Augusta Water Works, Goodrich Street extension, Augusta Canal, Augusta

Augusta Water Works, Goodrich Street extension, Augusta Canal, Augusta, Richmond County, GA. Surveyed as HAER GA,123-AUG,42-, with a 5,006-word written history.

From the record

“When completed in the Augusta Water Supply system was one of the best in the South and one of the cheapest in the United States.”

Written record, HAER GA,123-AUG,42- survey. Machine-read text.

Surveyed by the federal HAER program as HAER GA,123-AUG,42- · the record runs 5006 words · one of 101 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Significance

69 words

Source document Quoted word for word from HAER GA,123-AUG,42-. Not written, edited or summarised by this site.

When completed in the Augusta Water Supply system was one of the best in the South and one of the cheapest in the United States. The Raw Water Pumping Stations have always pumped canal water; some stations still use canal water to power the pumps. The complex is also significant because it illustrates the application of three types of power water, steam, and electric to the operation of pumps

Written history

4831 words

The headings the report itself prints. Each one jumps to where it begins.

Source document Quoted word for word from HAER GA,123-AUG,42-. Not written, edited or summarised by this site.

Alan J. Steiner, August It is understood that access to this material rests on the condition that should any of it be used in any form or by any means, the author of such material and the Historic American Engineering Record of the Heritage Conservation and Recreation Service at all times be given proper credit. Augusta Water Works HAER GA-16 (Page 2)

History

The Augusta, Georgia, Water Works Raw Water Pumping Stations, constructed were part of a water system with a long history. * The city of Augusta, founded in first distributed water to its citizens via a number of shallow wells and pumps located around the town. In the City Council granted Thomas McGrew a license to provide the citizens of Augusta with water for twenty-five years. McGrew and Hiram Knowlton, mechanic, collected the flow of Turknett Spring in a stone gutter, passed the water through a strainer in the spring house and sent it to a brick reservoir. Prom there, six-inch diameter bored logs conveyed the water over two miles to a reservoir within the city.

In McGrew transferred his license to the city's Mayor, Samuel Hale, who operated the works until when he turned the system over to the City Council of Augusta. Until the late the spring system provided sufficient water to meet the needs of 2 Augustans. In the Mayor, George B. Evans, suggested that the city required more water and that a new water works be built. As Evans envisioned it, the new system would take water from the Augusta Canal, a power and 3 transportation canal constructed late in the The canal water would also drive the pumps which transmitted it throughout the city mains. Two years later, under Mayor Foster Elodgett, the city improved the Turknett Spring Water Works and constructed a canal water works.

A local 4 civil engineer, William Phillips, drew up the plans for both systems. Augusta Water Works HAER GA-16 (Page 3) According to engineer and historian, Thomas Heard Robertson, Phillip's canal water works plan "was an important innovation in its day." Phillips suggested that the city build a water treatment plant consisting of two sets of three basins, each adjacent to the end of the first level of the Augusta Canal. Water would pass from the canal through timber gates into a receiving and settling basin. After several days, during which larger particles settled to the bottom, the water would be conveyed through a fate house to a gravity filter basin paved with brick. From this basin, the filtered water would flow through culverts to a clear water basin.

A pipeline then would transfer the water to a water-powered pumping station on the second level of the Augusta Canal... The pumps would send the water to a ninety-four foot high cast iron tank, from which the water would drop to distribution mams. 8 The city carried out only part of Phillip's scheme. Late in the spring of a disagreement developed between the city and the earthworth contractors for the project concerning the price for disposing of waste soil. The city discontinued the work with the contractors on the second set of basins. The city intended to let a new contract on the work, but the War Between the States interfered with their plans. Construction materials previously obtained from the North, as well as skilled workmen, were increasingly unavailable.

By June 8, the municipal government considered the system as complete as possible with only one set of basins, the new system has cost the city approximately Augusta Water Works HAER GA-16 (Page 4) In the new.pumping station, the city installed two double-acting plunger pumps, built by I. P. Morris & Co. of Philadelphia, and a Jonval turbine operating under a head of 11 feet. The pumps had a capacity 9 estimated variously at 4 million to 8 million gallons per day Early in the the city added a small steam engine with a double-acting force pump to serve as a standby for times when the turbine could not operate. Since the water power was owned by the city and therefore free of charge, any use of steam power was expensive.

The storage of pumped, filtered water in the elevated tank permitted the city to avoid running the steam engine. The enlargement of the Augusta Canal from resulted in industrial development, and a consequent rise in the city's population. From to the population increased by about two-thirds. To meet the water needs of a burgeoning population, the city government financed the construction of a new pumping station at the end of the first level of the Augusta Canal. The new site was across the canal from the receiving and settling basins. The city still held the land to construct a second series of filtering basins, but took no further action in this direction. In the new station, finished early in the city 12 installed one steam and one water powered pump.

The water power pump 13 had a capacity of 5 Again, the steam pump served as a backup and probably was used sparingly. The total cost of the new pumphouse 14 came to Augusta Water Works HAER GA-16 (Page 5) By the late the municipal government again was making plans to revise the water works system. The population was nearly double that of ^ The water supplied by the two canal pumping stations soon would become inadequate. The settling and filter basins were not large enough to prevent the pumping of discolored water following periods of muddy water in the Savannah River. The pumped water was occasionally contaminated by decaying sewers and drains before it reached the townspeople. The pressure in the city mains was maintained only by pumping to the elevated tank.

Pressure on Broad Street, the heart of the business district, was too low for effective fire protection. The problems of water supply, as well as sewage and garbage, came to the attention of numerous groups of political and social reformers who hoped 19 to clean up the city government as well as the streets of the town. In the middle of a Water Works Commission appointed by Mayor W. B. Young hired an experienced university-trained civil engineer, Nisbet Wingfield, to study the water supply and sewage problems and make 20 recommendations for the development of new systems. Wingfield!s plan called for the construction of a new pumping station west of Augusta between the canal and the Savannah River. The location of the new station would place, it above possible sewage contamination.

The station would contain two horizontal piston pumps, driven by two sets of horizontal turbines. Each pump would have a 6 capacity. The pumps would send the canal water to a 50-million-gallon earth reservoir atop a hill in Summerville, an Augusta suburb. The water then would pass through a brick filter plant and empty into a clear water basin. A 24" main would Augusta Water Works HAER GA-16 (Page 6) carry the water,, by gravity, down the hill to the existing supply 21 pipe within the city. The municipal government approved Wingfield's 22 new Department of Public Works.

Construction of the new pump station began in November and 23 was completed by December Testing of the pumps to determine whether they met the contract specifications, as well as filter problems and mechanical failures at the pump station prevented the final 24 acceptance of the new system by the city until March 29, The pumps and power equipment for the new station were manufactured by R. D. Woods & Co. The new machinery consisted of two duplex double-acting plunger-type pumps, each with a capacity of 6 driven by two sets of 600 twin runner, horizontal Geyelin-Jonval waterwheels. The pumps 25 took suction from the penstocks, which fed the waterwheels. Excess water dropped twenty-nine feet to the tailrace and the Savannah River.

A pipe tapped water from one of the penstocks and dropped it on an overshot wheel suspended behind the rear of the building. The metal wheel drove shafting in the Water Works machine shop which ran a lathe, drill press, and and a dynamo. 27 Wingfield saw his original plans realized and proudly announced that the price of water in Augusta was "cheaper than that in 95% of the cities of the United States."28 Wingfield had believed that the two water-powered pumps could supply enough water to build up reserves which would make unnecessary the 29 construction of an auxiliary steam pumping plant. However, in Augusta suffered a large flood which resulted in canal breaks.

The failure Augusta Water Works HAER GA-16 (Page 7) * of the canal shut down the city's water-powered industries, as well as the pump station. As the level of fresh water reserves decreased, the need for an auxiliary steam plant to handle just such emergencies became clear. The city soon constructed two additional buildings at the site of the pumping station. In the first, which appeared to duplicate the original pump house, the city installed 3 boilers. 30 In a circular deep well pump room to the rear of the boiler house, the city placed 1 Wilson and Snyder Compound Duplex steam pump which took suction from the Water Works tail race.

31 The new plant offered protection against loss of fresh water supply during floods, and the city continued to maintain the old Street pump house in case a break occurred between the main from the filter station to the city supply pipe. 32 Even with the installation of the steam pump, Wingfield saw the eventual need for an additional pumping unit. From to 33 consumption of water in Augusta doubled. The city could attempt to reduce consumption or to increase its pumping and storage capacities. Wingfield soon discovered that wastage made up much of the huge increase 34 in consumption. The new pumping stations provided water flow through city mains at a higher pressure.

Any leaking or faulty main or home fixture would cause more water to be wasted than before." Wingfield had hoped to avoid the expense of installing and reading water meters, but in the city made the switch from flat rates to metering. The Federal Government had hoped to locate an Army camp in the Augusta area, but the Army insisted on the availability of a reliable supply of pure water. Without metering, excessive consumption of water in Augusta would Augusta Water Works HAER GA-16 (Page 8) continue, and the city water works would not be able to guarantee a supply for the camp. The city council approved metering, the Army established Camp Hancock-outside of Augusta, and consumption of water dropped by some twenty-three percent over the next three years. 35 In Jonathan H.

Ferguson, Superintendent of the Canal and Water Works, reported that "the general installation of meters was the most progressive step since the building of the new water works," but still he saw a need for additional pumping capacity. In the city purchased two centrifugal pumps. 37 The Public Works Department planned to install one of these pumps in a new pump station on the south side of the canal across from the main pump house. J. H. Wise, a mechanical engineer from the Lombard Iron Works in Augusta, designed the new building and the pipe connection to the force main. In the new pump house, the city placed one of the two new Allis-Chalmers 7 39 pumps, along with a 700 horsepower electric motor to drive it. The 40 city ran the electric pump only at night when power rates were lower.

By running one water-powered pump during the day and the electric pump at night, the city was able to maintain a satisfactory water level in 41 the reservoir and to overhaul each water-powered pump in turn. The overhauling extenfed the lines of these pumps which, according to W. W. Hunter, Superintendent of the Canal and Waterworks in "were about ready to break down. In September and October the city of Augusta again suffered a flood which resulted in canal breaks. The water power pumps could not Augusta Water Works HAER GA-16 (Page 9) operate until city workers closed and sandbagged the Augusta levee headgates, and a gate spillway and break along the canal. The steam and electric reserve pumps were started up, but both gave considerable trouble to the operators.

The force main from the pump station to the filter plant also was troublesome. Considerable blowouts occurred because the steam and electric pumps run simultaneously. The Department of Public Works reacted to these problems by awarding a contract to the Lombard Iron Works to install two turbine electric pumps. 46 These Pomona pumps were placed in the steam pump pit and driven by Westinghouse electric motors atop vertical shafts, The arrangement of motors and pumps permitted their use in high water which flooded the pit. Originally, these electric pumps took suction from the tail race through the same line as the steam pump. Although the Department maintained the steam pump, it apparently never was used again. In M. B.

Cooper, Superintendent of the Canal and Water Works recommended that the city dismantle the steam pumps and boilers and sell the equipment while it still retained some value. During the Depression, the city of Augusta received assistance from the Federal Public Works Administration (PWA) to construct a modern filtration plant with a 15 capacity. 48 Since the filtration plant was to be modern and have an expanded capacity, E. E. Pund, the city engineer at the time, believed that "modernization of the pumping station must necessarily follow." The city quickly put the money saved on the filtration plant to good use.

In Robert and Co., Inc., Architects and Engineers, from Atlanta, Georgia, who had handled the new filter plant, Augusta Water Works HAER GA-16 (Page 10) prepared plans and specifications' for the modernization of the pumping station. Contractors removed the old water wheels and pumps, and installed two 700 hp, twin runner, horizontal shaft, center discharge Leffel turbines, connected to Farrel-Binningham speed increasers. A shaft, extending from each speed increaser, turned a 7.5 Dayton- Dowd horizontal, double-stage centrifugal pump. The new pumps began operation in but the city experienced considerable trouble with the pinion gears, bevel gears, and bearings of the speed increasers.

Operation of the new pumps did not smooth out until following the repair of the speed increasers and the replacement of the impellers in both pumps. In addition to the pump modernization, the city increased its standby capacity. The spare electricity driven Allis-Chalmers pump was placed in the pump house on the south side of the canal. 53 Federal grants supplied the funds for cleaning and rewinding the various electric motors and for moving the suction pipe for the Pomona pumps from the tail race 54 to the canal. With the new pumps and the more certain reserve capacity, the city for some time experienced fewer problems with its water supply. After the second World War, the U. S. Atomic Energy Commission built an H-Bomb plant in Aiken County, South Carolina, about 18 miles from Augusta.

The increase in population resulting from the congregation of a new work force placed some stress on Augusta's public works. Early in the city engineer, Jonathan D. Twiggs, began negotiations with the Housing and Home Finance Agency of the Federal Government to obtain Augusta Water Works HAER GA-16 (Page 11) advance funds to plan the extension and enlargement of the Augusta Water Works and sewer systems. The city received some Federal money and financed further improvements by selling $3 million worth of water works securities. With some of the money, the city built a new pump station at the water works. The new unit consisted of one Leffel turbine driving a speed increaser which turned a Peerless centrifugal pump.

The new pump had a capacity of 20 58 The installation of this unit probably terminated the operation of the Pomona pump in the deep well building. City engineer, M. P. Phillips, noted in that the additional pump assured the city system of a supply of approximately 30 The city pumping stations proved adequate for the next twenty years, The pump units installed in were used only to support the Peerless pump during peak periods and when the newer unit was down for repairs. By the mid-19701s, the Dayton-Dowd pumps alone could not provide an adequate amount of water over a prolonged period. An expansion of the complete water supply system, pumps, filters, reservoirs and distribution system, was necessary to meet the needs of the growing population in the Augusta area.

The city made plans for a new pumping station at the water works site to include a 30 Peerless pump and a 20 vertical drive Diesel pump which would take suction from the Savannah River and serve as a standby. A twin runner Leffel horizontal turbine was to drive a Falk speed increaser which would turn the Peerless pump. The new pumps and water wheels were to be installed in late Augusta Water Works HAER GA-16 (Page 12) Technology in Pumping Stations In the building, two 700 horsepower units of two horizontal turbines each, manufactured by James Leffel & Co. of Springfield, Ohio, turned shafts attached to two Farrel-Birminghara speed increasers.

These have a number of different' types of gears which redirected the power and increased the speed of the shaft to This shaft extended to two Dayton-Dowd double stage centrifugal pumps. The pump shaft had two impellers. Each impeller added an equal amount of energy to the water which was sucked out of the same penstocks that carried the water to drive the turbines. The pumped water flowed through pipes with gate and check valves to the force main that conveyed it to the city reservoir and filter plant. Excess water dropped into the Savannah River, except for a small amount which was tapped to drive a metal overshot water wheel placed on the rear of one of the wheel houses. This wheel once drove the water works dynamo and its machine shop.

The wheel remains, but now electric motors power the machine shop. The old deep well building which housed first steam and then electric pumps is no longer in use. Two electric motors which ran the old Pomona pumps via vertical shafts remain on platforms in the building, but no pumps remain in place. An exposed pipe, as well as large vents, were among the only indications of the original function of the boiler house, now used for storage. The Allis-Chalmers pump building on the south side of the canal still contains the two electrically driven centrifugal pumps, although the Augusta Water Works HAER GA-16 (Page 13) building is boarded up to prevent vandalism and appears to be in disuse.

These pumps, still provide some backup capacity during rainy periods when the river rises and prevents the operation of waterwheels. In 19 77 the city planned to update these electric pumps. Architecture In reporting to the Water Works Commission, Wingfield urged that the new pumping station be a permanent and attractive building of brick or stone. His conviction was that an impressive public building would demonstrate the reform adninistration1s pride in Augusta and its citizens. Wingfield himself undertook the task of designing the pumping station. The new facility would be built in the eclectic Victorian style and would include such details as Greek revival pediments.

The building, as even- tually constructed, reflected Wingfield's determination and commitment to make a utilitarian building look attractive and stylish. The plan of the new complex was a very simple one, consisting of a projecting central pavilion, the pump house, and two flanking wings, the wheelhouses. Several horizontal bands of limestone, which served as the sills and lintels of the windows, gave the three-part brick composition continuity. On the rear facade, which consisted of a single plane, only the interior and exterior corner pilasters carried the limestone bands. The cornice was ornamented with dentils, which, like the rest of the trim, were painted green. The front entrance of the pump station was centered and projected several feet in front of the building.

A smaller pediment above the entrance recalled the building's larger pediment. Augusta Water Works HAER GA-16 (Page 14) Although Wingfield had succeeded in giving Augusta a building with apparent sophistication and style, he had little idea of how to integrate this goal with the needs of a functioning pumping station. There was little relation between the detailed exterior facade and the interior, which was actually a large empty space with pumps situated on the base- ment level. The station was a grand public edifice which might have served any number of functions, least of which might be a pump station. The importance to Wingfield of the. appearance of the water works complex was shown by his design for a addition, built to house boilers to power auxiliary steam pumps.

The engineer planned a building of a size slightly larger than that of the pump hous.e. Whether the build- ing actually had to be a specific size to contain certain equipment is unclear. Wingfield designed this addition in a manner that maintained the balance of the water works complex. Later additions, built after Wingfield left the post of Commissioner of Public Works, did not maintain the Care- er O fully balanced plan or the ornamental style of the original buildings. Augusta Water Works HAER GA-16 (Page 15) FOOTNOTES 1. Thomas Heard Robertson, "Notes on the Development of the Augusta Water Works, The Georgia Operator 14 (Spring p. 8. Hereafter referred to as Robertson, "Notes." 2. Robertson, "Notes", p. 8; James R.

Croes, "The History and Statistics of American Water Works - CXXXVIII - Augusta, Ga., "Engineering News 8 (Nov. 19, Hereafter referred to as Croes, "History". 3. See HAER Augusta Canal Project, Report #1, Augusta Canal. 4. Robertson, "Notes", p. 9. 5. Robertson, "Notes", p. 9. 6. Robertson, "Notes", p, 9; The first basin was 10 feet deep. Once heavy clay particles had been deposited, the water went to the second basin, 15 feet deep. The second basin, which was ft. square, was originally designed for a filter basin, but the war prevented its completion as such, and the water passes simply through the 1/4 inch joints of the brick paving to the ... clear water basin." Croes, "History." 7. The pump was at Gardiner's Flume. Robertson, "Notes", p. 9. 8. Robertson, "Notes," p. 9. 9.

Robertson, "Notes", p. 34. 10. Croes, "History"; Augusta Daily Chronicle and Sentinel, Feb. 3, p. 3; June 6, p. 3; August 8, p. 3. 11. Richard Henry Lee German, "The Queen City of the Savannah: Augusta, Georgia, during the urban progressive era, (unpublished dissertation, U. of Florida, p. 28. Hereafter referred to as German, "Progressive." 12. The Sanitary Engineer and Construction Record 16 (Sept. 24, p. 13. Yearbook of the City Council of Augusta, (Augusta, p. 56. Hereafter referred to as Yearbook (dates). 14. Yearbook, p. 56. 15. German, "Progressive", p. 53. 16. Report of Wingfield, Proceedings, Water Works Commission, City Council J^ of Augusta, Sept. 13, Vault, City-County Building, Augusta, Georgia. Augusta Water Works HAER GA-16 (Page 16) 17. German, "Progressive," pp. 18.

Report of Wingfield, Proceedings, Water Works Commission, Sept. 13, 19. See German, "Progressive" for background on "reform" in Augusta. 20. German, "Progressive," p. 75. 21. Report of Wingfield, Proceedings, Water Works Commission, Sept. 13, 22. German, "Progressive," p. 75. 23. Robertson, "Notes," p. 34. 24. Robertson, "Notes," p. 34. 25. Robert & Co., Inc., "Report on Filtration Plant and Recommendations for Proposed Filtration Plant Improvements for City of Augusta, Augusta, Georgia, 11 Dec. p. 3. 26. The figure 29 feet is from Report of Wingfield, Proceedings, Water Works Commission, Sept. 13, 27. The author saw a metal overshot wheel when touring the water works site and asked a current employee about its purpose. Also see report of Jonathan H.

Ferguson, Superintendent of Canal and Water Works, Yearbook, (Augusta, p. 47. 28. Report of Nisbet Wingfield, Commissioner of Public Works, Yearbook, (Augusta, p. 76. 29. Report of Wingfield, Proceedings, Water Works Commission, Sept. 13, 30. Robert & Co., Inc., "Report on Filtration Plant....," p. 3. This report included a report on "The Existing Plant, Its Capacity, Physical Condition, and Results Being Obtained" and thus described the Raw Water Pumping Station. 31. Robert & Co., "Report on Filtration Plant...," p. 3. 32. See Yearbooks, reports of Commissioners of Public Works and Superintendents of Canal and Water Works. 33. Report of Nisbet Wingfield, Commissioner of Public Works and City Engineer, Yearbook (Augusta, p. 27. 34.

Report of Nisbet Wingfield, Commissioner of Public Works and City Engineer, Yearbook (Augusta, p. 29. 35. Message of Mayor Littleton, Yearbook (Augusta, p. 14. Message of Mayor Littleton, Yearbook (Augusta, p. 14. Augusta Water Works HAER GA-16 (Page 17) Report of W. H. Wise, Commissioner of Public Works, Yearbook (Augusta, p. 57. 36. Report of Jonathan H. Ferguson, Superintendent of Canal and Water Works, Yearbook (Augusta, p. 50. 37. Report of W. H. Wise, Commissioner of Public Works, Yearbook (Augusta, p. 36. 38. Report of W. H. Wise, Commissioner of Public Works, Yearbook (Augusta, p. 36; Report of W. H. Wise, Yearbook (Augusta, 'p. 57. 39. Report of W. H. Wise, Commissioner of Public Works, Yearbook (Augusta, p. 59; Robert & Co., "Report on Filtration Plant...," P. #. 40. Report of W.

H Wise, Commissioner of Public Works, Yearbook (Augusta, P. 59. 41. Report of W. H Wise, Commissioner of Public Works, Yearbook (Augusta, , p. 59, 77. 42. Report of W. W Hunter, Superintendent of Canal and Water Works, Yearbook Augusta, p. 85. 43. Report of W. H Wise, Commissioner of Public Works, Yearbook (Augusta, , p. 53, 60. 44. Report of W. H Wise, Commissioner of Public Works, Yearbook (Augusta, , p. 45. Report of W. H Wise, Commissioner of Public Works, Yearbook (Augusta, , p. 60. 46. Report of W. H Wise, Commissioner of Public Works, Yearbook (Augusta, , p. 60. 47. Report of M. B Cooper, Superintendent of the Canal and Water Works, Yearbook Augusta, p. 98. 48. Report of E. E Pund, Commissioner of Public Works, Yearbook (Augusta, , p. 73. 49. Report of E.

E Pund, Commissioner of Public Works, Yearbook (Augusta, , P- 73. 50. Report of E. E Pund, Commissioner of Public Works, Yearbook (Augusta, , P- 73. Augusta Water Works HAER GA-16 (Page 18) 51. Copy of "Advertisement Specifications Proposal, Form of Contract and Bonds for Raw Water Pumping Improvements, Unit No. 5, City of Augusta, Augusta, Georgia" - Revised March, Files, Robert & Co., Atlanta, Georgia. 52. Reports of E. E. Pund,"Commissioner of Public Works, Yearbook (Augusta, pp. Yearbook (Augusta, pp. Yearbook (Augusta, pp. Yearbook (Augusta, pp. Yearbook (Augusta, p. 68. 53. See "Advertisement - Specifications...", p. 3, Files, Robert & Co. 54. Reports of E. E. Pund, Commissioner of Public Works, Yearbook (Augusta, pp. Yearbook (Augusta, p. 61. 55. Jonathan D.

Twiggs, Annual Report of the City Engineer and Commissioner of Public Works, Yearbook (Augusta, p. 45. 56. Jonathan D. Twiggs, Annual Report of the City Engineer and Commissioner of Public Works, Yearbook (Augusta, p. 45. 57. Phone conversation with Fred Gary, Superintendent of Canal and Water Works: August 31, 58. Phone conversation with Fred Gary, August 31, 59. Report of M. P. Phillips, City Engineer, Yearbook (Augusta, p. 42. 60. Report of Fred Gary, General Superintendent, Waterworks Operations, Yearbook (Augusta, 61. Phone conversation with Fred Gary, August 31, 62. Phone conversation with Fred Gary, August 31, 63. The author is indebted to Bob Jorgensen, Student Historian, and Scott Ageloff, Student Architect, HAER Augusta Canal Project, for architectural description and ideas. 64.

Phone conversation with Fred Gary, August 31, Augusta Water Works HAER GA-16 (Page 19)

Bibliography

City Documents Yearbooks of the City Council of Augusta, Ga. , Information about the Water Works in Mayor's Addresses, Reports of Commissioners of Public Works and Superintendents of Canal and Water Works. Company Records Robert and Company, Inc., Architects and Engineers. Atlanta, Georgia. Company papers and blueprints involving work done for city of Augusta in and Newspapers Augusta Daily Chronicle and Sentinel, Articles concerning problems at Water Works and addition of steam pump. Periodical Articles Croes, James R. , "The History and Statistics of American Water Works - CXXXVIII - Augusta, Ga. ," Engineering News 8 (Nov. 19, Provided additional information about the early history of the Augusta Water Works.

Robertson, Thomas Heard, "Notes on the Development of the Augusta Water Works The Georgia Operator 14 (Spring Well researched article by local engineer. j?he Sanitary Engineer and Construction Record 16 (Sept. 24, p. 467 Note stating that Augusta Water Works was enlarged in early part of Augusta Water Works HAER GA-16 (Page 20) Telephone Conversation With Fred Gray, Superintendent of Canal and Water Works, August 31, Provided information on recent developments. Unpublished Material German, Richard Henry Lee, "The Ocean City of the Savannah: Augusta, Georgia, during the urban progressive era, (unpublished dissertation, U. of Florida, Contained background information on reform in Augusta.

In context

Augusta, Georgia The place record: every map, photograph and survey of this town.
Richmond County, Georgia 83 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Augusta

24 of 77 records shown

The federal surveyors worked through Augusta building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
U.S. Veterans Hospital No. 62HABS GA-242413,149 words
Augusta CanalHAER GA,123-AUG,41-9,732 words
Sibley Manufacturing CompanyHAER GA,123-AUG,54-9,524 words
John P. King Manufacturing CompanyHAER GA,123-AUG,46-8,344 words
New Savannah Bluff Lock and DamHAER GA-1677,819 words
Sand Bar Ferry BridgeHAER GA-1466,443 words
U.S. Veterans Hospital No. 62HABS GA-2424-A5,487 words
Georgia Iron WorksHAER GA,123-AUG,47-4,819 words
Enterprise Manufacturing CompanyHAER GA,123-AUG,44-4,468 words
U.S. Veterans Hospital No. 62HABS GA-2424-B4,450 words
U.S. Veterans Hospital No. 62HABS GA-2424-D2,671 words
Augusta Machine WorksHAER GA,123-AUG,45-2,527 words
White HouseHABS GA,123-AUG,8-2,160 words
U.S. Veterans Hospital No. 62HABS GA-2424-C2,070 words
Greene Street Historic DistrictHABS GA,123-AUG,56-1,958 words
Hight & MacMurphy FoundryHAER GA,123-AUG,50A1,932 words
Dartmouth Spinning CompanyHAER GA,123-AUG,51-1,694 words
Russell & Simmons FactoryHAER GA,123-AUG,58-1,478 words
Paragon MillHAER GA,123-AUG,57-1,458 words
Augusta Railway CompanyHAER GA,123-AUG,43-1,432 words
Crescent Grain & Feed MillHAER GA,123-AUG,55-1,350 words
Campbell BuildingHABS GA,123-AUG,62-1,088 words
Atlantic Coastline Railroad Freight WarehouseHABS GA-23771,064 words
Cunningham's Flour MillHAER GA,123-AUG,52-1,055 words

Provenance

  • Written history. Quoted verbatim from HAER GA,123-AUG,42-. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.