Cape Canaveral Air Force Station, Launch Complex 34, 17251 Freedom Road, Cape Canaveral

Cape Canaveral Air Force Station, Launch Complex 34, 17251 Freedom Road, Cape Canaveral, Brevard County, FL. Surveyed as HAER FL-8-6, with a 18,475-word written history.

From the record

“Launch Complex 34 at Cape Canaveral Air Force Station (CCAFS) was built to support the Saturn and Apollo programs.”

Written record, HAER FL-8-6 survey. Machine-read text.

Surveyed by the federal HAER program as HAER FL-8-6 · the record runs 18475 words · one of 123 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Significance

18360 words

The headings the report itself prints. Each one jumps to where it begins.

Source document Quoted word for word from HAER FL-8-6. Not written, edited or summarised by this site.

Launch Complex 34 at Cape Canaveral Air Force Station (CCAFS) was built to support the Saturn and Apollo programs. All Saturn I test flights launched from Complex 34. The complex was modified for the Saturn IB. Launch Complex 34 was the site of the Apollo 1 fire in January that took the lives of three astronauts. In October the first manned Apollo flight launched from Complex 34. As one of the primary Saturn testing facilities, Launch Complex 34 played a pivotal role in the Apollo program. The development of the larger, more powerful Saturn V required the construction of Launch Complex 39 at Kennedy Space Center. Launch Complex 34 was deactivated in and abandoned in place in Report Prepared by: Kimberly Hinder Architectural Historian, Archaeological Consultants, Inc.

Blaikie Court, Suite A, Sarasota, Florida Updated Dr. Susan Enscore U.S. Army Engineer Research and Development Center Construction Engineering Research Laboratory Newmark Drive, Champaign, IL Date: June (updated by Dr. Enscore April CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 2) HISTORICAL

Overview of Cape Canaveral Air Force Station

Rocketry in the United States originated with the pioneering work of Robert H. Goddard, who launched the first liquid-propelled rocket in Across the Atlantic, German engineers were simultaneously developing their own rocket science program. Encouraged by the Nazi regime during World War II, the Germans developed the V-1 buzz bomb and the V-2 ballistic missiles, which they used against Allied cities in Although the Allied forces had experimented with missiles powered by rocket engines, they lacked the technology to compete with the against which there was little defense. As a result, the U.S. Army, Navy, and U.S. Air Force (USAF) each initiated their own missile programs to fulfill their particular roles in national defense. Following the war, the U.S.

Army brought 115 German rocket engineers and scientists, including Dr. Wernher von Braun, to the United States to develop their program. These engineers conducted experiments to refine the German V-2 and develop long-range surface-to-surface guided missiles. Initially stationed at Fort Bliss, Texas, the team assisted the Army in testing rockets at the White Sands Proving Grounds beginning in May This site, however, was geographically constrained and posed a danger to civilians when rockets misfired.1 Increasingly concerned with Soviet missile and nuclear development after World War II, the Department of Defense created and charged the Committee on Long Range Proving Grounds to select a suitable missile test site in October Cape Canaveral was selected for several critical reasons.

Missiles could be launched over the Atlantic Ocean and tracked from islands. The isolated location of the Cape enhanced security for research and development. The government already owned land at the Cape, and the undeveloped nature of the remaining land made it less expensive to acquire. The launch area was accessible via water, easing the transportation logistics of heavy rockets and building supplies. The warm weather also allowed year-round operation of a missile site at the Cape.2 In President Harry S. Truman signed legislation which established the Joint Long Range Proving Ground at Cape Canaveral, with Patrick USAF Base (originally the Banana River Naval 1 Charles D. Benson and William B.

Faherty, Moonport: A History of Apollo Launch Facilities and Operations (National Aeronautics and Space Administration, Scientific and Technical Information Office, reprint as Gateway to the Moon: Building the Kennedy Space Center Launch Complex and Moon Launch! A History of the Saturn-Apollo Launch Operations, Gainesville: University Press of Florida, 1 (page references are to reprint edition). 2 David Barton and Richard S. Levy, An Architectural and Engineering Survey and Evaluation of Facilities at Cape Canaveral Air Force Station, Brevard County, Florida (Resource Analysts, Inc., 16 March Benson and Faherty, 4. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 3) Air Station) selected as the support base.

Although the entire facility was initially under the cooperative use of the Army, Navy, and USAF, by a directive of the Department of Defense, the USAF ultimately assumed responsibility for the range. The Joint Long Range Proving Ground was renamed the Air Force Missile Test Center, the first of many subsequent name changes. Although the Army continued its operation of the White Sands Proving Grounds in New Mexico and the Navy continued to fund its missile testing center at Point Mugu, California, both military branches continued to play an active role at Cape Canaveral.3 Construction and Missile Development at Cape Canaveral Between April and June of land was acquired at the Cape through negotiation and condemnation proceedings.

During this period, the United States Army Corps of Engineers was designated as the construction agency. The Jacksonville District of the Corps opened an office at Patrick Air Force Base in to oversee construction at Patrick Air Force Base and the Air Force Missile Test Center at Cape Canaveral. By December the office had managed million of construction contracts. For each construction project, the agency (Army, Navy, or USAF) would submit project specifications, a deadline for completion, and authorization to begin construction to the Corps. The Corps would then negotiate and award a contract to an architectural/engineering firm for preparation of the construction plans.

Once the plans were submitted, the Corps advertised and selected a contractor who was required to complete the project within the time frame or pay penalties.4 As the United States entered peacetime and reduced military funding during the late the various branches of the military sought to determine their roles in missile research and design. The Army continued refining the German with the assistance of the team led by Wernher von Braun and 300 carloads of V-2 missile components seized during World War II. The Army conducted the first successful launch at Cape Canaveral on July 24, An Army-General Electric Corporation-California Institute of Technology team launched Bumper No. 8, a modified V-2 rocket, from Launch Pad 3.

The Army team continued to use Pad 3 to conduct additional launches through 3 E.R. Bramlitt, History of Canaveral District (South Atlantic Division, US Army Corps of Engineers, Benson & Faherty, 3, 7. 4 Bramlitt, 33. 5 Benson & Faherty, 1, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 4) During the late and early USAF activities at Cape Canaveral focused on winged cruise missile research and development as a deterrent force in the weapons race between the United States and the Soviet Union. Constrained by a reduced budget, the USAF chose to fund research and testing on the cruise missile, projected to be operational before the ten years anticipated for the development of the ballistic missile.

These winged missiles resembled unmanned airplanes and fell into four different categories: air-to-air, air-to-surface, surface-to- air, and surface-to-surface. These missiles were restricted to the Earth s atmosphere because they required oxygen for engine combustion. The earliest launch pads, used for firing experimental winged missiles including the Lark, Matador, Snark, Bomarc, Bull Goose, and Mace, were located at the tip of the Cape, and included Launch Complexes and Support buildings, including a communications building, a water plant, a fire-fighting unit, electrical substations, a skid strip for the landing and reuse of the missiles, and Hangars C and O, were constructed near the original launch pads.

As explosive power increased, and missiles necessarily grew larger, support activities were relocated farther from the launch pads to an Industrial Area which was situated along the western shore of the Cape.6 After the Soviets detonated their first atomic device in and following the outbreak of war in Korea in the United States government reassessed the military cutbacks of the late With increased funding and the development of relatively lightweight nuclear warheads, the USAF and Army decided to pursue ballistic missile research and development. Faster and more accurate than the winged cruise missiles, ballistic missiles, with their own oxygen source, could leave the Earth s atmosphere. The ballistic missiles were divided into two categories based on the distance they could travel.

The intercontinental ballistic missiles (ICBM) had a range of over miles. Intermediate range ballistic missiles (IRBM) had a range of miles. The USAF, which remained focused primarily on the development of cruise missiles, initiated a ballistic missile study which resulted in the Atlas missile.7 To advance its research and development of ballistic missiles, the Army Ballistic Missile Agency moved their team of German engineers from Fort Bliss, Texas, to the Redstone Arsenal in Huntsville, Alabama. Soon after the move to Huntsville, the launch team, known as the Missile Firing Laboratory established facilities at Cape Canaveral.

With the first launch of the Redstone missile on August 20, at Launch Pad 4, the MFL inaugurated the testing of 6 Barton and Levy, 6, 25; Bramlitt, Jacob Neufeld, The Development of Ballistic Missiles in the United States Air Force, (Washington, Office of Air Force History, United States Air Force, 7 Neufeld, 98, Benson and Faherty, 1, 3, 7. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 5) ballistic missiles, an event which foreshadowed the construction of numerous launch facilities for ballistic missiles at the Cape.8 Both the detonation of the first thermonuclear device in and intelligence reports indicating that the Soviet Union was developing long-range missiles and thermonuclear warheads led to advancements in ballistic missile development.

In the USAF formed a panel of U.S. scientists to examine their Snark, Navaho, and Atlas missile programs. The panel recommended accelerating development of the Atlas ICBM.9 By USAF officials convinced President Eisenhower to assign the ICBM development program the highest national priority. Accordingly, the USAF initiated programs for the design and testing of the ICBM Titan in and the ICBM Minuteman in As the USAF ICBM program grew, intelligence reports indicated that the Soviet Union would have ICBMs with nuclear warheads operational by Fearing that the United States could not match the Soviet ICBM threat, the Department of Defense decided to fund the development of IRBMs because they would be operational sooner and would act as a deterrent based out of Europe.

In the Department of Defense approved two IRBM programs, the USAF Thor and the Army/Navy Jupiter, which developed simultaneously and were assigned an equal national priority as the ICBM programs.10 The constant drive to develop more accurate and powerful weapons during the Cold War led to the construction of numerous launch complexes along the Cape. Although many of the early launch complexes were adapted to new uses as support structures, complexes constructed for one type of missile were rarely reused to launch another type of missile because they were not configured structurally, electronically, or for safety concerns for the new larger and more powerful missile. Economically, it was more cost effective to design and build a new complex than to reconfigure and adapt an old complex.

Explosive hazards, the dangers of launching over other complexes or inhabited areas, and maintaining a line of site between the launch vehicle and the launch control center (blockhouse) determined the choice of sites and distance between launch complexes. Each missile had similar ground requirements at the launch complex including a launch pad, a gantry service tower, a blockhouse for on-site command and control of 8 Benson and Faherty, 1, 3, 7. 9 Neufeld, David N. Spires, The Air Force and Military Space Missions: The Critical Years, in The U.S. Air Force in Space: to the Century, Proceedings Air Force Historical Foundation Symposium, Andrews AFB, Maryland, September ed. R.

Cargill Hall and Jacob Neufeld (Washington, DC: USAF History and Museums Program, United States Air Force, 10 ibid., CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 6) the launch, and a network of power, fuel, and communication links.11 The government maintained programs for both ICBMs and IRBMs concurrently, and facilities for both types of missiles were constructed at Cape Canaveral.

Over time, the area south of the tip was developed for launching IRBMs (Redstone, Pershing, Polaris/Poseidon, and Thor) and included Launch Complexes 17, 18, 25, 26, 29, and The area north of the tip was developed for launching ICBMs and space launch vehicles (Atlas, Titan, Saturn) and included Launch Complexes 19, 20, 34, 36, and Throughout the early and mid-1950s, the focus of activities at Cape Canaveral remained on missile development for defense against the Soviets. In November the Secretary of Defense divided the responsibilities for research and development of missiles among the armed forces. The USAF received responsibility for all intermediate and long-range missiles, both IRBMs and ICBMs, while the Army was restricted to missiles with a range of 200 miles or less.

The Navy was limited to developing submarine and ship-based IRBM missile systems.13 Cape Canaveral and the United States Space Program In President Eisenhower announced that the United States would launch an unmanned satellite as part of the nation s participation in the International Geophysical Year which extended from July through December The Army, Navy, and USAF immediately initiated planning for their own satellite programs.14 When the Soviets launched the satellite Sputnik I in October of the attention of the public turned to space exploration. The following month, the Soviets placed the Sputnik II satellite carrying a dog into orbit around the Earth. The launch caused a furor among Americans who feared that the U.S.

was losing not only the space race, but also that a missile gap existed between the U.S. and the Soviets, who it was believed had hundreds of operational ICBMs. The President initially assigned responsibility for the U.S. space program to the Department of Defense. The Army s Development Operations Division led by 11 Benson and Faherty, 12 Barton and Levy, 4, 9; Denise P. Messick, Cynthia G. Rhodes, and Charles E. Cantley, Space Wing Cultural Resource Management Plan, Technical Report No. 386 (Stone Mountain, Georgia: New South Associates, 95; James N. Gibson, Nuclear Weapons of the United States: An Illustrated History (Atglen, PA: Schiffer Publishing, Hartmann 13 Neufeld, Barton and Levy, 17. 14 R. Cargill Hall, Civil-Military Relations in America s Early Space Program, in The U.S.

Air Force in Space: to the Century, Proceedings Air Force Historical Foundation Symposium, Andrews AFB, Maryland, September ed. R. Cargill Hall and Jacob Neufeld (Washington, DC: USAF History and Museums Program, United States Air Force, 25. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 7) Wernher von Braun shifted their focus to the use of missiles to propel payloads, or even a man, into space.15 After several failures on the launch pad, the United States entered the space race with the launch of the Army s scientific satellite Explorer I on January 31, using a four stage Jupiter C missile named Juno I. With the threat of a growing fleet of operational Soviet ICBMs, the branches of the U.S.

military initiated the development of photographic reconnaissance satellites which were operational by Realizing that the military s involvement in the space program would jeopardize the goal of using space for peaceful purposes, the President s Science Advisory Committee urged that a centralized agency be created to oversee the scientific exploration of space. The new agency, the National Aeronautics and Space Administration (NASA), established October 1, was to be a civilian agency with the mission of carrying out scientific aeronautical and space exploration, both manned and unmanned.

The Department of Defense, especially the USAF, would continue with defense related missile and satellite development.17 Soon after the creation of NASA, Navy personnel and facilities associated with Project Vanguard and over 400 scientists from the Naval Research Laboratory were reassigned to NASA. The California Institute of Technology s Jet Propulsion Laboratory, affiliated with the Army, was also transferred to NASA.

Initially working with NASA as part of a cooperative agreement, President Eisenhower officially transferred a large portion of the Army s Development Operations Division with the team led by Wernher von Braun to NASA in March At the same time, Eisenhower named the Huntsville NASA installation the Marshall Space Flight Center, and designated the MFL at Cape Canaveral as the Launch Operations Directorate of NASA. The Launch Operations Directorate, led by Dr. Kurt Debus, managed the overall integration, testing, and the launch operations of NASA.18 NASA soon organized a National Launch Vehicle Program to identify and analyze which missiles would be the most effective in exploring space.

As a result, the Scout, Thor (Delta), Atlas, Titan, and Saturn, and modified versions of these rockets, were selected as boosters for manned and unmanned missions. Unmanned activities have included suborbital, orbital, and lunar satellite and vehicular missions to gather scientific information often relating to physics and astronomy. Although some were conducted to prepare for manned launches, most of the 15 Benson and Faherty, 16 ibid. 17 Hall, 30; Barton and Levy, 20; Spires, 39. 18 Spires, 39; Benson and Faherty, 15. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 8) missions were intended simply to gain scientific knowledge with which to better understand Earth.19 Already upstaged by the Soviets, one of NASA s first goals was to put a man in orbit around the Earth.

At its creation, the USAF s manned space projects were transferred to NASA, which NASA combined under the name Project Mercury in December NASA selected the first seven astronauts for the manned space program in April The goals of Project Mercury included sending a man into space to orbit the Earth, testing his ability to perform in a weightless environment, and to recover both man and capsule.20 The program included two manned suborbital flights powered by a modified Redstone missile and four manned orbital flights powered by an Atlas missile topped by the Mercury capsule. The first suborbital flight occurred on January 31, with the launch of Ham, a chimpanzee.

The United States was again upstaged when the Soviet Union launched Vostock I with cosmonaut Uri Gagarin to orbit the Earth in April The launch of Alan Shepard the following month on a Mercury suborbital flight proved anticlimactic.21 Realizing the impact of the Soviet advancements on the American psyche, President John F. Kennedy appointed Vice President Lyndon Johnson, in cooperation with representatives from NASA and the associated industries, to develop a space program that would surpass the Soviet program. The panel recommended a ten-year phased approach which would include manned space flight, planetary exploration, and the development of new rockets and satellites.

Accepting the recommendations, President Kennedy presented the following before a joint session of Congress on May 25, I believe this nation should commit itself to achieving the goal, before this decade is out, of landing a man on the Moon and returning him safely to the Earth. No single space project in this period will be more impressive to mankind, or more important for the long-range exploration of space, and none will be so difficult or expensive to accomplish.22 19 Barton and Levy, 20 Spires, 39; Exploring Space Project Mercury (U.S. National Aeronautics and Space Administration) 3, Kennedy Space Center Archives, Kennedy Space Center, Sweetsir Collection Box 12. 21 Harry Butowsky, Man in Space (Reconnaissance Survey) (Denver: National Park Service, 4.

22 ibid., Man in Space, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 9) With widespread support, the public and Congress embraced the goal and the program proceeded rapidly. Circling the Earth three times, John Glenn completed the first manned orbital flight of the United States on February 20, in a capsule propelled by an Atlas rocket from Launch Complex 14. Followed by three more manned orbital flights, the Mercury program concluded as a success on May 15, NASA initiated planning for Project Gemini in late as the intermediate step in sending a man to the moon.

Officially announced in the project was operational by The goals of Project Gemini included testing man s performance during extended periods in space, both within and outside of the spacecraft, development of rendezvous and docking techniques, and perfection of controlled reentry and landing techniques. The larger, more maneuverable capsule, designed to hold two men, was propelled by a Titan II rocket. Following the first unmanned Gemini launch on April 8, Gemini 3 was the first manned flight of the program in March Gemini 12, launched in November successfully completed the program.24 Apollo, the final step in landing astronauts on the moon, immediately followed Project Gemini.

Studies to build the Saturn rocket, which would propel man to the moon, actually started in with the team led by Wernher von Braun under the Army s jurisdiction.25 Ten times more powerful than the Atlas rocket and twenty times more powerful than the Jupiter, the size and power of the Saturn required the construction of Launch Complexes 34 and 37 at Cape Canaveral. Test flights of the Saturn rocket started at Launch Complex 34 in October In January NASA announced that the Saturn would be the moon launch vehicle. The goal of Apollo was to launch a team of three astronauts into orbit around the moon. While one astronaut remained in orbit, the others would then take an attached spacecraft to land on the moon and then redock with the primary vessel before returning to Earth.

The initial missions were Earth orbital (unmanned and manned) followed by lunar missions to orbit and, later, land on the moon.26 NASA utilized Launch Complexes 34 and 37 for research and development of the Saturn rocket. Continued modifications to the Saturn to increase its power to propel man to the moon led to a larger rocket with new blast and acoustic hazards. With these factors in mind, combined with the 23 Barton and Levy, 28. 24 Ibid., William A. Lockyer, A Summary of Major NASA Launchings: October 1, 1958-September 30, KSC Historical Report No. 1 (John F. Kennedy Space Center: KSC Historical Services, IX-1-8. 25 Benson and Faherty, 26 ibid., 37, Barton and Levy, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 10) stepped-up launch schedule necessary to land a man on the moon by the end of the decade, it was apparent by that the Apollo program required a new launch complex.27 Cape Canaveral, with over 22 launch complexes, did not have room for another complex. NASA officials solved the dilemma by acquiring land on Merritt Island, west and north of the existing missile launching area at the Cape. The first acquisitions of land started in with the majority under federal ownership by Initially known as the Merritt Island Launch Area, the land was acquired for use predominantly in support of the Manned Lunar Landing Program (Apollo) and was placed under NASA s exclusive jurisdiction.

With the new facilities, NASA s offices at the Cape, led by Kurt Debus, expanded and relocated to the Merritt Island Launch Area. The newly independent installation, on par with Marshall Space Flight Center, was renamed the John F. Kennedy Space Center in November after the death of the president.28 During land acquisition and construction of the Kennedy Space Center, NASA continued manned space flight under the Mercury and Gemini programs and preparations for Apollo.

During a simulation flight at Launch Complex 34, three astronauts, Virgil Grissom, Edward White, and Roger Chaffee, lost their lives in an oxygen fire in the cockpit on January 27, Apollo 4 (November 9, through Apollo 6 (April 4, were unmanned Earth orbital missions to test the Saturn rocket and the Command and Service modules. The October 11, Apollo 7 launch was the first manned Apollo launch which placed astronauts into Earth s orbit for a ten-day mission.

Apollo 8, the first launch at the newly completed Kennedy Space Center, achieved the first lunar orbit in December The goal of landing man on the moon was achieved with Apollo 11 on July 20, and was followed by six additional lunar missions which gathered extensive scientific information culminating in Apollo 17 in December Subsequent manned space programs included the Skylab, Apollo-Soyuz, and the Space Shuttle, which took its inaugural flight on April 12, The Space Shuttle program ended on July 21, History of Complex 34 As the first of three launch complexes constructed at Cape Canaveral to serve the Apollo program, Launch Complex 34 played a significant role in the development of the Saturn missile necessary to achieve the goals of the Apollo program.

The successful completion of the Apollo 27 Benson and Faherty, 28 ibid., 29 Barton and Levy, 31; Butowsky Man in Space, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 11) program brought an end to the fears that the United States was losing not only an arms race, but also a space race, with the Soviets. Launch Complex 34 proved pivotal in the development of the United States manned space program with the successful testing of all of the Saturn I Block I test flights, further testing of the Saturn IB, and the launch of Apollo 7, the first manned orbital flight of the mission. The Complex was also the site of the first NASA tragedy with the loss of Apollo 1 on the pad in January From to NASA launched seven space launch vehicles from Launch Complex 34.

Planning and development of the Saturn missile, and the construction of Launch Complex 34 (Figure 1), originated prior to the creation of the Apollo program. Following the launch of Sputnik I and Sputnik II which placed Soviet satellites into Earth s orbit in the attention of the American public turned to space exploration. When the President initially assigned responsibility for the U.S. space program to the Department of Defense, the Army s Development Operations Division of the Army Ballistic Missile Agency (ABMA) led by Wernher von Braun shifted their focus to the use of missiles to propel payloads, or even a man, into space.

After several failures on the launch pad, the United States entered the space race with the launch of the Army s scientific satellite Explorer I on January 31, using a modified Jupiter missile named Juno I. 30 Developed by the design team led by von Braun, the Saturn family of rockets originated as part of the Juno missile program in The Redstone-based Juno I and Jupiter-based Juno II were already viable rockets, while the Juno III and Juno IV remained in the planning stages. Originally designated as Juno V, initial designs called for a rocket with a first stage composed of a cluster of eight Redstone missiles surrounding one Jupiter missile. Each of the clustered missiles would be fitted with a modified Thor engine produced by Rocketdyne.

This nine-engine first stage would produce approximately 1.5 million pounds of thrust during liftoff. This pioneering design was the first to increase a rocket s payload capacity by clustering existing missiles. In August the Advanced Research Projects Agency (ARPA) officially authorized ABMA to proceed with the development of a rocket with a clustered first stage. In October von Braun recommended renaming the Juno V because the rocket was markedly different from the Jupiter-based Juno family of rockets. He suggested the name of Saturn since the planet is the sixth from the sun following Jupiter, a name which ARPA approved in February 30 Benson and Faherty, 31 Clifford J.

Lethbridge, Saturn I Fact Sheet, Spaceline.org, Spaceline, Inc., CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 12) Realizing that the military s involvement in the space program would jeopardize the goal of using space for peaceful purposes, the President established NASA on October 1, as a civilian agency with the mission of carrying out scientific aeronautical and space exploration, both manned and unmanned. NASA soon organized a National Launch Vehicle Program to identify and analyze which missiles would be the most effective in exploring space.

Although still under development, the potential power of the clustered rocket design of the Saturn led to its selection as one of the core boosters for space launch vehicles.32 Initially working with NASA as part of a cooperative agreement, President Eisenhower officially transferred a large portion of the Army s Development Operations Division, along with the group of scientists led by von Braun and the Saturn rocket program, to NASA.33 While still in the design phase, the Saturn Vehicle Evaluation Committee composed of representatives from the USAF, NASA, ARPA, and ABMA met in order to determine the configuration and goals for the Saturn missile.

Commonly known as the Silverstein Committee,34 the group selected three initial missions for the Saturn vehicle: unmanned lunar and deep space missions with a 9,920-pound escape payload, a 24-hour equatorial orbit with a 4,960-pound payload, and manned spacecraft missions in low orbits. To achieve these goals, the committee recommended that NASA consider three different configurations utilizing the clustered first stage concept mated with several different upper stages. Of the three suggested configurations, known as Saturn A, Saturn B, and Saturn C; the Saturn C was selected. The concept included five versions of the missile, Saturn C-1 through Saturn ranging from the least to the most powerful.

The Saturn which consisted of a two-stage vehicle closely resembling the original Juno V plans, was already under development (Figure 2). The Saturn C-2 would utilize the same first stage with an improved second stage and an added third stage. The Saturn C-3 through C-5 would be based upon the same configuration, but would employ varying numbers of more powerful Rocketdyne engines in the first stage. NASA selected the two-stage Saturn C-1 for Apollo research and development flights. Produced by Chrysler, which had also produced Redstone and Jupiter, the missile was ready for flight tests by 32 Hall, 30; Barton and Levy, Spires, 39. 33 Benson and Faherty, 15; Spires, 39. 34 Dr. Abe Silverstein, NASA s Director of Space Flight Development, led the committee.

35 Benson and Faherty, Lethbridge, Saturn I Fact Sheet; Chrysler was a contractor for the U.S. Army s Ordnance Guided Missile Center at Redstone Arsenal. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 13) Following the approval of the development of the rocket in the USAF and NASA evaluated existing and proposed launch sites for the new missile. The size and explosive power of the Saturn required the construction of a new launch complex at Cape Canaveral. At the time Launch Complex 34 was conceived, only four test flights of the Saturn vehicle were planned and there was no timetable requiring a rapid series of launches. With no strong argument to justify the cost of a second launch pad, a single launch pad was constructed at Complex 34 (Figure 3).

As a result, the maximum launch rate for the complex was four vehicles per year, allowing two months for vehicle checkout and one month for pad refurbishment between launches.36 Launch Complex 34 was constructed between June and June As the construction agency at Cape Canaveral, the U.S. Army Corps of Engineers let the contract for the construction of Complex 34 on June 3, Construction started five days later on June 8. Plans for the complex were prepared by Maurice H. Connell and Associates and Rader and Associates.

The initial construction costs for the brick and mortar totaled By the complex was valued at Although the complex reached beneficial occupancy status in February construction was completed in July and officially approved by the Corps in January Complex 34 was the first of two launch complexes at Cape Canaveral completed for the Saturn I and Saturn IB program, with the first launch of a Saturn I missile from the complex at Cape Canaveral on October 27, (Figure This first flight produced the largest thrust of a United States launch vehicle up to that time.

Significantly, Launch Complex 34 was the largest rocket launching site in the world, and the first built expressly for the peaceful exploration of space.38 The first four flights of the Saturn I were launched in the Block I configuration which consisted of a live first stage topped by a dummy upper stage composed of an inert Jupiter missile shell ballasted with water to provide aerodynamic stability. The live first stage consisted of eight Redstone stages, which acted as fuel tanks, surrounding one Jupiter missile, similar to the original design for the Juno V. Four of the Redstone stages and the Jupiter stage held liquid 36 LC Launch Complexes and Ground Support Equipment, 1.

37 Real Property Cards, Cape Canaveral Air Force Station; Eastern Test Range Launch Complexes, Cleary, Eastern Range Launches; Cleary, Space Wing ; Phaseout Plan, Prologue; Maurice H. Connell & Associates, Inc., Location & Vicinity Maps and Index to Drawings, 01- U-34-A1, and U-34-A2; Rader and Associates, Drawings Technical Facilities Catalog: Volume II, 38 Launch Complex 34 Facilities: Fact Sheet 05, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 14) oxygen, while the remaining four Redstones contained The liquid oxygen and combined to fuel eight Rocketdyne H-1 engines which powered the Saturn The Block I configuration was utilized to test the vehicle s compatibility with the launch facility, flight dynamics of the vehicle, and the reliability of the clustered first stage.40 In May President John F. Kennedy charged NASA and the associated industries to develop a space program that would surpass the Soviet program by landing a man on the moon by the end of the decade. With widespread support, the space program proceeded rapidly.

In order to streamline and accelerate the program, NASA discontinued development of the Saturn and instead focusing on plans for the the uprated C-1 (also known as the IB), and the Three more test flights of the Saturn C-1 followed in April and November and March all from Launch Complex 34 (Figure 5). In February the C designation was dropped from the Saturn names, leaving simply the Saturn I, Saturn IB, and Saturn Following the successful first test flight of the Saturn I in October NASA announced that the family of Saturn vehicles would be the launch vehicles used in the Manned Lunar Landing Program (Apollo).

Development and testing of rockets and complexes to implement the three stages in sending man to the moon, designated as Projects Mercury, Gemini, and Apollo, continued simultaneously. Apollo, the final step in landing astronauts on the moon, immediately followed the successful completion of Projects Mercury and Gemini. The goals of the Apollo program included a manned space flight of three astronauts to orbit the moon. While one astronaut remained in orbit, the other two would then take an attached spacecraft to land on the moon and explore the lunar surface then redock with the primary vessel before returning to Earth.

The initial missions were Earth orbital (unmanned and manned), followed by lunar missions to orbit, and, later, land on the moon.42 Under the direction of the NASA s Office of Manned Space Flight, the Apollo program was the joint responsibility of the Manned Spacecraft Center in Houston, the Marshall Space Flight Center in Huntsville, and the Launch Operations Directorate at Cape Canaveral (later at Kennedy Space Center) in Florida. The Marshall Space Flight Center undertook the development of the 39 is a kerosene based rocket fuel. 40 Lethbridge, Saturn I Fact Sheet ; Benson and Faherty, 43. 41 Benson and Faherty, 37, Barton and Levy, Lethbridge, Saturn I Fact Sheet ; Cleary, Eastern Range Launches.

42 Benson and Faherty, 37, Barton and Levy, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 15) Saturn launch vehicles. The Manned Spacecraft Center managed the development of Apollo spacecraft systems and astronaut selection and training. The Launch Operations Directorate at Cape Canaveral (later at Kennedy Space Center), which administered launch operations, was responsible for receiving, inspecting, assembling, preflight testing, and launching of the launch vehicles and Apollo spacecraft.43 Following the successful test flights of the Saturn I, Block I at Launch Complex 34, NASA initiated testing of the Saturn I, Block II configuration which featured operational first and second stages.

The second stage of the Block II configuration consisted of a Pratt and Whitney engine powered by a combination of liquid oxygen and liquid hydrogen. The addition of lengthened fuel tanks and improved H-1 engines increased the power of the rocket which was capable of transporting a pound payload into Earth s orbit. When initial evaluations in late indicated that an explosion of the Block II would render Complex 34 unusable for a year, NASA initiated the construction of a second Saturn complex.

Completed by January NASA conducted six test flights of the Block II configuration from Launch Complex 37 between January and July After the final test flight of the Block I configuration in March the facilities at Complex 34 were modified for the assembly, checkout, and launch of the larger, more powerful Saturn IB while NASA initiated testing of the Block II configuration at Complex 37. The USAF approved the initial modifications to the complex until it was officially transferred to NASA in November Alterations continued throughout and into The more advanced vehicle configuration led to alterations and upgrades to the and liquid oxygen fueling systems.

The gaseous nitrogen and helium batteries at the High Pressure Gas Facility were subsequently replenished from the central converter-compressor facility designed to service both Launch Complexes 34 and 37. A new High Pressure Gas Battery, the Liquid Hydrogen Facility, High Pressure Gaseous Hydrogen Storage Battery and Burn Stack, an Administration Office, another Sentry House, and the Theodolite Building were installed at the complex.

In addition, the Mobile 43 Launch Complex 34 Facilities: Fact Sheet 05, 44 Benson and Faherty, 30; Lethbridge, Saturn I Fact Sheet ; Cleary, Space Wing: Its Heritage, History & Honors Launch Facilities & Programs: Complexes 34 and 37 ; Clifford Lethbridge, Cape Canaveral Rocket and Missile Box Scores, Spaceline.org, Spaceline, Inc., Clifford Lethbridge, Cape Canaveral Launch Sites Box Scores, Spaceline.org, Spaceline, Inc., 45 Launch Complex 34 Facilities: Fact Sheet 05, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 16) Service Structure and the Umbilical Tower were modified to support the new configuration and the Apollo spacecraft.46 The Saturn IB incorporated an uprated Saturn I first stage mated to a new second stage (Figure 6).

Scientists reduced the weight of the eight Rocketdyne H-1 engines in the first stage while improving their thrust. Designed to support manned space flight, the second stage was composed of a Rocketdyne J-2 engine which burned a combination of liquid oxygen and liquid hydrogen. Three solid-propellant ullage motors on its aft skirt provided acceleration for the spacecraft between the cutoff and separation of the first stage and the ignition of the second stage. Two auxiliary propulsion system modules also on the aft skirt provided for spacecraft maneuvering while in orbit. An Instrument Unit, which allowed for electronic control and guidance during ascent, was a ring attached to the top of the second stage.

The space capsule and launch escape system utilized for the manned flights were attached to the Instrument Unit by an adaptor. Following its use in the lunar landing program, the Saturn IB was also used in Skylab and Apollo-Soyuz Test Project.47 The first test flight of the Saturn IB was launched from Complex 34 on February 26, (Figure 7). Two more unmanned test flights followed, one from Complex 34 and one from Complex 37. The fourth scheduled flight was to be the first manned mission scheduled to be launched from Complex 34 in February However, during a countdown simulation, three astronauts, Virgil Gus Grissom, Edward White, and Roger Chaffee, lost their lives in an oxygen fire in the cockpit on January 27, (Figure 8).

Following an investigation of the Apollo 1 accident, the spacecraft and Umbilical Tower were altered to improve safety. The wiring, the escape hatch, the environmental control system, and the space suits were redesigned. The atmosphere in the spacecraft was changed to 60 percent oxygen and 40 percent nitrogen. Fans, water hoses, fire extinguishers, and an escape slide wire were added to the white room. In case of another fire, astronauts and workers could ride the escape slide wire to the ground in seconds.48 46 Office of Manned Space Flight, 2-9 through and Figure United States Air Force, Property Cards and Launch Complex 34 files. 47 Clifford J.

Lethbridge, Saturn IB Fact Sheet, Spaceline.org, Spaceline, Inc., 48 Benson and Faherty, Lethbridge, Saturn I Fact Sheet ; Lethbridge, Cape Canaveral Rocket and Missile Box Scores ; Lethbridge, Cape Canaveral Launch Sites Box Scores. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 17) Apollo 4 in November Apollo 5 in January and Apollo 6 in April were launched as unmanned Earth orbital missions to continue testing of the Saturn rocket and the Command and Service modules; these launches took place at the new Apollo pads at Launch Complex Apollo activity at Launch Complex 34 continued with the October 11, Apollo 7 launch, the first manned Apollo launch which placed astronauts into Earth s orbit for a ten-day mission (Figure 9).

Essentially a test flight, the crew (Walter Schirra, Donn Eisele, and Walter Cunningham), tested the Command Service Module and its guidance and control systems, the Instrument Unit, the Spacecraft Lunar Adapter, spacesuit design, food supplies, and work routines. During the flight, the astronauts separated the Command Service Module from the second stage in order to practice rendezvous operations with the booster. Seven television transmissions from the spacecraft were broadcast on live television in the United States and overseas. Apollo 7 was the final launch from Complex Continued development of the Saturn V to increase its power, necessary to propel man to the moon, led to a larger rocket with new blast and acoustic hazards.

With these factors in mind, combined with the stepped-up launch schedule necessary to land a man on the moon by the end of the decade, it was apparent by that the Saturn V required a new launch complex. Cape Canaveral, with over 22 launch complexes, did not have room for another complex. NASA officials solved the dilemma by acquiring land on Merritt Island starting in to construct Launch Complex 39, west and north of the existing missile launching area at the Cape. Placed under NASA s exclusive jurisdiction, the installation was initially known as the Merritt Island Launch Area, but was renamed the John F.

Kennedy Space Center in November after the death of the president.51 The first test launch of a Saturn V occurred from the newly completed Launch Complex 39 at the Kennedy Space Center on November 9, and was designated Apollo 4. Apollo 8, the first manned launch from Complex 39, achieved the first lunar orbit in December The goal of landing man on the moon was achieved with Apollo 11 on July 20, and was followed by six additional lunar missions which gathered extensive scientific information culminating in Apollo 17 in December 49 Lethbridge, Saturn I Fact Sheet ; Cleary, Complexes 34 and 37 ; Lethbridge, Cape Canaveral Rocket and Missile Box Scores ; Lethbridge, Cape Canaveral Launch Sites Box Scores ; Barton and Levy, 31; Butowsky Man in Space, 50 Clifford J.

Lethbridge, Apollo 7 Fact Sheet, Spaceline.org, Spaceline, Inc., 51 Benson and Faherty, 52 Barton and Levy, 31; Butowsky Man in Space, Clifford J. Lethbridge, Saturn V (Apollo) Fact Sheet, Spaceline.org, Spaceline, Inc., CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 18) The success of the Saturn IB, the explosive hazards and power of the Saturn V launch vehicle, and the construction of Launch Complex 39 at Kennedy Space Center led to the termination of further Apollo development flights from Launch Complex 34.

The Complex was reduced from an operationally ready state to a downmoded configuration in October and a Phaseout Plan was approved in April The Complex was mothballed in November and the Service Structure and Umbilical Tower were razed in April due to excessive rust and deterioration.

Launch Complex 34 was officially abandoned in October with most of the facilities transferred back to the USAF s control in November NASA retained control of the Operations Support Building and the Blockhouse, which served as a site for NASA tour stops until it was transferred back to the USAF in Several buildings and structures, including the Phased Array Radar Pedestal, Van Shelter, Toilet, Septic Tank, Optical Tracker, two Electrical Substations, Shop/Storage Building, and three Hazardous Waste Storage Sheds were constructed around the complex during the Soon after Launch Complex 34 was officially abandoned, many of the structures were removed from the real property records, demolished, or moved to other complexes.56 The Sentry Houses; Paints, Oils, Lubricants, Cleaning Fluids (POLCF) Building; Umbilical Tower; and Service Structure were demolished.

The Administration Office was relocated to Launch Complex 30 in The tanks, pumps, lines, and machinery have been removed from the fueling facilities, the Amplifier Facility and Cableway, the Flume and Skimming Basin, the Theodolite Building, and the Launch Pad and Pedestal, but the concrete structures and blast walls remain to mark their locations. The Flame Deflectors remain parked in their service area.

Although most of the control panels and machinery have been removed from the Blockhouse, the building remains largely intact, with the original periscopes and most of the original finishes in place (Figure The interior of the Operations Support Building was extensively altered for other uses before it was demolished in or Launch Complex 34 was listed as part of the National Historic 53 Phaseout Plan, Prologue, (John F. Kennedy Space Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 2.

54 Master Planning, CCAFS Basic Information Guide; Cleary, Launch Facilities & Programs: Complexes 34 and 37 ; United States Air Force, Property Cards and Launch Complex 34 files; Butowsky, National Register Nomination, 55 Master Planning, CCAFS Basic Information Guide; United States Air Force, Property Cards and Launch Complex 34 files. 56 United States Air Force, Property Cards and Launch Complex 34 files; United States Air Force, Voucher Nos. and 57 Master Planning, CCAFS Basic Information Guide. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 19) Landmark District on April 16, In honor of the astronauts lost in Apollo 1 and the goals achieved at Launch Complex 34, a Historical Site Kiosk (Facility No.

was erected on the Launch Pad in 58 United States Air Force, Property Cards Launch Complex 34 files. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 20) ARCHITECTURAL DESCRIPTION OF LAUNCH COMPLEX 34 The U.S. Army Corps of Engineers initiated the construction process for Launch Complex 34 in June Construction started on the 45-acre site on June 8, (Figure The complex reached beneficial occupancy status in February which was followed by the first launch of a Saturn missile in October. The Corps officially approved the plans and completed construction in January The majority of the following physical description is based upon a review of the Real Property Cards and the Basic Information Guides from and as well as analysis of the As-Built Drawings completed by Maurice H.

Connell & Associates, Inc. and Rader and Associates in and Pan American World Airways, Inc. in Launch Complex 34 consisted of a concrete Launch Pad and Pedestal (Facility No. renumbered and associated structures serviced by one Blockhouse (Facility No. 21900A, renumbered and an Operations Support Building (former Facility No. The following ancillary structures were noted in the Basic Information Guide: Sentry House (Facility No. renumbered High Pressure Gas Facility (Facility No. renumbered No. LOX Facility (No. Electric Equipment Building (Facility No. renumbered No. Fuel Facility (Facility No.

21900E/18410A, 59 Real Property Cards, Cape Canaveral Air Force Station, Space Wing Office of History, Patrick AFB; Eastern Test Range Launch Complexes, Cape Canaveral AFS, Space Wing Office of History, Patrick AFB, 16 April Mark Cleary, Eastern Range Launches, Space Wing Office of History, Patrick AFB, 11 December Mark Cleary, Space Wing: Its Heritage, History & Honors Launch Facilities & Programs: Complexes 34 and 37 Space Wing Office of History, Patrick AFB, Launch Operations Center, Launch Complex 34 (John F. Kennedy Space Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 1.

60 United States Air Force, Real Property Accountable Record-Inventory Detail, Property Card Launch Complex 34 files, Space Gateway Support Company, GIS Real Property Office, John F. Kennedy Space Center; Rader and Associates, Air Force Missile Test Center: Complex 34. Drawings Research Planning/Design Engineering Office, Kennedy Space Center; Maurice H. Connell & Associates, Inc. Air Force Missile Test Center, Complex 34. Drawings Complex 34 Launch Facilities: Location & Vicinity Maps and Index to Drawings, 01- U-34-A1, and U-34-A2, Research Planning/Design Engineering Office, Kennedy Space Center; Pan American World Airways, Inc. Saturn Launch Complex 34.

Drawing 34 Research Planning/Design Engineering Office, Kennedy Space Center; Pan American World Airways, Inc., Basic Information Guide, (Cape Canaveral Missile Test Annex, Research Planning/Design Engineering and Real Property Offices, Kennedy Space Center; Pan American World Airways, Inc., Basic Information Guide, (Cape Canaveral Air Force Station, Research Planning/Design Engineering and Real Property Offices, Kennedy Space Center; Engineering and Environmental Planning, CCAS Basic Information Guide: Facilities, Utilities, Instrumentation, and Communications, (Cape Canaveral Air Station: Johnson Controls World Services, Inc., Master Planning, CCAFS Basic Information Guide: Facilities at CCAFS and KSC (Kennedy Space Center: Space Gateway Support, October CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 21) renumbered Special Liquid Storage Building (Facility No. renumbered No. Flume and Skimming Basin (Facility No. Amplifier Facility and Cableway (Facility No. and Electric Substations and Septic Tanks to serve the Blockhouse and Launch Pad (Figure Subsequent construction in included the Paints, Oils, Lubricants, Cleaning Fluids (POLCF) Building (former Facility No. the Operations Support Building (former Facility No. and a Septic Tank (Facility No. and Electric Substation (Facility No. associated with the Operations Support Building.

Although not included in the Basic Information Guides, the Umbilical Tower and Mobile Service Structure were vitally important facilities at the Launch Complex.62 Following the successful testing of the Saturn I vehicle, the USAF transferred the complex to NASA, who modified the facilities to launch the Saturn IB (Figure Modifications included the construction, between and of the Liquid Hydrogen Facility Liquid Hydrogen Facility Electric Equipment Building (Facility No. renumbered the High Pressure Gaseous Hydrogen Storage Battery (Facility No. and Burn Stack (Facility No. the High Pressure Gas Battery (Facility No.21900U), temporary trailers forming an Administration Office, and the Theodolite Building (also known as the Alignment Building; Facility No. A second Sentry House (Facility No.

was moved to the complex in The Launch Pad served as the hub of the complex, around which the remaining facilities were located. The Launch Pad area included the Launch Pedestal, Flame Deflector, Automatic Ground Control Station, Umbilical Tower, Mobile Service Structure, Environmental Control Systems Building, and other major firing accessories. Other elements of the complex were separated from the launching area by distances dictated by propellant explosive hazards.64 There was also an area separate from and north of the main launch complex that contained support facilities such as a theodolite tower, a substation, camera sites, a maintenance supervisor s office, paint storage buildings, and a spray paint shed.

These facilities were mostly constructed between and and the majority remained until Complex 34 was 61 Pan American World Airways, Inc., Basic Information Guide, 62 United States Air Force, Property Card Launch Complex 34 files. 63 United States Air Force, Property Card Launch Complex 34 files. 64 LC Launch Complexes and Ground Support Equipment, (John F. Kennedy Space Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 1. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 22) abandoned. By everything was removed except for a small storage building which had been abandoned in It was removed by

Launch Pad Area

Launch Pad and Pedestal (Facility No. The Launch Pad and Pedestal (Facility No. is located approximately northeast of the Blockhouse. Constructed of reinforced concrete, the circular Launch Pad is in diameter with a maximum height of above sea level, set on soil consolidated by vibroflotation. The Pedestal, located in the center of the Launch Pad, was used to support the launch vehicle during checkout and firing. The square, high Pedestal is constructed of reinforced concrete formed over steel stiffeners supported on four columns (Figure The platform and leg surfaces exposed to vehicle exhausts were plated with steel. The structure is set on a foundation containing approximately 13 million pounds of reinforced concrete set by and poured thick at the outer edges and thick at the center.

A diameter opening in the center of the platform provided access to the vehicle boattail section. During a launch, the opening in the platform of the Pedestal allowed the engine exhaust to pass through to the Flame Deflector which was situated beneath the opening between the columns of the Pedestal.

The portion of the pad around the deflector is surfaced with refractory brick to protect the pad from the rocket exhaust.66 Eight steel vehicle support arms mounted on the platform of the Pedestal provided support to the erected vehicle (Figure Four of the supports, situated 90 degrees apart, were cantilevered 65 Pan American World Airways, Inc., Basic Information Guide, (Cape Canaveral Missile Test Annex, Pan American World Airways, Cape Kennedy Air Force Station: Building Schedules and Locations (Patrick Air Force Base, FL: Facilities Planning Section, Pan American World Airways, Inc., Basic Information Guide, Cape Canaveral: Facilities, Utilities, Instrumentation, and Communications, (Cape Canaveral Air Force Station: Facilities Engineering Department Engineering and Environmental Planning, CCAS Basic Information Guide: Facilities, Utilities, Instrumentation, and Communications, (Cape Canaveral Air Station: Johnson Controls World Services, Inc., 66 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, 2; Launch Complex 34 Facilities: Fact Sheet 05, (John F.

Kennedy Space Center: National Aeronautics and Space Administration, [2, 7], Archives, Kennedy Space Center, LOC Box 1; Office of Manned Space Flight, Apollo Systems Description, Volume III, (Launch Operations Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 1; Maurice H. Connell & Associates, Inc., Drawings and Charles D. Benson and William B. Faherty, Moonport: A History of Apollo Launch Facilities and Operations (National Aeronautics and Space Administration, Scientific and Technical Information Office, reprint as Gateway to the Moon: Building the Kennedy Space Center Launch Complex and Moon Launch! A History of the Saturn- Apollo Launch Operations, Gainesville: University Press of Florida, 29 (page references are to reprint edition).

CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 23) toward the vehicle at the outboard engine positions. In order for the engine shrouds to clear the arms at liftoff, these four arms would retract horizontally after the thrust commit signal was given. Located alternately between these support arms, the other four support arms also served as holddown points during thrust buildup following the ignition command signal. These holddown arms were released by a toggle linkage activated at the launch commit signal. If any of the retractable support arms failed to operate or in case of an emergency cutoff prior to release, all four retractable supports automatically returned to their locked position.

Although the complex was mothballed in and transferred from NASA back to the USAF in the Launch Pad and Pedestal remain in place.67 Flame Deflectors Situated between the columns of the Pedestal during a launch, the Flame Deflector was used during a launch to protect the launch pad and launch pedestal by deflecting the Fahrenheit engine flame into two controlled directions. The Flame Deflector was built with a series of roof- type trusses formed in an inverted V at an 80 degree angle. Constructed of welded and bolted steel, the two flame-deflecting surfaces are covered with 1" steel plates coated with a 4" layer of special heat-resistant ceramic. Overall, the 150-ton Deflector is approximately 43' long, 32' wide, and 21' high.

Shipped to the complex in sections, the Flame Deflector was assembled on the supporting rail system. When in position under the Pedestal, the four retractable railway wheels were raised hydraulically and the load was transferred to tiedown anchor points. Shear plates were lowered into slots to prevent the Deflector from moving. Hinged 41"-high side shields protected against flame spillage and backwash over the sides of the Deflector. When not in use, the Flame Deflector was moved along the track to its parking and repair area at the northwest edge of the launch pad. A second Flame Deflector was available on the spur track in case of major damage to a Deflector during launch.

To further protect the launch pad, the central portion of the pad in the vicinity of the Flame Deflector is paved with refractory brick to protect it from the intense heat during a launch.68 67 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, 3; Launch Complex 34 Facilities: Fact Sheet 05, United States Air Force, Real Property Voucher, Voucher No. Space Gateway Support Company, GIS Real Property Office, John F. Kennedy Space Center; Maurice H. Connell & Associates, Inc., Drawings and 68 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Office of Manned Space Flight, Launch Complex 34 Facilities: Fact Sheet 05, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 24) Automatic Ground Control Station Serving as a distribution point for all of the measuring and checkout equipment, power, and high- pressure gas, the Automatic Ground Control Station provided square feet of usable space under the Launch Pad. This facility consisted of an electronic equipment room, battery room, distributor pit, generator room, terminal room, and a restroom. Access was provided to these rooms by a flight of stairs at the northern edge of the Pad, adjacent to the Flame Deflector parking and repair area. All of the sub-pad rooms, which constituted the Automatic Ground Control Station, are linked and held terminal boards, instrumentation racks, and high-pressure gas lines, in addition to the mechanical and electrical equipment.

Electrical, communications, and control cables and lines extended from the terminal room near the center of the Pad through an access tunnel and an above-ground roofed cableway to the Blockhouse. Ventilation was incorporated into the design, and motor-driven sump pumps provided drainage.69 Environmental Control Systems (E.C.S.) Building The E.C.S. Building was constructed for the Saturn 1B launch vehicle configuration. Prior to this, the E.C.S. equipment was housed on an open-air concrete platform with a 14'-high deck supported by columns that also held equipment and supported cable trays connecting to the adjacent umbilical tower. The new enclosed building was constructed to the north of the existing E.C.S.

platform, on a concrete slab, and had concrete-block walls covered with a smooth concrete coat. It housed Heating, Ventilation, and Air Conditioning (HVAC) systems to provide conditioned air through the umbilical tower to the launch vehicle and spacecraft (if included on the vehicle). The old platform and deck were roofed over, continuous with the new building s open-air second story addition (Figure There are/were sleeve openings on both the north and south walls for conduit to pass through. Equipment in the building included air conditioning units, an air compressor, a demineralizer, and a second floor expansion tank. The north wall of the enclosed building remains in place, along with low curbs outlining the remaining walls.

An operational intercom system, with approximately 300 stations, was installed throughout the complex. A closed-circuit television loop, consisting of 20 television monitors and 11 cameras, was also used for monitoring, checkout, and observing a launch. Cameras, remotely controlled 69 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, 5; Office of Manned Space Flight, Maurice H. Connell & Associates, Inc., Drawing CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 25) from the Blockhouse, were mounted around the Launch Pedestal for photographic coverage of launch operations.70 Water Deluge System A quenching system was installed to reduce the intense heat and remove spilled fuel from the Launch Pedestal area.

As part of the Water Deluge System, a 36" water line extended water to the torus ring of the Pedestal. Four gallon-per-minute nozzles were installed at the Pad surrounding the launch vehicle as a general protection measure. The Water Deluge System provided a water shield between the engines of the Saturn vehicle and the burning propellant residues in case of an emergency cutoff of the engines prior to launch. Additionally, water was available at the Launch Pad and at all work levels of the Umbilical Tower and Service Structure.71 Flume and Skimming Basin (Facility No. The Launch Pad was graded with a perimeter trench connected to a skimming basin for the drainage of surface water and possible propellant spillage. The Flume and Skimming Basin (Facility No.

constructed in collected excess water and fluids spilled on the Launch Pad in order to prevent contamination of the surrounding ground. The Flume is essentially a concrete-lined ditch which extends from under the Launch Pad northeast approximately to the Skimming Basin, which is situated outside of the perimeter road. The Skimming Basin is a concrete paved vat approximately x Collected fuel, which floated on the surface of the water, could be burned in the Skimming Basin. After NASA returned the complex to the USAF in this facility was abandoned in place in August The Flume and Skimming Basin remain on site. 72 70 Launch Operations Center, Office of Manned Space Flight, United States Air Force, Property Card 01- Launch Complex 34 files.

71 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, 3; Benson and Faherty, Moonport, 21. 72 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, 2; United States Air Force, Property Card Launch Complex 34 files; United States Air Force, Voucher No. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 26) Umbilical Tower Although not individually noted in the Basic Information Guides, an Umbilical Tower was also part of the complex. The Umbilical Tower provided various electrical cables, pneumatic lines, checkout consoles, cryogenic replenishing lines, liquid nitrogen cooling tanks, mechanical refrigeration units, air-conditioning ducts, valve complexes, and other systems necessary to service the booster and upper stages.

Situated adjacent to the Launch Pedestal, the Umbilical Tower was an open truss steel structure square at its base and high including the base. The base was enclosed by steel blowout panels which provided two air-conditioned equipment rooms to house preflight checkout equipment, tower electrical distribution system, and other equipment. From the level (above the square base building), the tower tapered to " square at the top (Figure A one-ton capacity elevator provided access between the service platforms located at each level above the base. A 5,000-pound capacity electric hoist, which incorporated a hook reach and a 360-degree pivot, was mounted on top of the tower to lift electrical cables, umbilical arms, and other heavy equipment.

Four hydraulically-controlled umbilical swing arms, weighing approximately one ton each, were attached to the tower by hinged joints at the nearest diagonal leg of the tower, and extended horizontally toward the vehicle. Each arm was capable of swinging 135 degrees to either side and could be adjusted vertically in 6" increments. Each arm held links between the vehicle and the tower which led to the ground-based power, air conditioning, hydraulic, pneumatic, fuel, measuring, and command systems. Situated at the 0" level, the Apollo spacecraft access arm provided a means for astronauts to enter or leave the spacecraft. This arm was connected to the white room, an environmentally sterile room located in the Umbilical Tower.

The elevator, which could travel at a speed of per minute, provided a means of egress in an emergency. The Umbilical Tower was razed in April due to excessive rust and deterioration.74 73 LC Launch Complexes and Ground Support Equipment, 4; Office of Manned Space Flight, 2-3 through Maurice H. Connell & Associates, Inc., Drawings U-34-A1 and U-34-A2; Master Planning, CCAFS Basic Information Guide.

74 LC Launch Complexes and Ground Support Equipment, 5; Launch Complex 34 Facilities: Fact Sheet 05, Office of Manned Space Flight, 2-3 through Cleary, Launch Facilities & Programs: Complexes 34 and 37 ; United States Air Force, Property Card Launch Complex 34 files; Harry Butowsky, National Register of Historic Places Nomination Form/National Historic Landmark Federal Agency Nomination: Cape Canaveral Air Force Station (Washington, National Park Service, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 27) Mobile Service Structure Similarly, the Mobile Service Structure was also part of the complex, although it was not individually noted in the Basic Information Guides.

The Mobile Service Structure, which provided work platforms for the assembly, checkout, and servicing of the launch vehicle, was an inverted U-shaped, rigid box truss frame design (Figure The structure rose in height, extended x at the base, and weighed tons. The central top box truss, with its bridge runway hoisting equipment, was long, wide, and deep. The bridge crane, with vertically adjustable runway trusses, had individually controlled 40- and 60-ton hoists with a hook height which could be extended to Two smaller hoists were located at the level. The top box truss rested on two box truss columns with x 0" cross sections, each of which rested on a two-story base section wide x long.

Each leg of the structure incorporated a two-story building containing operation and checkout equipment, a work deck, seven fixed platforms with 790 square feet of floor area each, and eight movable, enclosed, horizontally-retracting platforms with 814 square feet of floor space used to encase the vehicle in a wide central opening. Each platform was designed to support a capacity of 12 personnel and 600 pounds of equipment. Two personnel and one freight elevator provided access to the platforms.

The two high base sections held engineering and laboratory space and power equipment necessary for self-locomotion of the tower on a dual-track railway system between the Mobile Service Structure Parking Area and the Launch Pad.75 Anchored to steel piers by hydraulically operated steel pins, the Service Structure and encased launch vehicle could withstand hurricane force winds of 125 miles per hour. Four hurricane doors, which extended from the Launch Pedestal to the level, and two retractable silo sections, which extended from the to the levels, protected the space vehicle from adverse weather conditions. Mounted on four 12-wheel trucks, each powered by 100-horsepower electric motors, the structure was moved between to per minute by an operator situated in a cab at the level.

At the Launch Pedestal, support points moved the Service Structure from the tracks and anchored it to the ground. After checkout was complete, the Service Structure was moved on two sets of tracks placed apart to its parking area, approximately southwest of the Launch Pedestal. Automatic synchronizing controls 75 Maurice H. Connell & Associates, Inc., Drawings and Pan American World Airways, Inc., Drawing 34 Office of Manned Space Flight, Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Technical Facilities Catalog: Volume II, (Washington, National Aeronautics and Space Administration, Archives, Kennedy Space Center, NHB 8800.5(I), LOC 23A.2N; Launch Complex 34 Facilities: Fact Sheet 05, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 28) prevented skewing the tower during movement. A self-contained, 500 kV-a diesel-electric generator powered the motors and tower equipment during movement. External ground power was used for all operations except tower locomotion and emergency lighting. The tower had lightning protection and grounding systems, aircraft warning lights, and illumination for night operations. The Service Structure was razed in April due to excessive rust and deterioration.76 Theodolite Building (Facility No. and Amplifier Facility and Cableway (Facility No. The Theodolite Building (Facility No. also known as the Alignment Building, was constructed by NASA in as part of the improvements for the Saturn IB.

Located immediately south of the Launch Pad, the facility held a theodolite utilized in maintaining the azimuth alignment. With 287 square feet of space, the concrete building has a concrete foundation and concrete roof. After the transfer back to the USAF in the building was abandoned in The Amplifier Facility and Cableway (Facility No. was constructed in as one of the original facilities at the complex. The Cableway consisted of an above-ground roofed linear structure extending from the Blockhouse to the southern perimeter of the Launch Pad, where it moved underground into the Automatic Ground Control Station. Poured concrete stanchions supported the cable trays.

The Amplifier Facility is a concrete block structure that incorporates 400 square feet of space and is set on a concrete foundation with a built-up roof. There was a single door opening. The Amplifier Facility and Cableway held all of the lines of power and communications between the Launch Pad and the Blockhouse. The Amplifier Facility housed equipment that boosted the signals on their way from the Pad to the Blockhouse. After the transfer back to the USAF in the facility was abandoned in The Amplifier Facility 76 Maurice H.

Connell & Associates, Inc., Drawings and Pan American World Airways, Inc., Drawing 34 Butowsky, National Register Nomination, Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Office of Manned Space Flight Launch Complex 34 Facilities: Fact Sheet 05, Cleary, Launch Facilities & Programs: Complexes 34 and 37 ; United States Air Force, Property Card Launch Complex 34 files. 77 United States Air Force, Property Cards and Launch Complex 34 files; Pan American World Airways, Inc., Basic Information Guide, United States Air Force, Voucher No. ; Al Hartmann, Volunteer, Air Force Space and Missile Museum, E-mail, 16 June and 26 June CCAFS, Archaeological Consultants, Inc., Sarasota. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 29) and the Cableway remain in place, although the Cableway is no longer roofed, and the cables and cable trays have been removed.78

Propellant Storage and Transfer Systems

Liquid Oxygen (LOX) Facility (No. The Liquid Oxygen (LOX) Facility (No. is situated approximately 650 south of the Launch Pad and Pedestal. Stored and transferred at Fahrenheit, LOX was utilized to fuel the first and second stages of the launch vehicle. This fuel storage area, which consisted of a LOX tank and a replenishing tank, was situated on a concrete slab foundation (Figure A reinforced concrete blast wall, with earthen fill on the north side, borders this fuel storage area on the north to separate the fuel from the Launch Pad and Pedestal.

The gallon capacity main fill tank was an insulated sphere with an outside diameter of An inner sphere, which actually contained the LOX, was separated from the outer sphere by of expanded perlite, a mineral insulating powder, in a pressurized gaseous nitrogen atmosphere. Utilizing a heat exchanger, a working air pressure of 30 pounds per square inch gage (psig) was maintained for self-pressurization. A 350 horsepower motor powered a gallon-per-minute, head pressure cryogenic pump to transfer LOX through an 8" line from the spherical tank to the vehicle booster during main fill operations.

When live upper stages were involved, a 175 horsepower electric motor powered a gallon-per-minute, head pressure cryogenic pump to transfer LOX through a 6" line in a fuel trench to the umbilical tower line. From here, individual lines led to the stage servicing connections during the main fill operations.79 A smaller gallon, 11' diameter cylindrical LOX tank was used to replenish the oxygen which evaporated during the latter stages of launch preparation. Vacuum-jacketed, perlite insulation insured low evaporation loss. The tank was self-pressurized to 200 psig working air pressure. The booster and upper stages were replenished through a 3" vacuum-jacketed line from the replenishing LOX tank to the umbilical tower line.

The liquid level in the booster LOX tanks was maintained with a pneumatically actuated modulating valve controlled by a LOX tanking computer and level control system. The LOX transfer system was completely automated and 78 United States Air Force, Property Cards and Launch Complex 34 files; Pan American World Airways, Inc., Basic Information Guide, United States Air Force, Voucher No. 79 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Office of Manned Space Flight, Launch Complex 34 Facilities: Fact Sheet 05, Maurice H. Connell & Associates, Inc., Drawings and CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 30) remotely controlled from panels in the Blockhouse.

Prior to propellant loading, the system component checkout was accomplished from either the Blockhouse or the LOX facility.80 Fuel Facility/Industrial Waste Storage Facility (Facility No. Electric Equipment Building (Facility No. and the Special Liquid Storage Building (Facility No. Approximately 950 southeast of the Launch Pad and Pedestal, the Fueling Facility, later known as the Industrial Waste Storage Facility (Facility No. was used to store and transfer this kerosene-based fuel utilized in the launch vehicle s first stage. Consisting of storage and transfer equipment set on a concrete slab, and its storage facility is separated from the launch area by a reinforced concrete blast wall and protective revetment which creates approximately square feet of space.

Two diameter, gallon insulated cylindrical tanks were used for fuel storage. The transfer system and associated plumbing consisted of two gallon-per-minute centrifugal pumps operating at 175 psig head pressure, a circulation pump, filter-separator unit, an eductor system, and miscellaneous valves, piping, and controls. The booster was serviced by the two gallons-per-minute pumps manifolded into an 8 transfer line set in a fuel trench. A fuel density indicator was used to monitor the fuel density at all times. The fuel tank of the vehicle was initially overfilled. The excess was drained by a tanking computer which would adjust the fuel level to 100 percent. When all of the vehicle s tanks were filled to the correct level, the jet eductor evacuated the transfer lines.

Prior to liftoff, the correct LOX fuel weight ratio was maintained by replenishing the LOX to the level dictated by the fuel level and density. The transfer system was completely automated and controlled from the Blockhouse. Prior to loading the vehicle with fuel, a system component checkout was automatically performed.81 The Fueling Facility and its support buildings, the Electric Equipment Building (Facility No. and the Special Liquid Storage Building (Facility No. were constructed in as part of the original facilities of the complex. The Electric Equipment Building powered the Fueling Facility. This small concrete building, with 216 square feet of space, is constructed on a concrete foundation topped by a built-up roof.

The Special Liquid Storage 80 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Office of Manned Space Flight, Launch Complex 34 Facilities: Fact Sheet 05, Master Planning, CCAFS Basic Information Guide. 81 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Launch Complex 34 Facilities: Fact Sheet 05, United States Air Force, Property Cards and 21900E, Launch Complex 34 files; Maurice H. Connell and Associates, Inc., Drawings and CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 31) Building also served as part of the Fueling Facility. With 252 square feet of space, the concrete building has a concrete foundation and a built-up roof.

Along with the rest of Complex 34, the Fueling Facility, the Electric Equipment Building, and Special Liquid Storage Building were transferred to NASA in NASA returned the three facilities to the USAF in All three remain on site. Liquid Hydrogen Facility (No.21900Q), Electrical Equipment Building (Facility No. and the High-Pressure Gaseous Hydrogen Storage Battery (Facility No. Utilized for servicing the hydrogen-fueled upper stages of the Saturn IB, the highly flammable Liquid Hydrogen Facility (No.21900Q), is situated approximately northeast of the Launch Pad, outside the perimeter road. It was constructed between and for the Saturn IB configuration.

A reinforced concrete blast wall and protective revetment separates the fueling facility from the launch area and provided partial weather protection. Liquid hydrogen was stored and transferred at Fahrenheit. The facility consisted of a spherical tank, pneumatic and electrical consoles, and necessary plumbing and valves. The stainless steel, 38' diameter, insulated and vacuum-jacketed spherical storage tank had a capacity of gallons. A vacuum pump was provided for use in the storage tank purging and inerting sequence, which was required prior to the initial filling. The LH2 tank was filled and replenished by pressure transfer through a 5" vacuum-jacketed line set in a fuel trench. A 100 psig tank working pressure was maintained for transfer operations.

The system had the capability to deliver gallons per minute with a replenish rate of 0 to 200 gallons per minute, and a fine-fill rate of 500 gallons per minute. Because LH2 is highly explosive, all of the electric starters and distributors for the facility were located in nitrogen-purged panels in a building removed from the storage tank. Special ducting systems on the vehicle and umbilical tower disposed of the gaseous hydrogen resulting from the vehicle tank cooldown operations and venting of the loaded tank. These ducting systems removed the hydrogen to the LH2 Burn Pond situated northwest of the LH2 storage area. The transfer system was completely automated and remotely controlled from the Blockhouse. An Electrical Equipment Building (Facility No.

provided power to the 82 United States Air Force, Property Cards 21900E, 18410A, and Launch Complex 34 files. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 32) facility. With 240 square feet of space, the concrete building has a concrete foundation and a built-up roof.83 The High Pressure Gaseous Hydrogen Storage Battery (Facility No. is located immediately southwest, between the LH2 Facility and the perimeter road. Constructed in this facility supplied cold hydrogen gas for launch vehicle pneumatic requirements. The facility consisted of two 200 cubic foot cylindrical gaseous hydrogen vessels capable of delivering a maximum pressure of pounds per square inch (psi). The tanks sat on a concrete slab and were surrounded on three sides by concrete walls.

After NASA returned the complex to the USAF in these facilities were retired in The blast wall, concrete partial walls, and Facility No. remain in place. High Pressure Gas Facility (Facility No. and High Pressure Gas Battery (Facility No. 21900U) The original High Pressure Gas Facility (No. was constructed in east of the Blockhouse and south of the Launch Pad and Pedestal. The High Pressure Gas System converted, stored, and transferred gaseous nitrogen and helium to the vehicle and various functional stations during prelaunch operations. The system provided high pressure gas for vehicle checkout, purging and pressurization, for functional operation of certain ground support equipment, and for charging the vehicle storage spheres which supply the in-flight requirements.

Gaseous nitrogen was used to charge the vehicle storage spheres for in-flight consumption, to operate ground service equipment components, and as a purging agent. Helium was used for first stage pressurization, for upper-stage in-flight storage spheres, and for liquid oxygen tank bubbling to prevent temperature stratification prior to launch. This facility consists of a x x high concrete revetted, vault-type structure with square feet of space, which was used to store cylinders (batteries) of high-pressure helium and nitrogen gases. The facility incorporated storage and transfer facilities, filters, control panels, and measuring devices.

The 83 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Launch Complex 34 Facilities: Fact Sheet 05, United States Air Force, Property Card Launch Complex 34 files; Pan American World Airways, Inc., Basic Information Guide, Maurice H. Connell & Associates, Inc., Drawing 01- 84 Launch Complex 34 Facilities: Fact Sheet 05, United States Air Force, Property Card Launch Complex 34 files; United States Air Force, Voucher Nos. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 33) measuring devices were for the control of contamination, moisture, and hydrocarbon content of the stored gases.

The storage system consisted of a cluster of psig storage cylinders.85 Nitrogen and helium were supplied and stored in two mobile transfer/converter vehicles which connected to the fixed, high-pressure storage battery facility. Nitrogen, procured in liquid form and converted to gas, was utilized to purge fuel and LOX lines, engine and instrument compartments, and to operate certain pneumatic components. The liquid nitrogen was converted to a high-pressure gas at psig through the use of electrical heaters and ethylene glycol/liquid nitrogen heat exchangers integral with the transfer vehicle. Four stainless-steel lines transferred the gaseous nitrogen to a primary distributor station in the mechanical room of the Automatic Ground Control Station at the launch pad.

Once at the pad, the pressure of the gas was reduced to psig for further distribution to the using points. A pressure-reducing valve complex at the storage site supplied nitrogen at psig to the LOX and fuel storage areas.86 Helium, procured at psi pressure, was compressed and stored in a pressure battery at psi. Used for bubbling the LOX tanks of the booster and to prevent the LOX from forming strata of different temperatures, the gaseous helium was delivered to the storage site at psig pressure in mobile transfer/converter vehicles which were connected to the fixed, high-pressure storage battery facility.

Two trailer-mounted, motor driven helium booster compressors with 70 standard cubic feet per minute capacity located within the storage structure raised the pressure to psig, after which it was stored in bottles. Helium at psig was delivered to the primary pneumatic distributor in the mechanical room of the Automated Ground Control Station to the base of the Launch Pedestal.87 Alterations to the complex in for the Saturn IB configuration included the elimination of the mobile storage and vaporizer vehicles. The batteries were subsequently replenished from the central converter-compressor facility designed to service both Launch Complexes 34 and 37. A new High Pressure Gas Battery (Facility No.

21900U) was constructed east of the Launch Pad to 85 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Office of Manned Space Flight, 2-7 thorough Figure United States Air Force, Property Cards and Launch Complex 34 files. 86 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Office of Manned Space Flight, 2-7 through Figure 87 Launch Operations Center, LC Launch Complexes and Ground Support Equipment, Office of Manned Space Flight, 2-7 thorough Figure CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 34) provide additional storage space closer to the Launch Pad for the expanded number of high- pressure nitrogen and helium storage batteries necessary for the new vehicle.88 By storage for liquid nitrogen was provided by a gallon, double-walled, spherical tank and a gallon tank. Liquid nitrogen was converted to gaseous nitrogen through the use of four high-pressure vaporizers and two low-pressure vaporizers. It was then transferred to gaseous nitrogen storage batteries. Four 200 cubic foot vessels and six clusters of nine vessels each cubic feet per cluster) were manifolded together to form the nitrogen battery.

Helium was compressed by means of three separate, four-stage compressors and was stored in the helium storage battery which consisted of six clusters of nine vessels each cubic feet per cluster) manifolded together. The High Pressure Gas Facility and the High Pressure Gas Battery were abandoned in place in The High Pressure Gas Facility remains on site, and has been categorized as a storage facility since The main concrete wall of the High Pressure Gas Battery also remains in place.

Blockhouse and Technical Support Area

Blockhouse (Facility No. Electrical Substation (Facility No. and Septic Tank (Facility No. Situated approximately southwest of the Launch Pad, the domed Blockhouse (Facility No. was constructed in and operated as the launch control center housing the communications, instrumentation, and control consoles. The interior of the 120'-diameter dome features square feet of floor space on two floors (Figure For the construction of the Blockhouse in a large area was excavated and partially filled with sand onto which the reinforced concrete foundation was poured (Figure The 12-sided, dome-shaped portion of the building consists of three different layers.

The inner dome is constructed of reinforced concrete, poured approximately 5' thick, and covered by sand varying in thickness from at the apex of the dome to at the base. The earthen fill is covered with a 4"-thick layer of shotcrete. The interior of the dome is sprayed with a 2" coat of acoustical material. A special blastproof door weighing 23 tons further insulates the structure to withstand blast pressure of 88 Office of Manned Space Flight, 2-7 through and Figure 89 Launch Complex 34 Facilities: Fact Sheet 05, United States Air Force, Property Cards and Launch Complex 34 files; United States Air Force, Voucher Nos. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 35) psi equivalent to the explosion of 50 kilotons of TNT at a distance of necessary should a missile explode on the pad or near the launch site.90 These insulating layers provide the Blockhouse with an interior diameter of 80' and a maximum height of The first floor was utilized by booster and upper stage contractor personnel who were involved in closed-circuit television and tracking, telemetry, and communications operations. The first floor held two Instrument Rooms, an RF and Telemetry Room, a Terminal Room, a Range Terminal and Utility Area, a Ready Room, and a Toilet Room. The entrance to the Blockhouse is inset through a flat-roofed extension on the west side of the building.

In addition to the inset entrance, this extension held an Equipment Room and Toilet Room and was subsequently enlarged in Communication and power lines linking the Blockhouse to the other facilities at the complex entered the building through the Cableway which met the building on the northeast corner. The lines stretched from the Cableway through an underground trench to an Instrumentation Pit at the east end of the Blockhouse, and extended throughout the Blockhouse through Instrumentation Trenches beneath the floor. With the exception of the restrooms which have ceramic tile floors, the remaining rooms on the first floor have steel trowel floors, gypsum board and exposed concrete walls, and ceilings with exposed steel.

Emergency escape tunnels are located in the northwest and southwest corners. An equipment elevator and stairs to the second floor are located in the northwest corner of the building.91 The second floor held launch supervision and monitoring and recording panels (Figure The majority of the second floor was occupied by the Instrument Room, also known as the Control Room. A small Observation Room was separated by glass from the operating area. An observation balcony on top of the building provided an aerial view during pre-launch activities. These two rooms have asphalt tile floors, a ceiling covered with acoustical spray-on material, and walls with a rubber base topped by exposed concrete.

Two periscopes in the control room and an eight-station, closed-circuit television network provided views of the launch. These periscopes and most of the interior finishes remain intact.92 An Electrical Substation and a Septic Tank with a capacity of gallons served the Blockhouse.

The transformers have been 90 Launch Complex 34 Facilities: Fact Sheet 05, Technical Facilities Catalog: Volume II, Office of Manned Space Flight, 2-5 through Master Planning, CCAFS Basic Information Guide; Rader and Associates, Drawings 01- and Launch Operations Center, 91 Launch Complex 34 Facilities: Fact Sheet 05, Launch Operations Center, Office of Manned Space Flight, 2-5 through Rader and Associates, Drawing 92 Launch Complex 34 Facilities: Fact Sheet 05, Launch Operations Center, Office of Manned Space Flight, 2-5 through LC Launch Complexes and Ground Support Equipment, 6; Rader and Associates, Drawings 01- and CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 36) removed from the Electrical Substation.93 Along with the rest of the complex, the Blockhouse was transferred from the USAF to NASA in In NASA returned the Blockhouse to the USAF. The Blockhouse is currently used for storage.94 Operations Support Building/Engineering Support Building (former Facility No. Situated southwest of the Blockhouse, the Operations Support Building (former Facility No. had square feet of space and was constructed in The one-story building provided laboratory facilities for measurement and calibration of telemetry and ground support equipment, network checkout, missile component checkout and evaluation, and prelaunch test and post-launch data review and evaluation.

Utilized for general shop and engineering activities in direct support of launch operations, the building also provided space for critical parts storage, mechanical equipment, clean room, and personnel work areas.95 The concrete block Operations Support Building was set on a concrete foundation and topped by a flat roof. Although many of the structures at the complex were transferred from NASA back to the USAF in the Operations Support Building remained under NASA s purview. After the deactivation of the complex, the Operations Support Building served a number of different uses including office space, a hazardous materials storage facility, and a records storage facility. The building was demolished in or An Electrical Substation (former Facility No.

and a gallon Septic Tank (former Facility No. served the Operations Support Building.96 Three Hazardous Waste Storage Sheds (former Facilities No. No. and No. were located west of the Operations Support Building. All three, constructed in were metal buildings with metal roofs and set on concrete foundations with 50 square feet of space.97 The sheds were removed between and 93 Master Planning, CCAFS Basic Information Guide; United States Air Force, Property Cards and Launch Complex 34 files. 94 United States Air Force, Property Cards and Launch Complex 34 files. 95 Technical Facilities Catalog, Office of Manned Space Flight, Launch Complex 34 Facilities: Fact Sheet 05, United States Air Force, Property Card Launch Complex 34 files; United States Air Force, Voucher No.

96 Launch Operations Center, Pan American World Airways, Inc., Basic Information Guide, Master Planning, CCAFS Basic Information Guide; United States Air Force, Property Cards and Launch Complex 34 files; Engineering and Environmental Planning, CCAS Basic Information Guide, United States Air Force, Voucher No. 63- 97 Master Planning, CCAFS Basic Information Guide; United States Air Force, Property Card Launch Complex CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 37) Paints, Oils, Lubricants, Cleaning Fluids (POLCF) Building (former Facility No. The Paints, Oils, Lubricants, Cleaning Fluids (POLCF) Building (former Facility No. was south of the High Pressure Gas Facility on the outer edge of the perimeter road.

The POLCF building, with square feet of space, was constructed in Soon after NASA transferred the complex back to the USAF in this building was removed from the records kept by the Real Property Office in and thereafter demolished.98 Sentry Houses (Facilities No. and No. Two metal Sentry Houses were located at Launch Complex 34. The first Sentry House (Facility No. was a metal building incorporating 44 square feet of space set on a concrete foundation with a built-up roof. Constructed in as part of the original complex, this Sentry House was located on the southeast side of the entrance road, across from the Operations Support Building. The second Sentry House (Facility No. was also a metal building with 44 square feet of space, a concrete foundation, and built-up roof.

Located on the northwest side of the entrance road, north of the Operations Support Building, this Sentry House was originally constructed in as Facility No. It was relocated through the salvage yard to Complex 34 in July Used only intermittently after the complex was abandoned in both Sentry Houses were demolished by Administration Office In NASA installed ten x metal trailers joined together to form an Administration Office. After the complex was deactivated, the trailers were relocated to Launch Complex 30 as Facility No. in 34 files; Engineering and Environmental Planning, CCAS Basic Information Guide, 98 United States Air Force, Property Card Launch Complex 34 files; United States Air Force, Voucher Nos.

62- and 99 United States Air Force, Property Cards and Launch Complex 34 files; Pan American World Airways, Inc., Basic Information Guide, 100 United States Air Force, Property Card Launch Complex 34 files. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 38)

Additional Ground Support Equipment

The Communications System at Launch Complex 34 consisted of closed-circuit television, a Norcom two-wire intercom system of 300 units, and a paging system integrated with other systems by means of a switching system. The closed-circuit television system incorporated 20 television monitors and 11 cameras which had complete mass switching capability from the Blockhouse. Cameras provided numerous views of prelaunch activities throughout the complex. In addition, several control panels throughout the complex were tied into computer systems at the Mission Control Center in Houston, the worldwide tracking network at the Goddard Space Flight Center, and offices in Washington, Electrical, water, and fire-suppression systems supported the activities at Launch Complex 34.

In addition to the primary support structures, cabling and pipeline connected the structures to form a cohesive complex. Cabling and pipeline included of water distribution system, of sewage disposal system, of grounding system, of power lines, and of lines for the High Pressure Gas System, as well as the cableway system itself.102

Modifications and Deactivation

Initially constructed to launch the Saturn I, Launch Complex 34 was the site of four Saturn I launches between October and March (Figure In November the USAF transferred the complex to NASA. The USAF and NASA modified the complex between and to launch the Saturn IB, which was first launched in February The more advanced vehicle configuration led primarily to alterations and upgrades to the fueling systems. Computers, graphic flow-chart panels, lines, and valving at the (Facilities No. No. and No. and LOX facilities (No. were upgraded and replaced. The mobile storage and vaporizer vehicles utilized to supply gaseous nitrogen and helium to the High Pressure Gas Facility (Facility No. were eliminated.

The batteries were subsequently replenished from the central converter-compressor facility designed to service both Launch Complexes 34 and 37. A new High Pressure Gas Battery (Facility No. 21900U) was constructed east of the Launch Pad in to provide additional storage space closer to the Launch Pad for the expanded number of high-pressure nitrogen and helium storage batteries necessary for the 101 Launch Complex 34 Facilities: Fact Sheet 05, 102 United States Air Force, Property Card Launch Complex 34 files. 103 Launch Complex 34 Facilities: Fact Sheet 05, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 39) new vehicle. The entire Liquid Hydrogen Facility (No. including the storage tank, a burn pond, and its associated Electrical Equipment Building (Facility No.

were constructed northeast of the Launch Pad in for the new configuration. Adjacent to the Liquid Hydrogen Facility, NASA built the High Pressure Gaseous Hydrogen Storage Battery and Burn Stack (Facility No. in The Theodolite Building (Facility No. also known as the Alignment Building, was constructed in to house a theodolite utilized in maintaining the azimuth alignment. NASA also installed temporary metal trailers to form an Administration Office. Alterations to the Mobile Service Structure included modifying the service platform inserts to conform with the revised configuration of the new vehicle and adding three enclosures, one at the level and two at the level, for measuring and networks activities.

Modifications to the Umbilical Tower included the addition of one swing arm to support the Apollo spacecraft and two umbilical swing arms, one to facilitate propellant loading and one for electro-mechanical operations and checkout and to support cables and lines to the vehicle. In addition, the existing hold-down and support arms were replaced with new arms to conform to the revised configuration of the new vehicle. The Automatic Ground Control Station facility was modified with a revamped computer room and upgrades to the mechanical equipment to support the Saturn 1B. The Environmental Control System Building was constructed on the Launch Pad to provide conditioned air for the launch vehicle through the Umbilical Tower.

Two concrete-slab Toxic Vapor Disposal Pads were constructed in south of the Launch Pad and on either side of the road leading from the LOX Facility to the Launch Pad. Short access roads led to the facilities. The west pad (Facility No. was for Oxidizer venting, while the east pad (Facility No. was for fuel. By Launch Complex 34 had reached its mature configuration (Figure A switching station (Facility No. was added near the existing Sentry House (Facility No. in A second Sentry House (Facility No. was moved to the complex in Most of the alterations following the tragedy of Apollo I in January involved modifications to the spacecraft. The wiring, the escape hatch, the environmental control system, and the space suits were redesigned.

The atmosphere in the spacecraft was changed to 60 percent oxygen and 40 percent nitrogen. Fans, water hoses, fire extinguishers, and an escape slide wire were added to 104 Office of Manned Space Flight, 2-9 through and Figure United States Air Force, Property Cards and Launch Complex 34 files; Hartmann, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 40) the white room. In case of another fire, astronauts and workers could ride the escape slide wire to the ground in seconds.105 The success of the Saturn IB, further development of the Saturn launch vehicle, and the construction of Launch Complex 39 at Kennedy Space Center led to the termination of further Apollo development flights from Launch Complex 34.

The Complex was reduced from an operationally ready state to a downmoded configuration in October and a Phaseout Plan was approved in April The Complex was mothballed in November and the Service Structure and Umbilical Tower were razed in April due to excessive rust and deterioration. Launch Complex 34 was officially abandoned in October with most of the facilities transferred back to the USAF s control in November NASA retained control of the Operations Support Building and the Blockhouse, which served as a site for NASA tour stops, until it was transferred back to the USAF in The former location of the Operations Support Building is now occupied by equipment and two new buildings that are not related historically to Complex 34. The new construction is surrounded by a fence.

Soon after the complex was officially abandoned, many of the structures at the complex were removed from the real property records, demolished, or moved to other complexes. The Umbilical Tower and Service Structure were demolished in The fuel tanks, pumps, and machinery at the Launch Pad, LOX Facility, LH2 Facility, Gaseous Hydrogen Facility, High Pressure Gas Facility, High Pressure Gas Battery, and Fueling Facility were removed following the deactivation of the complex, along with electrical substations and other miscellaneous equipment. It is not known when the E.C.S. Building was demolished, but it is likely this occurred at the same time as the demolition of the Service Structure and the Umbilical Tower.

The trailers which formed the Administration Office were relocated to Launch Complex 30 as Facility No. in The POLCF Building was demolished around 105 Benson and Faherty, 106 Phaseout Plan, (John F. Kennedy Space Center: National Aeronautics and Space Administration, Prologue, Archives, Kennedy Space Center, LOC Box 2. 107 Master Planning, CCAFS Basic Information Guide; Cleary, Launch Facilities & Programs: Complexes 34 and 37 ; United States Air Force, Property Cards and Launch Complex 34 files; Butowsky, National Register Nomination, 108 United States Air Force, Property Cards and Launch Complex 34 files; United States Air Force, Voucher Nos. and CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 41) In the Phased Array Radar Pedestal (Facility No.

Van Shelter (Facility No. Toilet (Facility No. Septic Tank (Facility No. Optical Tracker (Facility No. and Electrical Substation (Facility No. were constructed on the southeast side of the entrance to Launch Complex 34. A Shop/Storage Building (Facility No. was subsequently built in the same area in followed by two Electrical Substations: Facility No. in and Facility No. in These facilities, which are not historically part of Launch Complex 34, are now inactive, and the radar has been removed.109 Three Hazardous Waste Storage Sheds (Facilities No. No. and No.

were constructed west of the Operations Support Building as part of NASA s operations in These storage sheds were demolished between and and the Operations Support Building was demolished in or Used only intermittently after the complex was abandoned in both Sentry Houses were demolished by Launch Complex 34 was listed as part of the Cape Canaveral Air Force Station National Historic Landmark District on April 16, In honor of the astronauts lost in Apollo 1 and the goals achieved at Launch Complex 34, a Historical Site Kiosk (Facility No.

was erected on the Launch Pad in Although the equipment has been removed, the Launch Pad and Launch Pedestal, the Blockhouse, the concrete structures and blast walls of the fueling facilities, the Flume and Skimming Basin, the Amplifier Facility and Cableway, the Theodolite Building, the High Pressure Gas Facility, the buildings, the Liquid Hydrogen Electrical Equipment Building, and the road network remain in place, and the Flame Deflectors remain parked in their service area (Figure 109 United States Air Force, Property Cards and Launch Complex 34 files. 110 Master Planning, CCAFS Basic Information Guide; United States Air Force, Property Card Launch Complex 34 files. 111 United States Air Force, Property Cards and Launch Complex 34 files.

112 United States Air Force, Property Card Launch Complex 34 files. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 42)

Bibliography

Barton, David and Richard S. Levy. An Architectural and Engineering Survey and Evaluation of Facilities at Cape Canaveral Air Force Station, Brevard County, Florida. Resource Analysts, Inc., 16 March Benson, Charles D. and William B. Faherty. Moonport: A History of Apollo Launch Facilities and Operations. National Aeronautics and Space Administration, Scientific and Technical Information Office, reprint as Gateway to the Moon: Building the Kennedy Space Center Launch Complex and Moon Launch! A History of the Saturn-Apollo Launch Operations, Gainesville: University Press of Florida, Bramlitt, E.R. History of Canaveral District South Atlantic Division, US Army Corps of Engineers, Butowsky, Harry.

Man in Space (Reconnaissance Survey) Denver: National Park Service, National Register of Historic Places Nomination Form/National Historic Landmark Federal Agency Nomination: Cape Canaveral Air Force Station. Washington, National Park Service, Cleary, Mark. Space Wing: Its Heritage, History & Honors Launch Facilities & Programs: Complexes 34 and 37. Space Wing Office of History, Patrick AFB, Eastern Range Launches, 11 December Eastern Test Range Launch Complexes, Cape Canaveral AFS. Space Wing Office of History, Patrick AFB, 16 April Engineering and Environmental Planning. CCAS Basic Information Guide: Facilities, Utilities, Instrumentation, and Communications. Cape Canaveral Air Station: Johnson Controls World Services, Inc., Exploring Space Project Mercury. U.S.

National Aeronautics and Space Administration. Sweetsir Collection Box 12. Kennedy Space Center: Kennedy Space Center Archives. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 43) Gibson, James N. Nuclear Weapons of the United States: An Illustrated History. Atglen, PA: Schiffer Publishing, Hall, R. Cargill. Civil-Military Relations in America s Early Space Program. In The U.S. Air Force in Space: to the Century, Proceedings Air Force Historical Foundation Symposium, Andrews AFB, Maryland, September ed. R. Cargill Hall and Jacob Neufeld, Washington, USAF History and Museums Program, United States Air Force, Hartmann, Al, volunteer, Air Force Space and Missile Museum. E-mail, 16 June and 26 June Archaeological Consultants, Inc., Sarasota. Phaseout Plan. John F.

Kennedy Space Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 2. LC Launch Complexes and Ground Support Equipment. John F. Kennedy Space Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 1. Launch Complex 34 Facilities: Fact Sheet 05. John F. Kennedy Space Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 1. Launch Operations Center. Launch Complex 34. Kennedy Space Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 1. Lethbridge, Clifford J. Apollo 7 Fact Sheet. Spaceline.org, Spaceline, Inc., Cape Canaveral Rocket and Missile Box Scores. Spaceline.org, Spaceline, Inc., Cape Canaveral Launch Sites Box Scores.

Spaceline.org, Spaceline, Inc., Saturn I Fact Sheet. Spaceline.org, Spaceline, Inc., Saturn IB Fact Sheet. Spaceline.org, Spaceline, Inc., Saturn V (Apollo) Fact Sheet. Spaceline.org, Spaceline, Inc., Lockyer, William A., Jr. A Summary of Major NASA Launchings: October 1, 1958-September 30, KSC Historical Report No. 1. John F. Kennedy Space Center: KSC Historical Services, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 44) Master Planning. CCAFS Basic Information Guide: Facilities at CCAFS and KSC 2. Kennedy Space Center: Space Gateway Support, October Maurice H. Connell & Associates, Inc. Air Force Missile Test Center, Complex 34. Drawings Complex 34 Launch Facilities: Location & Vicinity Maps and Index to Drawings, 01- U-34-A1, and U-34-A2.

Research Planning/Design Engineering Office, Kennedy Space Center. Messick, Denise P., Cynthia G. Rhodes, and Charles E. Cantley. Space Wing Cultural Resource Management Plan. Technical Report No. Stone Mountain, Georgia: New South Associates, Neufeld, Jacob. The Development of Ballistic Missiles in the United States Air Force, Washington, Office of Air Force History, United States Air Force, Office of Manned Space Flight. Apollo Systems Description, Volume III. Launch Operations Center: National Aeronautics and Space Administration, Archives, Kennedy Space Center, LOC Box 1. Pan American World Airways, Inc. Basic Information Guide, Cape Canaveral Missile Test Annex, Research Planning/Design Engineering and Real Property Offices, Kennedy Space Center.

Basic Information Guide, Cape Canaveral: Facilities, Utilities, Instrumentation, and Communications, Cape Canaveral Air Force Station: Facilities Engineering Department, Cape Kennedy Air Force Station: Building Schedules and Locations. Patrick Air Force Base, FL: Facilities Planning Section, Basic Information Guide, Cape Canaveral Air Force Station, Research Planning/Design Engineering and Real Property Offices, Kennedy Space Center. Saturn Launch Complex 34. Drawing 34 Research Planning/Design Engineering Office, Kennedy Space Center. Rader and Associates. Air Force Missile Test Center: Complex 34. Drawings 01- Research Planning/Design Engineering Office, Kennedy Space Center. Real Property Cards, Cape Canaveral Air Force Station. Space Wing Office of History, Patrick AFB.

CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 45) Spires, David N. The Air Force and Military Space Missions: The Critical Years, in The U.S. Air Force in Space: to the Century, Proceedings Air Force Historical Foundation Symposium, Andrews AFB, Maryland, September ed. R. Cargill Hall and Jacob Neufeld, Washington, USAF History and Museums Program, United States Air Force, Technical Facilities Catalog: Volume II. Washington, National Aeronautics and Space Administration, Archives, Kennedy Space Center, NHB 8800.5(I), LOC 23A.2N. United States Air Force. Real Property Accountable Record-Inventory Detail. Launch Complex 34 files. Property Cards 18410A, 21900E, and Space Gateway Support Company, GIS Real Property Office, John F. Kennedy Space Center.

Real Property Voucher. Voucher Nos. Space Gateway Support Company, GIS Real Property Office, John F. Kennedy Space Center.

Historic Drawings

As of the technical drawings used for research in this study have not been cleared for release to the public domain. It is, therefore, not possible to reproduce in this document the drawings that were used to gather information about the design, construction, and use of facilities at Launch Complex 34, CCAFS. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 46) APPENDIX: FIGURES FROM DATA PAGES Figure 1. Location of Launch Complex 34,

Ccafs. U.s

Air Force Space and Missile Museum. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 47) Figure 2. Saturn I Launch and Missile Statement. Appendix A, Figure 1, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 48) Figure 3. Preliminary Concept of Launch Complex 34. Figure 5, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 49) Figure 4. Saturn 1 (SA-1) on launch pad before first launch of a Saturn vehicle, October 27, NIX (Document) ID: NASA Information Exchange, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 50) Figure 5. Fourth Launch of Saturn I, March 28, NIX (Document) ID: NASA Information Exchange, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No.

(Page 51) Figure 6. Saturn IB Launch Vehicle and Missile Statement. Appendix A, Figure 2, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 52) Figure 7. First Launch of Saturn IB, February 26, Figure NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 53) Figure 8. Apollo I astronauts in front of Pad at Launch Complex 34, January 17, NIX (Document) ID: NASA Information Exchange, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 54) Figure 9. Launch of Apollo 7, Apollo s first manned launch, October 11, Photograph Johnson Space Center, Office of Public Affairs, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 55) Figure 10. President John F.

Kennedy and officials in briefing in second floor of Blockhouse, September 11, Photo Kennedy Space Center, Great Images in NASA, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 56) Figure 11. Dr. von Braun and Don Ostrander, head of the Launch Vehicle Program at NASA Headquarters, look at a model of Launch Complex 34 in NIX (Document) ID: NASA Information Exchange, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 57) Figure 12. Launch Complex 34, Basic Information Guide, Pan American World Airways, Inc. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 58) Figure 13. Launch Complex 34, Basic Information Guide, Pan American World Airways, Inc. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 59) Figure 14.

Construction of Launch Pedestal at Complex 34, Figure 6, Benson and Faherty, Moonport. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 60) Figure 15. Saturn I on Launch Pedestal with Umbilical Tower, in preparation for March 28, launch. Figure NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 61) Figure 16. Launch Pad, Umbilical Tower, Environmental Control System Building, and Mobile Service Structure Figure NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 62) Figure 17. Saturn I on Launch Pedestal surrounded by Mobile Service Structure, Fall Figure 81, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 63) Figure 18.

Liquid Oxygen Facility at Complex 34, date unknown. Figure 11, Benson and Faherty, Moonport. CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 64) Figure 19. Model of Blockhouse, Launch Complex 34, date unknown. Figure 11, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 65) Figure 20. Blockhouse and Mobile Service Structure under construction, Figure 38, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 66) Figure 21. Blockhouse, Interior of Second floor, date unknown. Figure 59, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 67) Figure 22.

Aerial view of Launch Complex 34 from north, Figure 58, NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 68) Figure 23. Aerial view of Launch Complex 34 from east, ca. Figure NASA History Office, CAPE CANAVERAL AIR FORCE STATION, LAUNCH COMPLEX 34 HAER No. (Page 69) Figure 24. Launch Complex 34, Basic Information Guide, SGS Master Planning, Cape Canaveral Air Force Station/Kennedy Space Center.

In context

Cape Canaveral, Florida The place record: every map, photograph and survey of this town.
Brevard County, Florida 134 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Cape Canaveral

24 of 118 records shown

The federal surveyors worked through Cape Canaveral building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
Cape Canaveral Air StationHAER FLA,5-CACAN,1-32,823 words
Cape Canaveral Air Force StationHAER FL-8-1232,234 words
Cape Canaveral Air Force StationHAER FL-8-AO27,461 words
Cape Canaveral Air Force StationHAER FL-8-11-B25,294 words
Cape Canaveral Air Force StationHAER FL-8-11-F22,264 words
Cape Canaveral Air Force StationHAER FL-8-11-O19,777 words
Cape Canaveral Air Force StationHAER FL-8-AV18,663 words
Cape Canaveral Air Force StationHAER FL-8-11-M17,593 words
Cape Canaveral Air Force StationHABS FL-581-A17,410 words
Cape Canaveral Air Force StationHAER FL-8-11-G17,133 words
Cape Canaveral Air Force StationHAER FL-8-11-J16,548 words
Cape Canaveral Air Force StationHABS FL-581-B14,684 words
Cape Canaveral Air Force StationHAER FL-8-11-L13,962 words
Cape Canaveral Air Force StationHABS FL-583-A13,824 words
Cape Canaveral Air Force StationHAER FL-8-11-R13,738 words
Cape Canaveral Air Force StationHABS FL-581-C13,646 words
Cape Canaveral Air Force StationHAER FL-8-713,389 words
Cape Canaveral Air Force StationHAER FL-8-A12,671 words
Cape Canaveral Air Force StationHAER FL-8-11-D12,041 words
Cape Canaveral Air Force StationHAER FL-8-11-K12,011 words
Cape Canaveral Air Force StationHAER FL-8-11-A11,934 words
Cape Canaveral Air Force StationHAER FL-8-11-P11,823 words
Cape Canaveral Air Force StationHAER FL-8-11-S11,622 words
Cape Canaveral Air Force StationHAER FL-8-11-C11,607 words

Provenance

  • Written history. Quoted verbatim from HAER FL-8-6. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.