Lock E11, located on the Erie Canal, is a component of the nationally significant New York State Barge Canal. It is also significant for the movable dam at this site. Description: Lock E11 is on the north side of the channel, more than 4 miles west of Lock E10. It is also the site of the Guy Park Mansion.1 The site is accessed by an asphalt driveway extending from State Route 5 that crosses a set of railroad tracks and ends in parking areas. The driveways and parking areas are lined with post-and-rail fencing or concrete post-and-chain fencing. A gravel parking area is also located on the upstream end of the lock. The lock site consists of the lock and associated structures, powerhouse, lockhouse, tool shed, machinery cabinet, movable dam (Dam 7), and spillway.
Lock E11 has a 12' lift to the west with normal pool elevations of below and above. The concrete chamber walls have been clad in steel plating. The sections of exposed concrete on the chamber walls are in poor condition with evidence of severe spalling and breakage. As is typical of locks E8 through E15 where flooding was an issue, there are two-story concrete cabins at all four corners of the lock chamber to keep the electric motors and switchgear above normal flood waters. The cabins have flat roofs and riveted-steel hinged doors. Each one has steel multi-light windows with awning windows in the middle section. The cabins on the landward side of the lock chamber have sloped metal awnings over the lock control machinery, and the control panel has been inset into the building.
All are equipped with modern light fixtures. Steel guard rails are located on the riverside of the chamber, as well as concrete stairs in poor condition. Overall the lock is in fair condition while the cabins are in good condition. The powerhouse is located on a hill and set back from the lock to the northeast to protect the generating equipment from flooding. The single-story concrete building has an asphalt-covered hip roof and concrete chimney. The entrance to the basement is enclosed in a frame addition with vertical board siding. Plywood infill has been added around the metal entrance door. The upper story windows have also been closed in with plywood. The remainder of the fenestration is steel, multi-light, with some pivot sash.
At the locks next to movable dams, the powerhouses were equipped with gasoline-powered generators rather than hydroelectric plants to 1 Description of current conditions is based on a site visit made by the HAER recording team in summer NEW YORK STATE BARGE CANAL, LOCK E11 HAER No. (Page 2) accommodate the lack of head in the off season. The original gasoline-driven generators have been replaced, but the powerhouse is overall in good condition. The lockhouse, built in is also located on the northeast side of the chamber at the downstream end. The single-story clapboard structure sits on a slightly raised concrete foundation. The fenestration consists of one-over-one-light vinyl windows. There is a concrete chimney and metal pane-and-panel doors. The gable roof is clad in asphalt shingles.
The building is in good condition.2 Located next to the powerhouse and behind the lockhouse is the tool shed, a single-story frame structure with vertical board paneling. The gable roof is clad with asphalt shingles. There are one-over-one-light vinyl windows with steel mesh storm windows. The entrance is a metal hollow door with a gable hood. The tool shed is in good condition. A riveted-steel machinery cabinet sits next to the tool shed on a concrete pad. It is in good condition. The concrete northeast guide wall exhibits severe spalling and cracking. It is lined with concrete-filled cast-iron bollards and modern light fixtures. The northwest guide wall is also built of concrete that is spalling and cracking.
There is a single concrete-filled cast-iron bollard, as well as modern light fixtures and metal utility hookups. Both walls are in poor condition. Dam 7, a Mohawk River movable dam, extends across the river. The dam has three riveted-steel Pratt trusses supported by concrete piers. The dam measures long between abutments with a center section flanked by sections. Steel gate panels and fabricated steel uprights are operated by chains hauled by mules (DC electric winches). The central span has seven movable panels while the flanking ones each have six. A spillway consisting of a concrete pad with a pipe railing and steel guard railing is located on the northeast side of the chamber at the downstream end, near the lockhouse. The spillway is in good condition.
History: Lock E11 and Dam 7 and Lock E12 and Dam 8 were part of Contract 17, awarded to Scofield Company in The contractor stopped work on October 21, and refused to resume operations. The Department of Public Works resumed work on the contract on November 2, and completed a portion of the south abutment of Dam 7. On March 3, the contract was re-let to Alexander Murdock and active construction began with the placement of cofferdams at Dams 7 and 8 in April Excavation of the lock and guide walls continued 2 The lockhouse was destroyed by flooding from Tropical Storm Irene in August and was replaced in with a hip-roofed frame building clad in clapboards on a tall concrete foundation located further back from the lock and river. NEW YORK STATE BARGE CANAL, LOCK E11 HAER No.
(Page 3) under the new contractor, followed by concrete work on the lock and lower guide wall. The construction at Dam 7 was overseen by State Assistant Engineer M. E. James.3 By fall the south and north spans of the dam had been completed, while the middle span and the steel work were still under construction. In addition, the concrete work at the lock and guide walls was nearly complete. The contractor then completed the gates and needle-beams, placed the lower lock valves, erected the steel bridge, and began excavating and pouring concrete for the middle span of the dam, which had been completed in & Cornell Company, the subcontractors, finished the bridge superstructure, which was comprised of uprights, dam gates, and walks.
Once completed, the wooden contact strips for the dam gates were placed, and the dam was lowered and tested.4 The power plant was built as part of Contract 92, overseen by State Assistant Engineer Kline and awarded to McArthur Brothers & Company in The work included installation of five gasoline-electric power stations at locks E11, E12, E13, E14, and E15, and one hydro- electric station at Lock E16. The work began on September 12, with the excavation of substructures at locks E11, E14, and E15. The powerhouses had been erected, cooling systems and gasoline-electric sets had been installed, and drilling and chipping had been completed by Various repairs and alterations have been made at the lock and dam site throughout its operational history.
In auxiliary concrete spillways were built on the riverside of the lock and on the opposite side of the river by the dam at locks E9, E10, E11, and E12. The areas adjacent to the spillways were also paved with concrete to prevent erosion. The project was initiated in response to flood damage incurred in September Additional flood repairs continued the following year. The upper and lower guide walls were extended under Contract At the lock, Contract US94 (dating to involved work on the sills and gates. In the Department of Public Works embarked on a project to lower approximately thirty-two lock sills so as to provide a minimum 13' depth and to alter the lock gates to fit; Contract US94 may have been related to that effort.
In a lockhouse described in the Annual Report as modern 3 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 87. 4 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 64; Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 74; Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 59; Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol.
1 (Albany: Lyon Company, 94. 5 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 6 State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (Albany: Lyon Company, Printers, 21. NEW YORK STATE BARGE CANAL, LOCK E11 HAER No.
(Page 4) was built; the modern designation probably stemmed from the fact that the new lockhouse was equipped with heat, hot water, and sanitary facilities.7 New gates were installed at the dam in and additional repairs were made in Standard Engineering Company of Albany, New York, was awarded Contract to make emergency repairs to the dam in The dam was cleaned and painted under Contract in and was rehabilitated under Contract the following year.8 Originally, fixed dams were planned for construction on the Mohawk River. This was problematic as there was a great deal of development along the river and if flooding occurred due to the fixed dams, the state would be responsible for the damage.
Movable dams, on the other hand, would allow ice to flow unimpeded down the river and would also achieve cost savings due to the reduced need for dredging and silt removal. David A. Watt traveled to Europe to study the various dam types and decided upon the bridge type with Boule gates, which he had observed in Mirowicz on the Moldau River (in what is now Czechoslovakia). In his history of the Barge Canal, Noble Whitford devotes a paragraph describing these structures. These dams, as they now appear in the Mohawk, seem to be bridges with abutments and piers. From the downstream side of the lower chord hang steel frames with heavy upright pieces 15 feet apart, upon which slide an upper and a lower tier of large rectangular steel plates, called gates.
When serving as a dam the bottoms of the lower gates rest on a concrete sill in the river bed, the tops of the upper gates forming the crest of the dam. When m ore water is to be passed one or more of the upper gates are partly or wholly raised. When all the water is to be passed, in extreme flood or during the winter, all the gates are raised and both gates and frames, which have a pin joint connection with the chord, are swung to a horizontal position under the bridge floor.9 The movable dams on the Mohawk River are now one of the character-defining features of the New York State Barge Canal.