Lock E24, located on the Erie Canal, is a component of the nationally significant New York State Barge Canal. Description: Lock E24 is on the south bank of the Seneca River east of Route The lock is accessed by an asphalt drive that runs along the north side of the lock into a small asphalt parking area. The site consists of the lock and associated structures, lockhouse, various sheds, and a guard gate. The lock has an 11' lift to the west with normal pool elevations of below and above. The concrete chamber walls have been lined with mild-steel plates, and there is cast-iron quarter- round coping. There are double-leaf, steel miter lock gates at each end of the chamber operated by spars and gear trains powered by DC electro-mechanical gate machinery.
The flow of water through the culverts in the chamber walls is controlled by valves also operated by DC electro- mechanical machinery. Control stand shelters are located on the north side of the chamber at both the upstream and downstream corners. The shelters are one-story frame buildings with horizontal wood siding and pyramidal asphalt roofs. There are wood one-light pop-out windows, and each has a pane-and-panel door. Concrete-filled cast-iron bollards sit on concrete pads and line either side of the chamber. Chain-link fencing and pipe railings surround the public access side of the lock, which is illuminated by historic light fixtures. The lock appears to be in good condition. A utility bridge spans the center of the lock chamber and is in good condition.
A set of open-grated stairs with concrete abutments and lined with pipe railing is located at the east end of the lock. The concrete abutments exhibit some spalling, so the stairs are in fair condition. At the upstream end of the lock chamber, just outside the lock gates, is a vertically-sliding guard gate. The riveted-steel superstructure sits on a concrete foundation. The steel gate has steel skin plates on the upstream side. The reinforced-concrete and steel counterweights operate with a cable system. A modern machinery cabinet is located on the top of the gate superstructure. The guard gate is in good condition. The powerhouse was removed from this site at some point, and there are no remnants of its former location on the north wall by the downstream gates.
1 Description of current conditions is based on a site visit by the HAER recording team in summer NEW YORK STATE BARGE CANAL, LOCK E24 HAER No. Page 2 The lockhouse is located at the northeast corner of the lock chamber. It is an irregular one-and- a-half-story concrete block building that sits on a concrete foundation. The hipped roof is covered with asphalt shingles and has sloping edges and gabled dormers. The dormers are covered with asphalt shingles and wood siding and have one-over-one-light vinyl windows. The fenestration on the first floor consists of two-over-two-light wood windows with steel mesh coverings. The entrances are wood pane-and-panel doors, one of which has a wood screen door.
Decorative exterior details include rusticated concrete block and partial quoins on the fa ade. The interior features hardwood floors and paneled walls. The lockhouse is in good condition. There are several sheds, include a storage shed on the access road, adjacent to the parking lot. This is a single-story gable-front frame shed that sits on a poured concrete foundation. The exterior is clad in shiplap siding pierced by six-over-six-light wood windows and a panel wood door. The gable roof is clad in asphalt shingles that are in poor condition. This storage shed is in good condition. A small modern shed is located south of the lock and parking area. The single- story metal building sits on a concrete foundation. It is in good condition.
Another modern storage shed is located next to the lockhouse. This one is a single-story frame building on a concrete foundation. It has vertical-board siding, a front gable roof covered with asphalt shingles, and a wood entrance door. It is in good condition. The concrete of the northeast guide wall is severely spalling and breaking in areas, although some repairs have been made. Concrete-filled cast-iron bollards line the wall, and there is a modern guide light. The northeast guide wall is in fair condition. The northwest guide wall is steel with concrete infill and a steel cap. The sections near the guard and lock gates are in poor condition. Concrete-filled cast-iron bollards line wall, along with reproduction light fixtures. This wall is in fair condition.
Finally, the southeast guide wall is lined with concrete-filled cast- iron bollards and is in good condition. History: Lock E24 was built as part of Contract 45, awarded on May 6, to Scott Brothers.
Work began in June, and the masonry work at the site had been completed by the end of The lock gates and valves were installed, and the contract was completed in The original plaques from the lock gates are in the lockhouse and read: Whitehead & Kales and Scott Brothers, 2 The power plant was built as part of Contract 90, awarded to D Olier Engineering Company on April 6, The foundation of the powerhouse was laid that year, and the structure was nearly complete at the end of Later work at the site included the installation of the guard gate in The gate was removed from Port Gibson, with one leaf installed at Lock E23 (see HAER and the other at this 2 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol.
1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, and Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 3 Annual Report, Annual Report, NEW YORK STATE BARGE CANAL, LOCK E24 HAER No. Page 3 lock. In the new oak quoin posts, miter posts, and sills were installed. Nine years later, the Annual Report described the erection of towers and an overhead buffer beam at the end of the lock. Repairs were made to the upper and lower approach walls in under Contract The lower gates were replaced as part of Proposal No. (Contract