The documentation of the Rome-Westernville Road Bridge was prepared by the Historic American Engineering Record (HAER), National Park Service, during the summer of for the New York State Historic Bridges Recording Project. This project was sponsored by the New York State Department of Transportation and under the supervision of Eric DeLony, Chief and Principal Architect, HAER. This report was written by Andrew Cole and Charles Scott. When citing this report, please credit the Historic American Engineering Record and the authors. Rome-Westernville Road Bridge HAER No.
Page 4 Bridge specifications were advertised during June and modified and re-advertised during July The construction contract was awarded to the Wrought Iron Bridge Company of Canton, Ohio on July 23, With a bid of the Wrought Iron Bridge Company offered the lowest bid of four competitors: Penn Bridge Company, Beaver Falls, Pennsylvania; King Iron Bridge Company; and Fort Edward Bridge Company, Fort Edward, New York. The Wrought Iron Bridge Company was represented in the Rome bidding by agent V. Palmer of Richfield Springs, New York. George C.
Schillner, who prepared the specifications, was the Rome city engineer between and He listed his occupation in the Rome City Directory as "Civil Engineer and Surveyor," and, after his retirement from the city government, as "Civil Engineer and Architect." Schillner was later employed by the New York State Barge Canal to supervise the preparation of detailed maps [the "Schillner Maps"] delineating all lands acquired by the State of New York for canal navigation up to The bridge was moved and raised as part of New York State Barge Canal Contract 55. Contract 55 was awarded to Arthur McMullen, New York, N. Y.
on October 19, and involved the relocation of 1.9 miles of the Black River Canal and the rebuilding of four locks, the building of a reinforced concrete aqueduct over the Mohawk River, the construction of the Delta Dam and reservoir, and the relocation of the iron truss bridge. Excavation for and construction of the concrete abutments began in August and continued into October. The bridge was moved downstream 30 feet, raised 12 feet, and placed on new concrete abutments during November and the eastern approach road completed in December. Contract 55 was declared completed in August Rome-westernville Road Bridge HAER No. Page 5
Annual Report of the State Engineer and Surveyor. Albany, State of New York, Costello, Martha A. A Cultural Resource Survey Report of PIN Route 46 over the Mohawk River and Larkins Creek. City of Rome. Albany, : New York State Museum, History of Oneida County. New York. Vol II. Chicago: Clarke Publishing Company, Low, Emile. "The Delta Dam and Storage Reservoir for Supplying Water to the Rome Summit Level, New York State Barge Canal." Engineering and Contracting. XXXVII, No. 25 (June 19, New York State Barge Canal Contract 55 Drawings, New York State Department of Transportation, Division of Waterways, Albany, New York, New York State Department of Transportation, Bridge Identification Number File, Region 2, Utica, New York. New York State Department of Transportation.
New Alignment Alternative. PIN BIN Golf Course Road over Mohawk River. City of Rome. New York State D.O.T., Rome City Directory. Rome Daily Sentinel. June July August 27, The History of Oneida County. Rome, Oneida County, Westernville Bicentennial Book Committee. Mocasin Tracks to Ski Trails. Westernville, Boonville Graphics, Inc.,