HISTORICAL INFORMATION A. Physical History: 1. Date of erection: (completed February 26, (Report of Chief of Engineers, U.S. Army, p. 2. Architect: U.S. Army Corps of Engineers 3. Original and Subsequent Owners: U.S. Army Corps of Engineers 4. Builder, Contractor: E. H. Latham Company 5. Original Plans: Proposal No. Standard and Government Form of Invitation for Bids (Construction Contract), September 7, War Department, U.S. Engineers Office, Jacksonville. 6. Alterations and Additions: Two machinery houses constructed circa (Lake Okeechobee Project, Hurricane Gate Operators Houses, Proposal No. by Contractor Paul H. Smith ("Copies of Specifications and Completed Contracts", Principal Engineer J. R. Peyton, U.S. Corps of Engineers).
The original gate structure was mechanically operated with a manual capstan. In the manual capstan was replaced with an electrically operated Limitorque. The handwheel on the electrical unit could still be used in emergencies, but was considered impractical because of the excessive number of turns required to open the gate fully. In an LP gas engine with a belt drive was added to serve in case of a commercial power failure. (Hurricane Gates No. 2, 3, 4, and 5. Periodic Inspection Report No. 1 (September Appendix III - Pre-Inspection Brochure B.
Historical Context: Hurricane Gate Structure 5 is one of five such structures authorized for construction in Lake Okeechobee by the River and Harbor Act of July 3, in accordance with Senate Document 7ist Congress, 2Hi Session, as part of a levee and navigation channel pro- ject. This authorization represented the culmination of a series of natural and political events in the area. Concern with water management in Central and Southern Florida has per- sisted since the Drainage of wetlands allowed land reclamation and resultant land sales and agricultural development. Prior to the Everglades Drainage District took responsibility for regulating Lake Okeechobee. By the canals to the lake had been constructed to allow navigation, including the West Palm Beach Canal now regulated by HGS 5.
By the Everglades Drainage District began experiencing serious financial problems, and by July all construction work halted. This finan- cial crisis was bracketed by two natural disasters. Earlier in a serious hurricane resulted in property damage and the loss of 400 lives near Moore Haven. Later, in another more serious storm resulted in HURRICANE GATE STRUCTURE 5 HAER No. (Page 3) flooding up to 8 feet and deaths by drowning. Relief from the Red Cross totaled over $2 million. These problems created the need for a new local agency to control water management in Central and Southern Florida and inspired the involvement of the Federal government in the process as well.
In response to these developments, the Florida Legislature created the Lake Okeechobee Flood Control District (Chapter Laws of Florida, Acts of to protect life and property from flooding in the areas around Lake Okeechobee and the Caloosahatchee River. As part of an effort to encourage federal involvement in water management, this newly created District hired George B. Hills, Hills Consulting Engineer of Jacksonville, Florida to prepare a history of the area and a proposal for future flood control efforts (Senate Document No. 7l Jl Congress, 3ll Session, April 30, An act proposing Federal adoption of the Lake Okeechobee project was introduced in Congress in December and referred to the House Flood Control Committee. Despite the national attention given the and hurricanes, the U.S.
Government was not interested in flood control projects at this time (with the exception of the Mississippi Valley). Consequently, the act was transferred to the Rivers and Harbors Committee for consideration as a navigation project where it was successfully translated into the River and Harbor Act of signed by President Herbert Hoover. The project was adopted essentially as defined by the "Caloosahatchee River-Lake Okeechobee Drainage Areas.
Florida" report prepared by the War Department (Senate Document Congress, Session, March 15, This report recommended the following: That the United States improve the Caloosahatchee River and Canal from Lake Okeechobee to the Gulf of Mexico by straightening and by dredging a channel which will provide a discharge outlet capacity of cubic feet per second from Lake Okeechobee and a navigation channel at least 6 feet deep and 80 feet wide, including the necessary control works, at an estimated cost of improve Taylor's Creek by providing a channel 6 feet deep and 60 feet wide from Okeechobee City into Lake Okeechobee at an estimated cost of provide a levee and a navigation channel 6 feet deep and 80 feet wide following in general the south shore of the lake at an estimated cost of improve the St.
Lucie River to provide a channel 6 feet deep and 80 feet wide at an esti- mated cost of provide for the protection of the St. Lucie Canal from erosion and silting at an estimated cost of the levees to be subject to modifications of location and design at the discretion of the Chief of Engineers; provided that the State of Florida, or other local interests contribute toward the cost of the above improvements, furnish evidence satisfactory to the Secretary of War that they will construct the north shore levee to a design to be approved by the Chief of Engineers, esti- mated to cost provide all lands needed for levees, HURRICANE GATE STRUCTURE 5 HAER No.
(Page 4) channels, and the disposal of spoil, agree to maintain all work and channels within the limits of the Everglades drainage district and to charge no tolls on any of these navigable waterways and agree that whenever authorized by Congress the United States shall have the right to modify or improve any of these waterways and their appurtenant structures. It is further recommended that in adopting the project Congress expressly provide that the St. Lucie Canal, the Caloosahatchee Canal, and the other channels forming the proposed cross-State waterway, shall be navigable waters of the United States and subject to the Federal laws for the protection of such waterways.
The total estimated cost of the above project to the United States will be for new work, with annually for maintenance in the Caloosahatchee River west of the western limit of the Everglades drainage district, and in the St. Lucie River east of the eastern limit of the Everglades drainage district Local interests, i.e. the Okeechobee Flood Control District, were to provide and all necessary rights-of-way. A subsequent amendment in reduced the local contribution to and rescinded the District's responsibility for maintenance after the project was completed. Hurricane Gate Structures 2, 3, 4, 5, and 6 were constructed for a total cost of over million (reported total cost of in Report of Chief of Engineers, U.S. Army, p.
reported total cost of in A Report to the Board of Commissioners of Okeechobee Flood Control District, p. HGS 5 is reported to have been the least expensive to construct (reported cost of in Report of Chief of Engineers, U.S. Army, p. reported cost of in A Report to the Board of Commissioners of Okeechobee Flood Control District, p. It was completed on February 26, Construction of HGS 5 was conducted in accordance with the National Industrial Recovery Act of Workers were allowed to work a maximum of 30 hours per week for a minimum wage of for skilled labor and for unskilled labor. No convicts could be hired, and preference was given to ex-servicemen with families and men from the "southern region". Part II: Architectural Information A. General Statement: 1.
Architectural Character: Functional 2. Purpose: Each year in advance of the hurricane season, the lake level is drawn down to elevation in order to provide additional flood storage capacity. The primary function of Hurricane Gate 5 is to close the drainage canal opening which passes flow through the Lake Okeechobee levee system to Palm Beach Canal during hurricane periods. Hurricane Gate 5 provides control for regulatory discharges and also passes sufficient discharges during normal and low flow periods to maintain stages in the downstream canals and satisfy mitigation demands. HURRICANE GATE STRUCTURE 5 HAER No. (Page 5) 3.
Description of Structure: Hurricane Gate Structure 5 consists of a pair of steel sector gates, installed in a concrete structure located at the intersection of the levee and canal centerlines. The structure is symmetrical about the centerline axis of the approach canal. The structure is oriented such that the approach canal at the structure site is at right angles with the levee. The masonry portion of the structure serves a dual purpose supporting the sector gate and retaining the levee embankment. B. Description of Exterior 1. Over-all dimensions: Hurricane Gate Structure 5 is approximately 112-feet-long with a chamber width of 50 feet. Gravity wingwalls about 101-feet-long extend upstream on the lakeside of the structure. 2.
Foundations: The structure is founded on alternating layers of rock with sand and shell between the layers of rock. 3. Walls and Floor: The structure is constructed with concrete walls and a concrete floor. The walls of the gate chamber are gravity sections with stepped backslopes. Expansion joints divide each chamber into four monoliths. The walls are separated from the chamber floor by expansion joints. 4. Structural System, Framing (Gates): The sector gates are constructed of riveted structural steel. They are constructed of structural steel framing with a skin plate. The gates are 32-feet-high with a central angle of 60 degrees for each gate. The water load on the skin plate is transmitted to horizontal girders. The girder loads are transmitted to the hinges and pintle.
Needle beam recesses are provided each side of the gates to permit dewatering the bay. 5. Openings: (a) Doorways and doors: The door frames are made of 3/8-inch steel plates with the doors being made of 1/4-inch steel plates reinforced on the back with 1-inch channels. (b)Windows: Four 1' -2 x 2' -9 glazed windows were provided at each operator's house. (c) Hardware: Each window was supplied with a malleable iron cam handle and a stay bar. Hinges with bronze pins were provided for all windows and doors. Locking bolts and padlocks were provided for all doors. 6. Operator's Houses: Two reinforced concrete operator's houses were provided at Hurricane Gate No. 5 - one over each machinery pit. HURRICANE GATE STRUCTURE 5 HAER No. (Page 6) C.
Description of Interior Mechanical-Equipment The history of operating machinery is as follows: (a) - Manual: The original structure was provided with a manual capstan for gate operation. (b) - Electric: The structure was modified to replace the manual capstan (pedestal and handwheel turning bar) with an electrically operated limitorque unit. The gate could still be operated manually via a handwheel on the Limitorque; however, the number of turns required on the handwheel to effect full gate travel was so great that handwheel operation as a method of standby in case of motor failure was impractical. (c) - LP Gas Engine Standby: A gas engine with belt drive was added as an emergency standby method of gate operation in case of commercial power failure. D.
Site: General setting and orientation: Hurricane Gate No. 5 is located in Herbert Hoover Dike at the head of West Palm Beach Canal on the east side of Lake Okeechobee at Canal Point. Access to the structure is via an access road approximately 300 feet in a westerly direction off U.S. 441 at Canal Point, thence in a southerly direction approximately 450 feet along the levee to the gate.