Lock C7, located on the Champlain Canal, is a component of the nationally significant New York State Barge Canal. The lock retains the original DC electro-mechanical gate and valve operating machinery. Description: Lock C7 marks the downstream end of the artificial channel section of the Champlain Canal, which extends from this point up to the canal s terminus. The site consists of the lock and associated structures and operating equipment and the lockhouse. Locks C7 and C8 shared a powerhouse, which was located at Lock C8, 2 miles away.1 The lock is accessed from a long asphalt road set on a berm paralleling the canal. Three modern steel pipe culverts are located along the length of the access road, which leads to an asphalt parking area.
The lockhouse, which is probably original, is located on the southeast bank of the lock. The one- story frame building sits on a concrete foundation and is clad in horizontal wood clapboards. Asphalt shingles cover the gabled roof. One-over-one vinyl windows light the building, and modern pane-and-panel doors provide access. A garage is located at the south end of the structure. The building is in good condition. A modern shed is located southwest of the lockhouse. The frame structure is clad in horizontal wood siding and sits on a concrete foundation. Asphalt shingles cover the gable roof. The lock has a 10' lift with normal pool elevations below and above. Its concrete chamber walls feature vertical cut-outs for pipe mooring aides.
The walls are in fair condition due to cracking and spalling. There are double-leaf, steel miter lock gates at each end of the chamber, operated by spars and gear trains powered by the original DC electro-mechanical gate machinery. This machinery, along with the valve operating machinery used to control flow of water through the culverts in the chamber walls, is housed in steel cabinets on the chamber walls. There are also modern electrical boxes on the chamber walls. The lock features diamond-plate covers, wood catwalks, and concrete stairs. A foot bridge is located at the downstream end of the chamber, downstream of the lock gates. The lock has modern light fixtures. The lock gates and valves are operated from two control stand shelters on the east side of the lock.
These frame 1 Description of current conditions is based on a site visit made by the HAER recording team in summer and historical maps from Series New York State Archives, Albany, New York. See Eastern Division, Champlain Canal, Section 2, Sta. + 00 to Sta. + approved April 2, 70. NEW YORK STATE BARGE CANAL, LOCK C7 HAER No. (Page 2) structures have synthetic siding, single pane wood pop-out windows, and a wood door. The lock is in generally good condition aside from the chamber walls. The southeast concrete approach wall to the lock has wood bumpers. The wall is spalling in some areas and is in fair condition. The northwest concrete approach wall also has some spalling and is in fair condition. The northeast approach exhibits extensive spalling and is consequently in poor condition.
A loading dock located approximately halfway down the access road consists of a steel I-beam superstructure with a steel plank deck surrounded by pipe railing. Steel walls with concrete rails set on them appear to form the dock s foundation. There are also steel pilings located around the dock. A notation of can be seen on the dock. History: Lock C7 was originally included in Contract 27, which encompassed the construction of Champlain Canal locks 7 and 8, as well as the canal prism from Fort Edward to Dunhams Basin. The Kinser Construction Company won the contract on November 23, As planned in Contract 27, the lock would be north of its present site. The unsatisfactory foundation at the site and a slide in December led to the change in the lock s location and its removal from Contract 27.
The construction of Lock C7 was then awarded as Contract 54 to Scott Brothers of Rome, New York, on December 13, The contractor s concrete plant was in place by April after considerable difficulty in finding a suitable location. The Annual Report notes representatives of the Public Works Department believed the canal banks of the present Champlain canal, opposite the lock, were weak and unsafe for carrying the load of a concrete plant and storage bins, so the department chose a site opposite the north end of the contract limits on the bank of the old Champlain Canal. The contractor cleared the trees from the north end of the contract and then began excavating the north end of the upper approach wall.
Lackawanna steel sheet-piling was driven to enclose of the wall until it had been completed. The sheet piling was then relocated to the next wall section.2 In March Hunkin-Conkey Construction Company of Cleveland took over the contract and completed the upper approach wall to the lock in October of that year. The cofferdam built around the lock collapsed, slowing their progress, but by the concrete was being poured for the lock.3 Later work at the site included wall repairs done in as part of Contract M4. The lock underwent a rehabilitation in that included refacing the chamber walls, lining the culverts, and doing electrical and miscellaneous work.
The work was completed under Contract 2 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, Noble E. Whitford, History of the Barge Canal of New York State (Albany: Lyon Company, 3 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 4 Canal Corporation Maintenance Contract records. NEW YORK STATE BARGE CANAL, LOCK C7 HAER No. (Page 3)