Mechanicville Terminal, located on the Champlain Canal, is a component of the nationally significant New York State Barge Canal. It is one of several terminals constructed along the Barge Canal to provide points for freight transfer. Description: Terminal Street, an asphalt road, provides access to the former Mechanicville Terminal on the Champlain Canal.1 The road leads to an asphalt parking area with modern wood fencing. A modern hardscaped area with concrete pavers and an informational sign is located to the rear of the parking area. A concrete retaining wall along the rear of the parking area has a ghost sign reading: Free Docking Power Water. This retaining wall extends from a concrete bridge abutment remaining from a non-extant road bridge.
The 435'-long terminal wall, located on the west bank of the Champlain Canal, is concrete with a cast-iron quarter round coping. The wall has ladders, bollards, cleats and modern utility hook- ups. At the southern end of the terminal wall is a set of wide concrete stairs with pipe railings that lead from the water to the top of the wall. The terminal is lit by reproduction lighting. The terminal is in good condition. History: Chapter 746 of the Laws of authorized the issuing of bonds in the amount of for the purpose of constructing terminals for the Barge canal system throughout the state. The State Engineer, State Surveyor, and Superintendent of Public Works were tasked with choosing terminal locations, which would ultimately be approved by the Canal Board.
By the board had approved terminals for Ithaca, Albany, Little Falls, Utica, Gowanus Bay (South Brooklyn), Schuylerville, Schenectady, Rome, Lockport, Mechanicville, Fonda, Fort Edward, Greenpoint (North Brooklyn), Amsterdam, Erie Basin (Buffalo), Herkimer, Ilion, Troy Constantia, Syracuse, Cleveland, Watkins, Port of Call (New York City), and Dresden. There was great interest in completing the terminals quickly so that the people may avail themselves of the use of this means of transporting their products and place the greater percentage of the 1 Description of current conditions is based on a site visit made by the HAER recording team in summer and historical maps from Series New York State Archives, Albany, New York. See Eastern Division, Champlain Canal, Section 1, Sta.
958 + 00 to 0 + 00 to Sta. 925 + 00, approved April 2, 19. NEW YORK STATE BARGE CANAL, MECHANICVILLE TERMINAL HAER No. (Page 2) people of the state of New York in water communication, not only with one another, but with the neighboring states and those bordering upon the Great Lakes and along the Atlantic coast. 2 The Canal Board let the contract for construction of Mechanicville Terminal to E. Brown Baker on September 4, The contract covered the construction of a dock wall and grading. State Assistant Engineer J.E. Hall managed the project until March when State Assistant Engineer Hale assumed authority.
Construction began at the site in August and had been completed by October 6, when the Canal Board accepted the work.3 The total cost was As originally designed, the terminal dock wall ran along the west bank of the canal, then made a sharp turn at the south end, and extended along the north bank of the Tenendawo Creek that fed into the Hudson River just to the south of the Mechanicville Terminal site.4 On December 29, Contract 203 was awarded to Collins Brothers to construct frame freight-houses at four terminals, including Mechanicville.5 Work began in March and was completed in April of that year. The 16' x 30' frame warehouse was originally located to the south of the access road, near the dock wall, but is no longer extant.6