Lock C9, located on the Champlain Canal, is significant as a component of the nationally significant New York State Barge Canal and is typical of the lock sites built along the canal system. Description: Lock C9 is located 6 miles north of Lock C8 and consists of the lock and associated structures and equipment and the lockhouse.1 It is accessed via a long and winding asphalt road from Route A gravel and dirt visitor parking area is located on the west side of a concrete bridge separating the access road from the lock. Lock operator parking is available at an asphalt lot next to the lock. The modern lockhouse sits on the west side of the lock. The structure appears to have been built of square concrete tiles but is actually of patterned concrete block.
Asphalt shingles cover the gabled roof. The roof extends beyond the building at both gable ends. Sliding vinyl windows with steel mesh storm windows light the structure. Steel doors provide entry. A public restroom is incorporated into the lockhouse. The building is in good condition. The storehouse, also located on the west side of the lock and near the lockhouse, is a one-story frame structure clad in shiplap novelty siding that sits on a concrete foundation. Asphalt shingles cover the gable-front roof. One-over-one vinyl windows light the structure. The building is accessed via a modern steel hollow door. The only remnant of the powerhouse, originally located on the east bank of the lock chamber, is a concrete slab foundation.
The lock has a 16' lift with normal pool elevations below and above. Its concrete chamber walls feature vertical cut-outs for pipe mooring aides and are in fair condition. The double-leaf steel miter gates and the valves in the chamber culverts operate via direct-acting hydraulic cylinders that replaced the original DC electro-mechanical equipment. The lock features diamond-plate and open-grate covers, catwalks, and concrete stairs that are in poor condition. Modern light fixtures illuminate the lock site. The gates and valves are operated from 1 Description of current conditions is based on a site visit made by the HAER recording team in summer and historical maps from Series New York State Archives, Albany, New York. See Eastern Division, Champlain Canal, Section 2, Sta. 831 + 50 to Sta.
779 + 00, approved April 2, 84. NEW YORK STATE BARGE CANAL, LOCK C9 HAER No. (Page 2) control stand shelters on the west bank of the lock chamber. The shelters are flat-roof, steel frame, with three walls of partially transparent panels of plexiglass and a fourth filled in with wood doors and vertical boards. The lock is in generally good condition. The northeast concrete approach wall exhibits excessive spalling and cracking and is in poor condition. The northwest approach wall is in fair condition with minor spalling. A dock with wood decking and a railing was appended to this wall. Modern reproduction light fixtures are located along the dock. The southeast concrete approach wall is in poor condition with excessive spalling in areas.
The southwest concrete approach wall has modern metal and concrete cleats and is in fair to poor condition. In addition to the spillway and fixed crest dam on Wood Creek (see HAER No. a spillway is located on East Creek. The East Creek Spillway consists of a concrete apron flanked by two concrete walls. A steel plate wall is visible on the north side of the spillway. The concrete superstructure is in fair condition, with areas of breakage and sections that have been overgrown with vegetation. History: Lock C9 was built as part of Contract 25, which encompassed excavating the canal, building Champlain Canal locks 9 and 10 (which was never built), spillways, power plants and other structures, bridge substructures and approaches, highways and retaining walls.
The total length covered by the contract was 13 miles, and it was awarded to Atlantic, Gulf and Pacific Company on November 19, Work began in April when the contractor began erecting dikes. Dredging started in August. By the concrete work for the lock had been completed, aside from the northwest approach wall, and the lock was finished in The construction of the lock gates, needle beams, needles and lock valves at Lock C9 was covered under Contract No. 32, which was awarded to Penn Bridge Company on April 19, The contract also covered Champlain Canal locks 6 and 8. C.A.
Curtis, State Assistant Engineer, had oversight of the project, which began in December and had been completed by May The contractor s work consisted of placing needle-beams, erecting and riveting the gates and installing the valves. The quoin posts, toe posts and fenders were built on the ground of white oak, while the needles were built of yellow pine.3 The operating equipment and lighting for Lock C9, along with Champlain Canal locks 11 and 12, was part of Contract 90, let on April 12, to D Olier Engineering Company of Philadelphia, Pennsylvania. State Assistant Engineer A.R. Morse oversaw the work.
By the powerhouse had been completed, aside from the roof, and the turbines and generators were in 2 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 95; Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 3 Annual Report, 91; Noble E. Whitford, History of the Barge Canal of New York State (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, NEW YORK STATE BARGE CANAL, LOCK C9 HAER No. (Page 3) place.
The contractor had also installed the gate and valve operating machinery, control panels and cabinets, and conduit. The work was completed in Later work at Lock C8 involved removing the existing gates and installing new gates and electrical equipment at locks C8 and C9 in as part of Contract The lock was rehabilitated in under Contract which included construction of a new lockhouse and installation of the new valve and gate operating machinery.5