cyanide plant. By the original tailings pile (the upper tailings area or the gray sand tailings) was referred to as the Old Tailings Pile, and a new tailings pond had been created directly to its east. The pond ranged in depth between 2 and 14 and was contained on the east by an approximately 5 -high berm that was also the crest of a 60 -tall tailings pile. Runoff from the tailings pile and pond traveled downslope through the ravine and was contained by the Dam.
The impoundment behind the Dam was almost 20 deep, and the water line sat approximately 2 from the top of the Dam.124 Fences were constructed to run on the north and south side of the tailings pile, narrowing at the deepest part of the ravine and widening again to surround the pond held by the Dam. The fences may have helped siphon the runoff and contain the tailings.125 8. Argonaut Gold Cyanidation Beginning in the Argonaut used cyanide vat leaching techniques to process tailings to extract additional gold not previously extracted at the stamp mill. Gold cyanidation is a metallurgical technique for extracting gold from low -grade ore or tailings by dissolving the material to a water-soluble cyanide solution that separates the gold from the ore.
The mine used at least three on-site cyanide plants at separate times during its operation. Tailings from the cyanide plant (gray sands) were impounded and stored in the Dam and earthen dams. Like many mines in the area, the Argonaut had stockpiled large quantities of its tailings and middlings, waiting for the development of methods that could profitably process these materials. In Simmonds & Latham of Melones, Calaveras County, built a 100-ton capacity cyanide plant east of the original stamp mill after obtaining a lease to work the Argonaut Mine s discarded tailings.126 At the time, approximately 121 Big Montezuma Mine at Nashville Promises to be Heavy Producer, San Francisco Chronicle, July 24, 122 Berriman, 123 San Francisco Chronicle, July 24, 124 Walker and Shew, 34. 125 Ibid., 35.
126 Eugene Franz Roeber, ed., Construction and Operation: California, Metallurgical and Chemical Engineering 16, no. 3 (February 1, Walker and Shew, 29; Weston Solutions, Inc., 1. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 23 tons of tailings had accumulated in storage.127 Plant capacity was expected to reach 150 tons per day.128 The cyanide plant closed in after only 2 years of operation. In Wilton E.
Darrow acquired a lease to work the tailings from the new mill once it began operations.129 Darrow owned and operated the California Slimes Concentrating Co., which began building a new cyanide plant between the [new] mill and the large Eastwood Dam in The cyanide plant likely resembled Darrow s other successful plants at the Fremont and Bunker Hill gold mines in Mariposa County, California and Kellogg, Idaho, respectively. The California Slimes Concentrating Co. expanded the cyanide plant at least once during the 5 years they operated it. By the plant had doubled its capacity, and in addition to cyanidation, was also capable of amalgamation, concentration, and flotation. California Slimes Concentrating Co.
used the plant until the Amador Metals Reduction Company, owned by Hamilton, Beauchamp & Woodworth, assumed the plant s operations in The Amador Metals Reduction Company processed the Argonaut tailings at the cyanide plant from to extracting gold from approximately tons of tailings a year.132 The company likely expanded the cyanide plant, adding equipment for treating slimes and concentrates.133 At least one other expansion took place in with the addition of a three-leaf filter, Ruggles-Cole dryer, a sacker, and a Coe classifier. The plant treated all of the tailings from the Argonaut mill, which flowed to the plant through a -long, concrete-lined wooden launderer. By it also operated a custom plant for treating gold concentrates.
Throughout the the plant treated the ore and concentrates from several mines in the district. Despite its reputation as one of the state s leading metallurgical plants, the Amador Metals Reduction Company ceased operations in July By the end of the plant had been dismantled and the equipment moved and stored at the Delta Tailing plant in Jackson Valley.134 The Amador Metals Reduction Company likely closed the cyanide plant in light of the Argonaut Mining Company s new developments, experiments, and improvements during the late By the Argonaut Mining Company was employing a successful 127 Roeber, Weston Solutions, Inc., 6. The exact location of this original stockpile is unclear but may have been near the site of Argonaut s original mill, located on the north side the present Highway 49.
The tailings may also have been stored in a thickening basin, or in some other area near the Argonaut s containment system of earth en dams and reservoirs. 128 Late News From the World s Mining Camps, Mining and Engineering World 45 (December 30, 129 Review of Mining, Mining and Scientific Press 114 (April 7, 130 Ibid., 131 News by Mining Districts, Engineering & Mining Journal no. 12 (September 16, 132 Denton W. Carlson and William B. Clark, Mines and Mineral Resources of Amador County, California Journal of Mines and Geology 50, no. 1 (January 133 News by Mining Districts, 134 Walker and Shew, 31. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No.
CA-2330 Page 24 method to efficiently treat its high-grade sulfurets and a small-capacity cyanide plant was installed inside of the existing mill.135 The company continued working tailings in its own cyanide plant until the mine suspended operations in 9. The Argonaut Mining Company and Local Quartz Mining Postwar Maintenance: Between and its bonanza period, the Argonaut Mine was producing the best average grade of ore of any mine along the Mother Lode, and the shaft had reached The year following the Dam s construction, the Argonaut Mining Company installed an 800 tramway from the mine shaft to the new mill and the additional 20 stamps were put into operation, treating 300 tons of ore daily.
By the shaft was deep and required an elaborate pumping system to stay 137 At this time, the California Slimes Concentrating Co., under contract with Simmonds & Latham, began installing a cyanide plant to work the tailings for residual gold.138 While California s mineral industry exhibited exceptional activity during early gold mining had suffered a period of depression. Although new gold mines had opened, and older ones had reopened, there had been no increase in output from the year before. Expenses for gold production had increased 18 percent in based on increased labor and supply costs and higher taxation. Many mine owners had to temporarily deactivate some of their stamps because of scarcity of skilled and unskilled labor, preventing them from hoisting the normal quantity of ore.
Adjoining states were offering higher wages than California, and copper mines were offering bonuses, attracting former gold mine workers. Furthermore, by when the United States had just entered World War I, the California Debris Commission had been vigorously enforcing its regulations, requiring deep mines to construct tailings dams, which further taxed mining company finances.139 During World War I and for some years thereafter, the annual gold production declined to about 2 million ounces.140 By gold mining began a slow recovery after several years of depression, particularly quartz mining on the Mother Lode and drift mining in the mountains. Work had resumed in the Argonaut, Kennedy, Fremont, and Moore mines on the Mother Lode in Amador County.
Operating costs began to return to a point where the ores common to the Mother Lode are payable, it is only natural that interest in the possibilities of this 135 Ibid., 43. 136 Wagner, 94. 137 Ibid., 95. 138 Walker and Shew, 25. 139 California Mines in Mining and Scientific Press 115 (September 1, 140 Kirkemo, Newman, and Ashley, 18. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 25 great vein system should be increasing. 141 That year, the Argonaut Mine became the site of the worst mining disaster in the Mother Lode. Forty-eight immigrant miners were trapped at below ground in August They died from deadly gas that was released during a mine fire. Governor William Stephens appointed an investigative committee, which was unable to determine the fire s cause.
The committee concluded that the fire was caused by incendiarism, meaning arson or defective wiring.142 The Argonaut Mine fire burned for over 2 days before it was extinguished. Rescuers worked for 2 weeks to descend to the level where the miners were trapped. All recovered victims were buried at local cemeteries.143 The Argonaut Mining Company closed the mine for a year after the fire, reopening in July However, from to a substantial amount of gold was recovered from tailings produced in earlier years of operation.
These were treated by a separate company, known as the Amador Metals Reduction Company, in a plant built especially for the purpose.144 Between and the Amador Metals Reduction Company treated the Argonaut Mine tailings, treating about tons of tailings, for which they recovered an average of per year.145 After the ore was crushed, it went through the amalgamation process. In a Memorandum from the EPA, Kim Muratore describes the subsequent processes as follows: Tailings from the amalgamation plates are sorted in spitzlutte, an instrument by which sand is sorted in a continual upward-flowing stream of water to separate out the small grain pyrites from the larger grain materials, producing two spigot products plus an overflow.146 Mark K. Walker and Dana O.
Shew provided additional details concerning the gold processing by stating: The spigot products were concentrated using vanners, and the overflow thickened in a cone and then also treated with the vanners. Vanner tailings were classified and dewatered in a drag classifier, then ground in tube mills. Meanwhile, after amalgamation, the pulp was concentrated on tables, with 141 Fletcher Hamilton, A Review of Mining in California During Preliminary Report No. 8 (San Francisco: California State Mining Bureau, January 21. 142 Cecilia Rasmussen, Gold Mine Disaster Was State s Deadliest, Los Angeles Times, January 15, 143 Sierra Nevada Geotourism. 144 Wagner, 145 United States Geologic Survey (USGS). Argonaut Mine. Mineral Resources On-Line Spatial Data.
(accessed February 27, citing Clark, Argonaut Mine tailings, Amador County: Unpublished preliminary report 64, California Division of Mines, 1. 146 Muratore, Kim. Memorandum: Releasable Chronology of the Argonaut Mine Site Ownership & Operation. United States Environmental Protection Agency, Region IX. January 28, 9. (accessed on February 27, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 26 classifier overflow pulp, after thickening, processed on slime tables.
The concentrates were sent over to the Amador Metals Reduction Company for further processing, while the general mill tailings were transported by flume and treated at the Amador Metals cyanide plant located a short distance from the mill.147 When the price of gold increased from to $35 an ounce in production increased rapidly and again exceeded the 4-million-ounce level in By that time, ball mills and flotation cells were installed replacing the 60-stamp mill, and the mill crushed nearly 300 tons of ore daily.
The Amador Metals Reduction Company operations halted in and much of the plant equipment was dismantled and removed for storage, freeing up additional storage space for tailings.149 In the Argonaut Mining Company constructed a cyanide plant to treat concentrates from the Argonaut mill, as well as those from the Plymouth Consolidated, which it also operated.150 The Argonaut and the Kennedy were the only two hard-rock mines in Jackson that remained active into the twentieth century.151 Both remained active until when Gold Limitation Order effectively closed mines not strategic to World War II.152 Believing that the mine closures would be temporary, the company directors kept the upper part of the mine dewatered and in repair in anticipation of reopening.153 After the war ended in the U.S.
government permitted gold mining to resume by lifting Order During the 3 years of inactivity, however, many of the deep mines had flooded, caved in, and otherwise deteriorated to the point where the cost of reopening was prohibitive.154 In December the Argonaut Mining Company s directors and examined the prospects for gold mining and recommended dissolution of the company. By February the majority of the stockholders had consented. During the dissolution of the corporation, the property was purchased by E.C. Taylor and Bernard Monte Verda, a local mining engineer. The Argonaut Mine s machinery was removed and sold.155 147 Walker and Shew, 27. 148 Kirkemo, Newman, and Ashley, 18. 149 Walker and Shew, 27; Wagner, 150 Wagner, 151 Jones, 72. 152 Varney, 24. 153 Wagner, 154 Ibid., 14.
155 Wagner, Calaveras Heritage Council, Calaveras Central Gold Mining Company, (accessed on November 17, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 27 By the time they closed, the Argonaut had produced $25 million in gold and the Kennedy $35 million.156 Since the area had produced more than worth of mineral products, with nearly 85 percent gold produced from the Plymouth Jackson district, the richest segment of the entire 115-mile length of the lode. Other important mineral products produced were clay, coal (lignite), and copper. By the mid - the districts largest gold producers the Argonaut, Kennedy, Keystone, and Plymouth mines had all been inactive for nearly a decade.
The Central Eureka mine, still active circa was one of the few Mother Lode gold mines that survived the government restriction order of and increased mining costs.157 On September 18, the Argonaut and Kennedy Mines were collectively designated California Historical Landmark No. 10. Postwar Maintenance: In the Argonaut and Plymouth Mines were sold to Bernard Monte Verda and the Mines Engineering & Equipment Company, which salvaged surface operations.
In Morse Van Horn purchased the tailings area and obtained contracts with Biomet II, Inc., and later North American Reclamation, to remove several thousand tons of ore and tailings for further processing and gold extraction.159 In the early approximately tons of unprocessed ore was reportedly removed from the property for gold processing in Nevada.160 Since the Argonaut Mine s closure, approximately 90 acres of the former mine site were subdivided and redeveloped as residential property. Argonaut Heights was established east of the tailings area in the early and using a cut-and-fill process to level the lots.
Two additional subdivisions, Jackson View Estates and Sierra View Estates, were built during the near the southern end of the tailings area on areas of known waste rock and mine tailings. The waste rock and mine tailings were covered with imported fill prior to residential construction.161 The Argonaut Dam has required surveillance and maintenance since the mining operation closed. While conventional dams do not need to be designed to last indefinitely, tailing dams retain materials (solids and water) that would be considered contamination if released. 162 156 Varney, 24. 157 Carlson and Clark, 158 California State Parks, Office of Historic Preservation, Argonaut and Kennedy Mines, Historical Landmark, (accessed on November 17, 159 Weston Solutions, Inc., 4.
160 Ecology and Environment, Inc., Sam pling and Analysis Plan, Argonaut Mine Tailing Pile Assessment, Jackson, California, Prepared for U.S. Environmental Protection Agency, Region 9, July 161 Weston Solutions, Inc., 6. 162 T. E. Martin and Davies, Trends in the Stewardship of Tailings Dams, AGRA Earth & Environmental Limited, Burnaby, Canada, (accessed November 17, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 28 Part II. Structural/Design Information A. General Statement: 1. Character: The concrete multiple arch dam s structure and appearance convey its role in the Argonaut Mining Company s system as a barrier to impound mine tailings from the mine s processing plant approximately to the north.
While mining operations ceased in and residential development now exists between the mine s headframe and the Dam, the Dam has continued its function as an impoundment for the mine s remaining tailings. Although the Dam and its immediate setting have been maintained and slightly altered over time, the Dam s principal components have not been substantially modified since construction was completed in Overall, the Dam effectively communicates its function as an impoundment dam through its structural features and materials. 2.
Condition of Fabric: The Dam still serves its intended purpose but is in a deteriorated condition, as evidenced by the eroding concrete at the top of the Dam, efflorescence, rust staining and biological growth visible on the Dam s face, and exposed concrete aggregate and rebar caused by spalling in the concrete structure and tie beam. Dense vegetation has grown along the downstream side of the Dam, and the upstream side has been filled with mine tailings.
Inspections conducted during the early noted cracking in the Dam as early as which is documented in historic photographs.163 The northernmost arch was partially removed circa for the construction of Argonaut Road, which was built concurrent with the residential development on the Argonaut Mining Company s former property northwest of the Dam. The Dam appears to have undergone no other significant alterations other than loss of the spillway, which either has decayed or was demolished. In the EPA, in coordination with the USACE, conducted a stability evaluation of the Dam and deemed the concrete dam to be structurally unstable and in need of reinforcement.164 Visible cracks in the structure and rubble at the north end of the Dam indicate an impact from the construction of Argonaut Drive.
The impounded tailings include toxic substances, such as arsenic, lead, and mercury. Wetlands are located near the tailings impoundment, and surface water from the mining area drains to Jackson 163 State of California Department of Public Works Division of Water Resources, Inspection of Dam, Argonaut No. 164 Weston Solutions, Inc., 1. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 29 Creek and wetlands.165 In September the Argonaut Mine site, including the Dam, was listed on the EPA s National Priorities List. Despite the Dam s condition and concerns about environmental contamination however, the Dam remains mostly unaltered from its original construction. B.
General Description: Situated in the Argonaut Mining Company s tailings area, approximately south of the mining operation s main head frame, the Dam is constructed of poured-in-place board- formed concrete. It measures approximately 420 long x 46 high, with 13 visible buttressed arches that range in thickness from 18 at the base to 12 at the top. The landscape slopes from each abutment, with the depth of each arch and buttress increasing toward the center. The arches, along with the stepped buttress walls, were reinforced with tons of reused 1- 1/8 hoisting cable, which extend 1 to 3 from the concrete. In addition, 1 x 2 chamfered concrete tie beams on the face between six of the arches brace the central and tallest of the buttress walls.
Spacing between the arches is approximately 30 x 1 , and the arches are approximately 32 deep at the toe. Within each arch, diagonal concrete seams are visible between the curved arch portion in the center and the projecting perpendicular buttresses. Imprints in the concrete from the structure s original board form construction indicate that 9 to 1 -wide boards were used in framing the concrete. Horizontal wood boards from the concrete board form remain near the toe in one of the arches. The top of the Dam displays 4 x 16 rectangular imprints in a repeating pattern. At the apex of the joining arches, the width of the crest measures approximately 3 x 7 . The Dam foundation may be composed of a weathered clayey siltstone of low plasticity.
However, a letter states that the Argonaut dam rests upon a hard dense diabasic rock of good quality, being tough massive, and fairly resistant to the action of percolating water. 166 Water was initially drawn from the bottom through a 16 iron pipe, but the drain is no longer extant. The Dam was also constructed with a simple wooden spillway at its northern end, which is no longer extant. However, a cluster of pipes is set within the concrete at the southern end of the Dam, as well as a rudimentary hole approximately 3 from the top, which may be used for overflow.167 During the mine operation, the Dam held the overflow water and slimes (originating at the cyanide plant and mill) from a series of earthen dams and tailings piles.
Since the mine closure, the Dam impoundment area has been filled with silt and sand.168 Approximately 2 to 3 of the upstream face remains exposed between the impounded fill and the crest of the 165 Ibid. 166 Chester Marliave, Memo Concerning Geology at Multiple Arch Dam Sites, Argonaut Dam July 24, 167 Marvin, 10. 168 Walker and Shew, 34. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 30 Dam. In Walker and Shew identified a cluster of pipes at the south end of the Dam set into the tailings, which may have served to drain trapped water from behind the Dam to prevent overflow. 169 C.
Main Components: Key components of the Argonaut Mine Dam include the thirteen-arch concrete impoundment Dam and the impounded mine tailings that originated from the Argonaut Mine Company s stamp mill and cyanide processing plant. The tailings fill the impoundment to approximately 2 to 3 below the Dam crest. The Dam measures approximately 46 in height at its tallest point and spans approximately 420 , with abutments in the high slopes along the edge of a creek drainage basin. The Dam s repeating arches, horizontal tie beam, diagonal seams, imprinted board-formed concrete, and exposed rebar illustrate the structure s construction methods.
The impoundment is nearly filled with tailings, with approximately 2 to 3 of the upstream face exposed between the crest of the Dam and the top of the fill. The associated Argonaut Mine was an approximately 330-acre hard rock gold mine site, with the main head frame and processing buildings located approximately north of the Dam. The Dam, along with two additional earthen embankment dams, impounded tailings from the mine s cyanide processing plant.
The cyanide plant covers approximately 6.5 acres and contains above-ground and partially buried concrete tanks, vats, and a thickening basin, as well as drainage channels, pipes, and other objects that remain as evidence of metallurgy practiced at the site.170 In addition to the Dam, the tailings area contains a 5-acre unprocessed and semi-processed ore storage area near the west end of the property, the cyanide plant area, and tailings impoundments behind two earthen dams built from tailings. The three tailings impoundments are situated southeast of the cyanide plant in a drainage valley covering approximately 48 acres. The upper tailings impoundment in an earthen tailings dam is in a sparsely vegetated area.
The middle tailings impoundment in the lower earthen tailings Dam has a wetland, with several deep erosional pits located near the Dam. The lower tailings impoundment is held by the Dam and has a wetland.171 Since the mine ceased operations in approximately 90 acres of the former mining property has been redeveloped as residential subdivisions. 169 Ibid., 67. 170 Ibid., 1. 171 Weston Solutions, Inc., 3. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 31 D. General Site Description: The Dam is located at the mouth of what was originally a relatively small northwest-to- southeast-oriented gully tributary of North Fork Jackson Creek in the western foothills of the Sierra Nevada physiographic province in the Jackson Creek drainage basin.
This drainage lies between the drainage basins of the Cosumnes and Tuolumne Rivers. The gully is almost entirely filled with sediment largely derived from the mine tailings. West of the Dam, the impounded tailings fill the ravine behind the Dam to within 2 to 4 of its crest in a vegetated and somewhat boggy wetland area. East of the Dam is the surviving end of the otherwise buried ravine and a steep slope to the south. The natural topography has been disturbed by the post-1962 construction of Sutter Street and circa construction of Argonaut Drive. Filling for these roads has created a depression in front of the Dam. This area in front of the Dam had long been overgrown with vegetation, which was recently cleared to allow access for monitoring and assessment.
The Dam is situated between a residential and rural area. To the north are residential properties and a pasture; to the west are the Argonaut High School, Amador Superior Court, and pasture land; to the south is pasture land; and to the east are residential properties and Jackson Junior High School. The surrounding terrain is characterized by gently rolling topography that is controlled regionally by several northwest-trending fault systems, as well as more locally by stream incision. The Mineral Land Classification of the Sutter Creek 15-Minute Quadrangle indicates the mine site is associated with metavolcanic and metasedimentary rocks of the Upper Jurassic Mariposa and Logtown Ridge Formations.
The Mariposa Formation is significant because the majority of the gold-bearing quartz veins of the so-called Mother Lode belt are associated with this geologic unit. The Site Inspection Report for the Argonaut Mine states that gold deposits are in a north- and northwest-trending mile-wide belt of gold gray to black slate.172 Soils immediately above the Dam are mapped as Mine Tailings and Riverwash derived almost entirely from historic mining activities. The Auburn and Argonaut soil mapping units surround the area, both of which are formed largely in weathered bedrock. It is likely that one or both of these soils comprised the project area prior to construction of the Dam and impoundment of runoff from the mine tailings. 173 172Weston Solutions, Inc., 9.
173United States Department of Agriculture Natural Resources Conservation Service, Web Soil Survey, (accessed January 27, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 32 Part III. Sources of Information A. Primary Sources Ancestry.com. Who's Who on the Pacific Coast, [database on-line]. Provo, UT, USA: Ancestry.com Operations, Inc., Argonaut Co. s Tailings Dam. Mining and Engineering World 45 (November 11, Axtell, Mel D. Biographys [sic] of Kennedy Mine Notables. Jackson, California: Amador County Historical Society California. World Mines Register 13 California Mines in Mining and Scientific Press 115 (September 1, Eastwood, John S. Stresses In The Multiple Arch Dam. John S.
Eastwood Papers, Water Resources Collections and Archives, University of California, Riverside, California. Eddy, Lewis H. The Argonaut Mine, Calif. Engineering and Mining Journal no. 6 (August 5, Hamilton, Fletcher. A Review of Mining in California During Preliminary Report No. 8. San Francisco: California State Mining Bureau, January Late News From the World s Mining Camps. Mining and Engineering World 45 (December 30, Logan, Clarence August. Mother Lode Gold Belt of California. Bulletin No. San Francisco, California: State Division of Mines, November (accessed on November 16, Marliave, Chester. Memo Concerning Geology at Multiple Arch Dam Sites, Argonaut Dam July 24, News by Mining Districts. Engineering & Mining Journal no. 12 (September 16, The Mining Summary.
Mining and Scientific Press 109 (July 25, Review of Mining. Mining and Scientific Press 114 (April 7, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 33 Review of Mining. Mining and Scientific Press 114 (April 21, Review of Mining. Mining and Scientific Press 118 (June 28, Roeber, Eugene Franz, ed. Construction and Operation: California. Metallurgical and Chemical Engineering 16, no. 3 (February 1, Sanborn Fire Insurance Company. Jackson, California, Jan. revised May sheet 9. State of California Department of Public Works Division of Water Resources. Record of Inspection of Dam, Argonaut, No. Tucker, William Burling. Mines and Mineral Resources of Amador County, Calaveras County, Tuolumne County.
San Francisco, California: California State Mining Bureau, September Vanderburg, W.O. Mining Methods and Costs at the Argonaut Mine, circular Amador County, California: Bureau of Mines Information, B. Secondary Sources Amador Gold, Argonaut Mine, Jackson, Amador County. (accessed on November 16, Arthur Bent of Los Angeles. Successful Methods: A Magazine of Construction Services, December o&sig=35MWpWcPG- (accessed on November 16, Baxter, R. Scott and Kimberly J. Wooten. Breweries of the Gold Country. Charleston, South Carolina: Arcadia Publishing, Berriman, Clyde R. Kennedy Tailing Wheels. National Register of Historic Places Nomination, United States Department of the Interior, Billington, David P. and Donald C. Jackson.
Big Dams of the New Deal Era: A Confluence of Engineering and Politics. Norman: University of Oklahoma Press, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 34 Calaveras Heritage Council. Calaveras Central Gold Mining Company. (accessed on November 17, California Department of Transportation. Historical Context and Archaeological Research Design for Mining Properties in California. Sacramento, California: Division of Environmental Analysis, California State Parks, Office of Historic Preservation. Argonaut and Kennedy Mines, Historical Landmark. (accessed on November 17, Carlson, Denton W. and William B. Clark. Mines and Mineral Resources of Amador County. California Journal of Mines and Geology 50, no. 1, January Cenotto, Larry.
Logan s Alley: Amador County Yesterdays in Picture and Prose, Vol 1. Jackson, California: Cenotto Publications, Clark, William B. Gold Districts of California, Bulletin Sacramento, California: California Division of Mines and Geology, (accessed on November 17, Cook, Deborah Coleen. Jackson. Charleston, South Carolina: Arcadia Publishing, Davis, William J. (ed.). Northern California and Builders. The Argonaut, San Francisco, California, Ecology and Environment, Inc. Sampling and Analysis Plan, Argonaut Mine Tailing Pile Assessment, Jackson, California. Prepared for U.S. Environmental Protection Agency, Region 9, July Gregory, Cedric E. A Concise History of Mining (Rev. Ed.). Lisse, The Netherlands: Swets & Zeitlinger Hill, Mary. Gold: The California Story.
Berkeley: University of California Press, History of Amador County, California with Illustrations and Biographical Sketches of its Prominent Men and Pioneers. Oakland, California: Thompson & West, Hoover, Mildred Brooke, Hero Eugene Rensch, and Ethel Grace Rensch. Historic Spots in California. 3rd ed. Stanford, California: Stanford University Press, ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 35 Jackson, Donald C. Building the Ultimate Dam: John S. Eastwood and the Control of Water in the West. Lawrence: University Press of Kansas, Jackson, Donald C. Considering the Multiple Arch Dam: Theory, Practice and the Ethics of Safety in a Case of Innovative Hydraulic Engineering. Natural Resources Journal 32 (Winter Jackson, Donald C. Great American Bridges and Dams.
New York: John Wiley & Sons, Jackson-Plymouth. Gold Districts of California. Oakland Museum of California, (accessed on November 16, Johnson, Bernard. Arthur Samuel Bent. Find A Grave. (accessed November 16, Jones, Ray and Joseph Lubow. Disasters and Heroic Rescues of California: True Stories of Tragedy and Survival. Guildford, Connecticut: Globe Pequot, Kirkemo, Harold, William L. Newman, and Roger P. Ashley. Gold. Washington, U.S. Department of the Interior. (accessed on November 16, Levy, Richard. Eastern Miwok. In Handbook of North American Indians, vol. 8 California, edited by William C. Sturtevant and Robert F. Heizer. Washington Smithsonian, Lilienthal, Lillie Bernheimer. In Memoriam: Jesse Warren Lilienthal. San Francisco: John Henry Nash, (accessed November 16, Martin, T. E.
and Davies. Trends in the Stewardship of Tailings Dams. AGRA Earth & Environmental Limited, Burnaby, Canada, (accessed November 17, Marvin, Judith. National Register of Historic Places Evaluation of the Argonaut Eastwood Multiple Arch Dam, Jackson, Amador County, California. Sonoma State University: Anthropological Studies Center, September ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 36 Meyer, Martin A. The Jews in California. In Western Jewry: An Account of the Jews and Judaism in California. San Francisco, California: Emanu-el, Muratore, Kim. Memorandum: Releasable Chronology of the Argonaut Mine Site Ownership & Operation. United States Environmental Protection Agency, Region 9. January 28, 9. (accessed on February 27, Napoli, Donald S.
Jackson Downtown Historic District. National Register of Historic Places Nomination, United States Department of the Interior, Poultney, John. Amador County. Charleston, South Carolina: Arcadia Publishing, Rasmussen, Cecilia. Gold Mine Disaster Was State s Deadliest. Los Angeles Time. January 15, Sierra Nevada Geotourism. Argonaut and Kennedy Mines (No. 786 California Historical Landmark). US Army Corps of Engineers (USACE). Argonaut Dam Stability and Retrofit Alternative Investigation, Jackson, CA. Phase I Technical Report. Prepared for Environmental Protection Agency, Prepared by U.S. Army Corps of Engineers, Sacramento District, Sacramento, California, United States Army Corps of Engineers (USACE).
Argonaut Mine Dam Phase II Technical Report Stability and Retrofit Alternative Investigation, Jackson, CA. Sacramento District, December 18, United States Department of Agriculture, Natural Resources Conservation Service. Web Soil Survey, (accessed January 27, United States Environmental Protection Agency (EPA), Office of Solid Waste, Special Waste Branch. Technical Report: Design and Evaluation of Tailings Dams. August United States Environmental Protection Agency (EPA), Region 9. Area of Potential Effects, Argonaut Mine Eastwood Multiple Arch Dam (EMAD) Retrofit, October 5, United States Geologic Survey (USGS). Argonaut Mine. Mineral Resources On-Line Spatial Data. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No.
CA-2330 Page 37 (accessed February 27, citing Clark, Argonaut Mine tailings, Amador County: Unpublished preliminary report 64, California Division of Mines, URS. Argonaut Dam Basis of Design Report. February Varney, Phillip. Ghost Towns of Northern California. Stillwater, Minnesota: Voyager Press, Inc., Wagner, Jack R. Gold Mines of California: An Illustrated History of the Most Productive Mines with Descriptions of the Interesting People Who Owned and Operated Them. Berkeley, California: Howell-North Books, Walker, Mark K. and Dana Ogo Shew. A Cultural Resources Inventory and Evaluation of the Argonaut Mine Cyanide Plant and Tailings Site, Jackson, Amador County, California.
Prepared for US Environmental Protection Agency, Region 9, San Francisco, California, April 29, Weston Solutions, Inc. Site Inspection Report, Argonaut Mine. Prepared for U.S. Environmental Protection Agency, Region 9, July Whitney, Charles Allen. John Eastwood: Unsung Genius of the Drawing Board. The Magazine of Western History 19 (Summer Young, Otis E. Western Mining. 5th ed. Norman: University of Oklahoma Press, Part IV: Project Information A. Contacts: 1. Kirk Ranzetta, Senior Architectural Historian, AECOM. B.
Prepared By: Kirk Ranzetta, Project Manager and Senior Architectural Historian, AECOM; Shoshana Jones, M.A., Architectural Historian, AECOM; Patience Stuart, Architectural Historian, AECOM; Leesa Gratreak, Architectural Historian, AECOM; James Mayer, RPA Geo-Archaeologist, AECOM. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 38 Appendix A Site Plan, Maps, and Plans (Note: Several historical maps and plans have been redacted from the HAER submittal but are available upon request from the applicable repository. A list of the removed images is included for reference after the site plan.) ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 39 ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 40 List of Additional Maps and Plans 1.
Plan and Upstream Elevation Drawings of Dam, by U.S. Army Corps of Engineers (USACE 2. Sanborn Fire Insurance Map of Jackson, CA, January revised May sheet 9. ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 41 Appendix B Historic Images (Note: Historical images have been redacted from the HAER submittal but are available upon request from the applicable repository. A list of the removed images is included for reference.) ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 42 List of Historic Images and Sources 1. Drawing of Jackson by Charles Parish, (Cook, 2. Geologic Map of Jackson-Plymouth District, Amador County, showing mine locations (Clark, William B.
Gold Districts of California, Bulletin Sacramento, California: California Division of Mines and Geology, (accessed on November 17, 3. John S. Eastwood, Designer for Dam, 4. Arthur Bent, Bent Brothers, Los Angeles, California, Contractors for Dam, The Bulletin of the General Contractors Association, Volume 11, General Contractors Association, February 28. 5. Jesse W. Lilienthal, President of Argonaut Mining Company Lillie Bernheimer Lilienthal, In Memoriam: Jesse Warren Lilienthal (San Francisco: John Henry Nash), Available at epage&q=mining&f=false . 6. Argonaut Miners, Jackson, California Available at 7. Argonaut Mine Headframe, William Burling Tucker, Mines and Mineral Resources of Amador County, Calaveras County, Tuolumne County, California State Mining Bureau, 18. 8.
Dam, Downstream (East) Face, view facing northwest. Mining and Engineering World 45, November 11, 9. Dam, Downstream Face (East), view facing southwest. Engineering and Mining Journal no. February 14, 10. News by Mining Districts, Engineering & Mining Journal no. 12, September 16, 11. Argonaut Dam, Memorandum to Mr. Hawley Argonaut Dam No. 478 inspected (State of California Department of Public Works Division of Water Resources). ARGONAUT MINE EASTWOOD MULTIPLE ARCH DAM HAER No. CA-2330 Page 43 12. Argonaut Dam, Inspection by Gerald McKinlay (State of California Department of Public Works Division of Water Resources). 13. Argonaut Dam, Inspection by State of California Department of Public Works Division of Water Resources. 14.
Argonaut Dam, Inspection by State of California Department of Public Works Division of Water Resources. 15. Argonaut Dam Spillway Entrance, Division of Water Resources estimate of spillway requirements for Argonaut Dam No. 478 (State of California Department of Public Works Division of Water Resources).