Crocker Reef Guard Gate, located on the Champlain Canal, is a component of the New York State Barge Canal. It is one of several guard gates built on the land-cut sections of the system. Description: The guard gate is located at the upstream end of an artificial channel section of the Champlain Canal built to bypass the Hudson River.1 When lowered, the gate could stop the flow of water into this section of the canal, which would have been necessary for maintenance or in periods of high water and rainfall.2 The northwest and southwest concrete approach walls to the guard gate are in fair to poor condition with sections of cracking and spalling. The 55'-wide, steel guard gate is flanked by steel lattice towers that sit on the concrete channel walls.
Cables and counterweights are used to raise and lower the gate. A modern gabled machinery shelter is located on the top of the gate. This guard gate differs from the standard form elsewhere on the Barge Canal in that there is not a bridge spanning the two towers. A sluice gate is located to the east of the guard gate and has a steel pulley system. The concrete platform of the sluice gate appears modern. To the west of the guard and sluice gates is a fixed crest concrete dam with an ogee spillway extending from Thompson Island across the Hudson River.
History: On April 18, Empire Engineering Company won Contract 1, which involved excavating the river channel from Northumberland to Fort Miller, and from Crocker s Reef to Fort Edward, the construction of Crocker s Reef dam, the approaches to the head and foot of The Land Line and other incidental work. By August the east spillway and abutments for Crocker s Reef Dam had been completed, and the following month the cofferdam for the west spillway in the west channel of the river had been erected. The dam was completed in 1 Description of current conditions is based on a site visit made by the HAER recording team in summer and historical maps from Series New York State Archives, Albany, New York. See Eastern Division, Champlain Canal, Section 2, Sta. 231 + 00 to Sta.
259 + 09, approved April 2, 57. 2 Michele McFee, A Long Haul: The Story of the New York State Barge Canal (Fleischmanns, NY: Purple Mountain Press, 3 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 76, Annual Report of the State Engineer and Surveyor of NEW YORK STATE BARGE CANAL, CROCKER REEF GUARD GATE HAER No. (Page 2) James D. Sherrill of Hudson Falls, New York, built the guard gate on November 1, as part of Contract 24. The work was later reassigned to Kingsbury Construction Company of Hudson Falls, New York, on June 3, Edward W.
Wendell, State Assistant Engineer, oversaw the project.4 The west guide wall to the guard gate and the abutment supporting the west tower had been completed in The following year, the guard gate and towers were in place, and the operating machinery had been installed. The walls of the sluice gate structure were completed, and the hoists were in place and operational. The contractors had nearly finished the concrete work, with the exception of the counterweights. The contract was completed in