Silver King Mining Company, Ore Mill, Park City West, Park City
Silver King Mining Company, Ore Mill, Park City West, Park City, Summit County, UT. Surveyed as HAER UTAH,22-PARK.V,3B-, with a 1,210-word written history.
From the record
“Demonstrates standard ore-transport practices and reveals level of automation achieved in early Cv. mining facilities”
Written record, HAER UTAH,22-PARK.V,3B- survey. Machine-read text.
Surveyed by the federal HAER program as HAER UTAH,22-PARK.V,3B- · the record runs 1210 words · one of 48 surveyed structures published for this county.
Source document
Quoted word for word from HAER UTAH,22-PARK.V,3B-.
Not written, edited or summarised by this site.
T.Allan Conp, HAER UT-22B UT-22C SILVER KING COALITION ttHffi1-
Tramway and Ore Loading Station
At the beginning of the twentieth century the Silver King Coalition Mine in Park City, Utah was both the largest producer of ore and ore-concentrates in the region and the largest dividend-payer In the state. Located a mile and a quarter south of Park City,at the head of Woodside Canyon, the Silver King plant was widely acclaimed as the most : i complete and efficient in the district. One major problem encountered by the Silver King was the transportation of its rich ore and concentrates to the tracks of the Rio Grande Railway and the Union Pacific Railroad in Park City. The road from the mine and mill to the railroad was steep and winding: heavy winter snows and spring rains often made it impassable.
The solution to this problem was an aerial wire-rope tramway connecting the workings of the mine and mill with an ore- loading station or tipple on the Park City railhead. Such aerial tramways were nothing new to Park City,or to Utah, but the Silver King does serve as an example of this .type of ore transport system and of the level of automation achieved in early twentieth century mining facilities. HAER UT-22B UT-22C Designed and erected under the supervision of Mr, J. Breckenridge Fleming (Mechanical Engineer for the Silver King) and Mr. Stephens (Superintendent of Constr- uction) , the tramway and ore tipple were part of a larger construction project that included a 250 ton-per-day automatic ore sampler.
This sampler was a five-story structure in which ore from the mine and concentrates from the mill were crushed, graded, and sampled for analysis "by the Silver King assay office located nearby.* The crushed and graded ore and concentrate were then stored in four 250-ton bins ready for loading on to the tramway. Both the sampler and the tramway and loading station were put into commission on June 1, The line of the tramway ran along the ridge of hills to the north of the mine and then down a rather steep incline to the loading station.
Over feet in length, the tramway cables were carried down the foot descent on thirty-nine steel towers varying in height from sixteen to sixty-five feet.- These.towers were fabricated in sections of 4x4 inch angle iron by the Gillette-Herzog Company of Minneapolis, Minnesota. Gables, buckets, and other related pieces were built on the Pinlay'son pattern by the A. Leschen and Sons *The best ore from the mine was shipped directly to the smelter while lower grades were milled or concentrated before being sent to the smelter. HAER UT-22B UT-22C Rope Company of St. Loui3. Two cables were carried on each side of the towers: a stationary or standing cable carried the weight of each bucket, and a moving or traction cable pulled or moved the buckets.
Both cables were made of crucible steel and had a breaking strain of pounds per square inch. The-traction cable was three-fourths of an inch in diameter, while the standing cable was one-and one ^-eighth inch in diameter on the downhill side and one inch in diameter on the uphill side.* Idler pulleys on each tower for the traction cable were babbited with a self-lubricating compound and required little or no attention. There were eighty buckets on the line spaced 175 feet apart, each with a capacity of 500 pounds of ore.and concentrate on the downhill run and 325 pounds of coal for the return trip. The coal was used to fire the boilers for the several steam engines .employed at the mine and. mill, ... .
It should be added that most of the supplies fdf the mine* timber, oil, powder, etc.-- were carried to the works on the tramway. The foot fall allowed the buckets of ore to be propelled by gravity, although when coal was sent up the tram additional power was supplied by the 125 Corliss steam engine in the sampler building. *The traction cable was apparently replaced by November, Howard reports a running or traction cable of six- strand, nineteen-wire, Lang-lay type, seven-eighths of an inch in diameter and manufactured my Robbing of extra strong cast steel.
(tj HAER UT22B UT-22C The tramway entered the ore loading station in Park City eighty-five feet above the ground at the fourth-floor level where the automatic unloading machinery as well as coal and supply loading apparatus were located. Ore and concentrates were dumped into one of four 250-ton bins situated above the railroad tracks running on each side of the loading station. There was room for six thirty-four foot railroad ore cars on each track and each track was built over a Fairbanks, Morse and Company seventy-five-ton scale. Despite the seemingly complicated process of getting ore and concentrates from the mine and mill to the railroad cars, it actually required only one man to load the buckets at the upper terminal and unloading was accom- plished automatically.
In fiscal year one engineer-journalist reported the' tramway operated at the low cost of 6A cents per ton. There are wire-rope tramways operating today in Park City, but now they carry skiers to the snow-instead of carrying ore over It. A good example of contemporary engineering in its day, the Silver King tramway is now het s been' dismantled and the ore loading station fun g t i on a. -pg ima.rvl 1 y aH -toe-"&Ub4ft ^-l1ey--^ouri&t^photograp.h.D T. Allan Comp HAER January3 K \\ HAER UT-22B UT-22C
Bibliography
Boutwell, James Mason. Geology and Ore Deposits of the Park City District, Utah. Professional Paper 77, United States Geological Survey. Washington: United States Government Printing Office, Best general source on Park City mines. One paragraph on the tramway and ore tipple. Callow, and Nevill. "Description of the Silver King Sampler and Mill," The Salt Lake Mining Review. December 15, pp. Description of interesting engineering features of sampler with brief mention of tramway. One photograph of "Silver King Works" and several sketches -- none on tramway or tipple. Howard, L.O., M.E. "Milling at- the Silver King/' The Salt Lake Mining Review. November 13J pp. Includes brief mention of aerial tramway; some indication of alterations and running costs. MacVichie, D.
Report on the Property of the Silver King Coalition Mines Company, December 1, The Silver King Coalition Mines Company was incorporated In May of This stock- holder's report is an extensive description of the new and expanded Silver King. Tramway and tipple mentioned briefly. Steel-e, James H., E.M. "A Model Tramway anh Sampler," The Engineering and Mining Journal. November 9J PP. 59o-597, An extensive description including three photographs, one of tramway and tipple. l
The federal surveyors worked through Park City building by building. These are the other structures
they measured and filed a report on, longest report first.
Written history. Quoted verbatim from HAER UTAH,22-PARK.V,3B-. United States federal work, no copyright under 17 U.S.C. 105.
Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.