Seaboard Coast Line Railroad Bridge, Spanning Savannah River, Calhoun Falls
Seaboard Coast Line Railroad Bridge, Spanning Savannah River, Calhoun Falls, Abbeville County, SC. Surveyed as HAER SC,1-SAVRI,1-, with a 1,113-word written history.
From the record
“The Seaboard Coast Line Railroad Bridge spans the Savannah River between Abbeville County, and Elbert County, Ga.”
Written record, HAER SC,1-SAVRI,1- survey. Machine-read text.
Surveyed by the federal HAER program as HAER SC,1-SAVRI,1- · the record runs 1113 words · one of 27 surveyed structures published for this county.
Source document
Quoted word for word from HAER SC,1-SAVRI,1-.
Not written, edited or summarised by this site.
The bridge is 2.5 miles west of Calhoun Falls, South Carolina, one-quarter mile below the mouth of Rocky River. The track reaches the Georgia bank three-quarters of a mile above the mouth of Beaverdam Creek in Elbert County. UTM: Quad: Heardmont Date of Construction:
Significance
79 words
Source document
Quoted word for word from HAER SC,1-SAVRI,1-.
Not written, edited or summarised by this site.
The Seaboard Coast Line Railroad Bridge spans the Savannah River between Abbeville County, and Elbert County, Ga. The structure is a 24-span plate girder railroad bridge which spans across the Savannah River. The bridge site was first developed in re- built in and and took its present form in This site comprises the first permanent railroad crossing of the Savannah River above Augusta and played a critical role in the shipment of granite from Elberton's newly founded granite industry.
Written history
913 words
The headings the report itself prints. Each one jumps to where it begins.
Source document
Quoted word for word from HAER SC,1-SAVRI,1-.
Not written, edited or summarised by this site.
John P. Johnson, September SEABOARD COAST LINE RAILROAD BRIDGE HAER (Page 2)
Seaboard Coast Line Railroad Bridge
The Seaboard Coast Line Railroad Bridge spans the Savannah River between Abbeville County, South Carolina, and Elbert County, Georgia. The bridge is three miles west of Calhoun Falls, one-quarter mile below the mouth of the Rocky River. The track reaches the Georgia bank three- quarters of a mile above the mouth of Beaverdam Creek. The bridge site was first developed in rebuilt in and and was completed in its present form in The structure is presently a 24-span plate girder railroad bridge that carries traffic across the Savannah River. The Georgia, Carolina and Northern Railway was consolidated in February In July the entire railroad was leased in perpetuity to the Raleigh and Gaston Railroad Company and the Seaboard and Roanoke Rail- road Company.
On July 23 the Elberton Star published a map of the new- rail line. The Star announced that the tracks were progressing from Monroe, North Carolina, through Greenwood, South Carolina. The Star also announced that the companies planned to cross the Savannah River near Elberton as the line continued on to Athens and Atlanta, Georgia. In April the Adams Quarry near Elberton was busy preparing cubic yards of granite blocks for bridge piers. During the summer, six granite piers were set on bedrock in the river and a wooden deck trestle about long was constructed. By September the single track had crossed the river and was being laid toward Elberton. The citizens of Elbert County welcomed Engine No. 405 of the N.
Railway as it arrived at the newly constructed depot on April 14, Rail con- struction was completed to Athens by June 1, At the bridge site the Savannah River is divided into two channels by Paris Island. The west channel is the main river and at low water is about wide and from 2' to 8* deep. The wooden trestle (con- structed from the South Carolina bank) consisted of: one trestle; one deck truss across the east channel; one trestle over Paris Island; three spans of deck trusses, each across the west channel; and one trestle to the Georgia bank. The base of the track was 54' above low water. The U. S. Weather Bureau maintained a gauging station here to take systematic measurements of the flow of the Savannah River.
The station was in operation from August until December On November 7, the & N. Railroad was merged into the Seaboard Air Line Railway. In August the entire Savannah River Valley experienced the worst flooding since The trestles across both channels were nearly destroyed and an eastbound passenger train was forced to wait near Middleton, Georgia, until temporary repairs could be made. In May A. A. Phelgan of the Vaughn Construction Company of Roanoke, Virginia, SEABOARD COAST LINE RAILROAD BRIDGE HAER (Page 3) supervised the partial replacement of the wooden trestle. The company added earth fill to the Georgia and South Carolina banks, poured 15 con- crete piers and installed 16 steel deck plate girders, each 73' long.
Although the original granite piers were topped with concrete and girders were installed, the track bed was actually lowered 6' from the track level. However, this allowed more clearance for flood waters and debris passing under the girders than under the old wooden trestle. The track was set 23* above the highwater mark of the August flood. In April T. A. Loving of Goldsboro, North Carolina, secured a contract to repair the structure. H. R. Bell, engineer for the Seaboard Air Line Railway from Atlanta, was present to supervise the work in the east channel. The company added one concrete pier, raised (with con- crete) two graiiite piers to the track level, and set two 89' deck plate girders. In construction was completed in the west channel and the bridge took its present form.
At that time, three concrete piers were set, four granite piers were raised (with concrete) to the track level, and six deck plate girders, each 76' long, were set on the new founda- tion work. These girders were manufactured by the Virginia Bridge and Iron Company. On June 1, the Seaboard Air Line Railway was merged with the Atlantic Coast Line to form the current Seaboard Coast Line Railroad Company. During the summer of the bridge was still in use while construction of a new railroad bridge proceeded about one-quarter mile south. Footnotes: 1. Correspondence, R. L. Bullard, Seaboard Coast Line Railroad to J. L. Hopkins, Savannah District, U.S.
Army Corps of Engineers, March 2, Elberton Star, July 23, December 14, February 28, 2 - Elberton Star, April 4, September 12, April 17, See also, Star, January 26, 3. Hall, B. M. A Preliminary Report on a Part of the Water Powers of Georgia. Atlanta: Geological Survey of Georgia, Bulletin No. 3-A, pp. Hall, and Hall. Second Report on the Water Powers of Georgia. Atlanta: Geological Survey of Georgia, Bulletin No. 16, pp. 4. Star, August 28, May 11, 5. Star, April 17, SEABOARD COAST LINE RAILROAD BRIDGE HAER (Page 4) 6. Correspondence, R. L. Bullard to J. P. Johnson., Historic American Engineering Record, August 20, Drawing of bridge with engineering details. See also, Patterson, William H.
"Through the Heart of the South: A History of the Seaboard Air Line Railroad Company, PhD Thesis, University of South Carolina, See also illustration of original railroad trestle in True Stories_ of the Savannah. Calhoun Falls, H. T. Cannon, p. 72.
The federal surveyors worked through Abbeville building by building. These are the other structures
they measured and filed a report on, longest report first.
Written history. Quoted verbatim from HAER SC,1-SAVRI,1-. United States federal work, no copyright under 17 U.S.C. 105.
Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.