BlockBefore

Mill Creek 2 and 3 Hydroelectric Systems, Mill Creek 3 Upper Flowline, Mill Creek, Yucaipa

Mill Creek 2 and 3 Hydroelectric Systems, Mill Creek 3 Upper Flowline, Mill Creek, Yucaipa, San Bernardino County, CA. Surveyed as HAER CA-2272-M, with a 801-word written history.

From the record

“The MC 3 Upper Flowline is a contributing feature to the Mill Creek Hydroelectric System Historic District.”

Written record, HAER CA-2272-M survey. Machine-read text.

Surveyed by the federal HAER program as HAER CA-2272-M · the record runs 801 words · one of 145 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Location

57 words

Source document Quoted word for word from HAER CA-2272-M. Not written, edited or summarised by this site.

The Mill Creek 3 Upper Flowline (MC 3 Flowline) runs from the MC 3 Intake west to the MC 3 Penstock, within Mill Creek Canyon in San Bernardino County, California. The MC 3 Flowline runs west on USGS topographic map Forest Falls, Sections 13, 14, 15, 16, and 17; T. and Yucaipa (Section 17; T. IS., R.

Significance

249 words

Source document Quoted word for word from HAER CA-2272-M. Not written, edited or summarised by this site.

The MC 3 Upper Flowline is a contributing feature to the Mill Creek Hydroelectric System Historic District. MC 3 is one of the earliest examples of a high-head hydroelectric system within the United States and one of the first commercial three-phase alternating current stations in California. Three-phase alternating later became the industry standard. Description: The MC 3 Upper Flowline is nearly six miles long. It consists of concrete pipes, tunnels and inverted siphons. There are about linear feet of concrete pipe, with about a 31-inch diameter on the inside. They line the 19 tunnels associated with MC 3. The outer walls of the pipes are about three inches thick, and made with Portland cement cast at the site.

They are buried about three feet below the surface and are laid throughout the MC 3 tunnels, except where the siphons are located. Concrete manholes structures with metal lids are situated along the flow line and are used to do repairs and inspections. History: The MC 3 Flowline was constructed as part of the Mill Creek 3 Hydroelectric System. The MC 3 system was constructed between and by the Redlands Electric Light and Power Company, later absorbed by Edison Electric Company of Los Angeles in The MC 3 system is still in operation today and is owned and operated by Southern California Edison. Please see the Historic Context section in the general Historic American Engineering Record for the Mill Creek 2 and 3 Hydroelectric Systems (HAER No. CA-2272) for additional information.

Sources

171 words

Source document Quoted word for word from HAER CA-2272-M. Not written, edited or summarised by this site.

Fowler, Frederick Hall. Hydroelectric Power Systems of California and Their Extensions into Oregon and Nevada, Water-Supply Paper Washington, Government Printing Office, White, David R. M. "Cultural Resource Management Plan for the Southern California Edison Company Mill Creek Hydroelectric Project (FERC Project No. San Bernardino County, California," June Low, George P. "The Generating, Transmission and Distribution Systems of The Edison Electric Company of Los Angeles, Cal.," The Journal of Electricity, Power and Gas. vol. XIII, no. 1. January, "Means Much to Redlands: Big Light and Power Deal Closed," Los Angeles Times. May 25, MILL CREEK 2 AND 3 HYDROELECTRIC SYSTEMS, MILL CREEK 3 UPPER FLOWLINE HAER No. CA-2272-M (Page 2) "Redlands Electric Light & Power Co., Edition Electric Co.

of Los Angeles, Mill Creek Powerhouses," National Register of Historic Places Inventory Nomination Form, April 30, item number 7, 10. Secord, Paul R. "National Register Nomination: Southern California Edison Company, Mill Creek Hydroelectric System," National Park Service, The building has been declared a contributing element to the Mill Creek Hydroelectric Project Historic District.

Written history

233 words

Source document Quoted word for word from HAER CA-2272-M. Not written, edited or summarised by this site.

MC 2 has not operated since when it was damaged during floods. It was not, however, decommissioned. The Southern California Edison Company, in conjunction with the San Bernardino National Forest, the agency that owns the property, proposes to formally decommission the facility. This process will include filling the sandbox and forebay with slurry, and removing the metal features. Although MC 3 is still in operation, it is also being recorded as part of this project because of the system's close association with MC 2. MILL CREEK 2 AND 3 HYDROELECTRIC SYSTEMS, MILL CREEK 3 UPPER FLOWLINE HAER No. CA-2272-M (Page 3) Location of Mill Creek Hydro Project Elements. (Map Courtesy of Southern California Edison) MILL CREEK 2 AND 3 HYDROELECTRIC SYSTEMS, MILL CREEK 3 UPPER FLOWLINE HAER No.

CA-2272-M (Page 4) Overview map of Mill Creeks 2 and 3 from circa using data from surveys conducted by Finkle (Courtesy of Southern California Edison) MILL CREEK 2 AND 3 HYDROELECTRIC SYSTEMS, MILL CREEK 3 UPPER FLOWLINE HAER No. CA-2272-M (Page 5) ' ," / i t , * . I bB V u Mill Creek 2 mid 3 Hydro Project Elements (Map Courtesy of Southern California Edison) MILL CREEK 2 AND 3 HYDROELECTRIC SYSTEMS, MILL CREEK 3 UPPER FLOWLINE HAER No. CA-2272-M (Page 6) n I- j_ Mill Creek 3 Upper Flowline Site Plan. Map indicates the location of the MC 3 Upper Flowline.

In context

Yucaipa, California The place record: every map, photograph and survey of this town.
San Bernardino County, California 963 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Yucaipa

24 of 25 records shown

The federal surveyors worked through Yucaipa building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-22728,010 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-Q4,238 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-Y2,456 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-I1,878 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-J1,064 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-C1,039 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-O989 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-K974 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-P958 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-D917 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-H917 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-L893 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-W892 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-B878 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-N876 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-T862 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-X862 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-G848 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-E843 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-A841 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-S837 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-U827 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-R819 words
Mill Creek 2 and 3 Hydroelectric SystemsHAER CA-2272-F812 words

Provenance

  • Written history. Quoted verbatim from HAER CA-2272-M. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.