New York State Barge Canal, Lock E3, Washington Avenue, north of Knox Street, Waterford

New York State Barge Canal, Lock E3, Washington Avenue, north of Knox Street, Waterford, Saratoga County, NY. Surveyed as HAER NY-372, with a 2,037-word written history.

From the record

“Lock E3, located on the Erie Canal, is significant as a component of the Waterford Flight of Locks, described as the greatest series of high lift locks in the world at the time of their construction.1 The Waterford Flight of Locks is part of the nationally significant New York State Barge Canal.”

Written record, HAER NY-372 survey. Machine-read text.

Surveyed by the federal HAER program as HAER NY-372 · the record runs 2037 words · one of 44 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Significance

1299 words

Source document Quoted word for word from HAER NY-372. Not written, edited or summarised by this site.

Lock E3, located on the Erie Canal, is significant as a component of the Waterford Flight of Locks, described as the greatest series of high lift locks in the world at the time of their construction.1 The Waterford Flight of Locks is part of the nationally significant New York State Barge Canal. Description: Lock E3 is the second lock in the Waterford Flight of Locks on the Erie Canal.2 An asphalt road provides access to the site. It crosses the spillway at the end of the bypass channel that parallels the lock on a steel I-beam bridge with an open-grate deck, pipe railings, and riveted-steel vertical truss supports. The bridge sits on the spillway s concrete substructure. An asphalt parking area features modern post-and-rail and chain-link fencing.

The lock site consists of the lock and associated structures, a spillway, powerhouse, lockhouse, and bypass channel that parallels the lock to the north. The lock has a lift with normal pool elevations of below and above. There are double-leaf, steel miter lock gates at each end of the chamber, operated by spars and gear trains powered by electric motors. The flow of water through the culverts in the chamber walls is controlled by valves also operated by electric motors. Control stand shelters are located on the west side of the chamber on the upstream and downstream corners. The frame shelters have fiber-cement board siding, asphalt-shingled pyramidal roofs, vinyl multi-light, double-hung sash windows, and vinyl doors.

The lock has open-grate metal stairs and modern reproduction light fixtures. The lock and control stand shelters are generally in good condition. The lockhouse sits on the south side of the chamber near the upper gates. It is a one-story, frame structure clad in fiber-cement clapboards. Asphalt shingles cover the gable-front roof, which has exposed rafter tails. Modern one-over-one-light vinyl windows comprise the fenestration. A modern pane-and-panel door provides access. The building is in good condition. 1 Noble Whitford, History of the Barge Canal of New York State (Albany: Lyon Company, Printers, 2 Description of current conditions is based on a site visit made by the HAER recording team in summer and a historical map from Series New York State Archives, Albany, New York.

See Eastern Division, Erie Canal, Section 1, Sta. 199 to Sta. approved March 29, 3. NEW YORK STATE BARGE CANAL, LOCK E3 HAER No. (Page 2) The powerhouse is north of the lockhouse. The one-story concrete building has a hipped roof covered with the original glazed clay tiles. The building is lit by nine-over-nine-light single- hung wood windows and three-light hopper windows under the eaves. Entrance to the building is by bead-board paneled, double doors with a four-light transom. The original motor-generator set has been removed and replaced with a modern solid-state rectifier; the original bridge crane is also gone. The powerhouse is in good condition despite the alterations. The concrete approach walls are in good to fair condition, with some areas of spalling.

The concrete retaining walls are also in good to fair condition, but they exhibit more areas of spalling than the approach walls. The concrete guide walls are in good condition. The bypass channel carries excess water around the lock and has concrete and stone walls and a steel water supply pipe. The walls are in variable condition, with some sections exhibiting spalling and cracking. At the end of the bypass is the spillway, a three-span concrete structure equipped with a stop-log and valve at the west end. The spillway is in good condition. History: Building a canal west from the Hudson River in the Waterford area was challenging because of the Cohoes falls.

As Noble Whitford describes it, prior surveys had located the route of the canal near the falls, but engineers discovered a land line from the Hudson to the Mohawk located 2- miles from the falls and quickly realized it provided the best route. To overcome the change in elevation, five locks separated by pools were necessary, creating the greatest series of high lift locks in the world with lifts ranging from to for a total of There were also bypass channels at all the locks, as well as two guard gates at the end of what became known as the Waterford Flight.

The bypass channels were in place to regulate the flow of water into the pools separating the locks, thereby insuring ample water for lockage and minimizing the risk of flooding.3 Contract 2, covering the construction of locks E2 and E3 and the prism through Waterford, was awarded in April to the Ferguson Contracting Company. The contract included excavating and protecting the sides of the canal from the Mohawk River to a point -mile west of the head of Lock E3. The total length of the contract was .91 miles. The Annual Report noted that the contractor mixed all the concrete at a central mixing plant and then transported it in buckets on flat cars to the site. By the lock was estimated to be 94 percent complete.

The core walls and spillway had been finished, and excavation of the prism had been done above Lock E3. The remainder of the work was completed as part of Contract 2E with the work reassigned to Holler & Shepard in The new contractors finished excavating the remainder of the lower approach walls for Lock E3 and replacing 30' of the concrete of the north lower approach wall.4 3 Whitford, quote from Michelle McFee, A Long Haul: The Story of the New York State Barge Canal (Fleischmanns, NY: Purple Mountain Press, 4 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 74, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol.

1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 53; Whitford, NEW YORK STATE BARGE CANAL, LOCK E3 HAER No. (Page 3) Construction of the power plant was part of Contract 92, awarded to MacArthur Bros. Co. & Lord Electric Co. in That year, the transmission line from the powerhouse at Crescent Dam to Lock E3 was completed. Aside from the woodwork and painting, the powerhouse was finished. The changes to the upper gate machinery recesses had been completed, and the metal duct extending from the substation to the end of the light line on the upper left approach walls was in place.

The following year, the electrical equipment had been installed, and the lamp poles erected.5 The lock gates and valves were included in Contract 33, awarded to Penn Bridge Company on January 7, Work began in November at Lock E2 and progressed along the other locks making up the Waterford Flight. The work at locks E2 and E3 was under the supervision of State Assistant Engineer O. Hasbrouck.6 Various repairs and alterations were made to the lock after its initial completion. A leak between locks E2 and E3 required additional sealing with steel sheet piling and cinders in That same year, extensive repairs were made to the road to the lock.

In the lower lock gates were replaced as part of Contract The gate sills were lowered and new quoin posts were installed, as well as new pivots and sockets at the upper lock gates. The Department of Public Works embarked upon a campaign that year to lower approximately thirty-two lock sills on the canal so as to provide a minimum 13' depth. Further alterations were evidently made to the sills and gates in under Contract US87. The lower gates were rehabilitated at Lock E3 as part of Contract in

Sources

463 words

Source document Quoted word for word from HAER NY-372. Not written, edited or summarised by this site.

Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, 5 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol.

1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 6 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 60; Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 48- 49. 7 State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (Albany: Williams Press, Inc., 27; State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (Albany: Maintenance Contracts, NEW YORK STATE BARGE CANAL, LOCK E3 HAER No.

(Page 4) Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1. Albany: Lyon Company, Hay, Duncan. New York State Barge Canal. National Register of Historic Places Registration Form, Maintenance Contracts, McFee, Michelle. A Long Haul: The Story of the New York State Barge Canal. Fleischmanns, NY: Purple Mountain Press, Series New York State Archives, Albany, New York. Eastern Division, Erie Canal, Section 1, Sta. 199 to Sta.

approved March 29, 3. State of New York, Department of Public Works. Annual Report of the Superintendent for the Year Albany: Williams Press, Inc., Annual Report of the Superintendent for the Year Albany: Whitford, Noble. History of the Barge Canal of New York State. Albany: Lyon Company, Printers, Historians: Laura S. Black and Jami Babb, summer

Written history

170 words

Source document Quoted word for word from HAER NY-372. Not written, edited or summarised by this site.

The Historic American Engineering Record (HAER) is a long- range program that documents and interprets historically significant engineering sites and structures throughout the United States. HAER is part of Heritage Documentation Programs (Richard O Connor, Manager), a division of the National Park Service, United States Department of the Interior. The New York State Barge Canal Survey was undertaken in summer in cooperation with the Erie Canalway National Heritage Corridor (ERIE), Beth Sciumeca, Executive Director. Justine Christianson, HAER Historian, and Duncan Hay, ERIE, served as project leaders. The staff of the New York State Canal Corporation provided access to the sites. Craig Williams of the New York State Museum provided research materials and assistance.

The HAER field team consisted of Jami Babb and Laura Black. NEW YORK STATE BARGE CANAL, LOCK E3 HAER No. (Page 5) Appendix: Images of Current Conditions Image 1: Lockhouse. Field photograph taken by HAER recording team, summer Image 2: Powerhouse at right and control stand shelter at left. Field photograph taken by HAER recording team, summer

In context

Waterford, New York The place record: every map, photograph and survey of this town.
Saratoga County, New York 233 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Waterford

12 records

The federal surveyors worked through Waterford building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
New York State Barge CanalHAER NY-3712,640 words
New York State Barge CanalHAER NY-3752,191 words
New York State Barge CanalHAER NY-3762,136 words
New York State Barge CanalHAER NY-3742,070 words
New York State Barge CanalHAER NY-3482,040 words
New York State Barge CanalHAER NY-3771,894 words
Champlain CanalHAER NY,46-WAFO,1-1,616 words
Champlain CanalHAER NY,46-WAFO,2-1,451 words
New York State Barge CanalHAER NY-3791,225 words
New York State Barge CanalHAER NY-378933 words
New York State Barge CanalHAER NY-373744 words
New York State Barge CanalHAER NY-370727 words

Provenance

  • Written history. Quoted verbatim from HAER NY-372. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.