Lock E10, located on the Erie Canal, is a component of the nationally significant New York State Barge Canal. It is also significant for the Mohawk River movable dam at this site. Description: Lock E10 is more than 6 miles west of Lock E9 on the south bank of the Mohawk River. The site is accessed by an asphalt driveway extending north from Route At the time of the site visit, the driveway ended at a construction area, where trailers and vehicles occupied a temporary, gravel parking area. Downstream of the lock was another unfinished parking area constructed of stone and dirt. The lock site consists of the lock and associated structures, powerhouse, lockhouse, movable dam (Dam 6), and spillway. The lock has a 15' lift with normal pool elevations of below and above.
The concrete chamber walls have been clad in steel plates and cast-iron quarter-round coping. There are double-leaf, steel miter lock gates at each end of the chamber, operated by spars and gear trains powered by electric motors. The flow of water through the culverts in the chamber walls is controlled by valves also operated by the electric motors. As is typical of Locks E8 through E15 where flooding was an issue, there are two-story concrete cabins at all four corners of the lock chamber to keep the electric motors and switchgear above normal flood waters. The cabins have flat roofs and steel-riveted hinged doors. Each one has steel multi-light windows with an awning window in the middle section.
The cabins on the south side of the lock chamber have sloped metal awnings over the lock control machinery, and the control panel has been inset into the building. Steel guard rails line the north (river) side of the chamber, and there are also concrete stairs for access. The lock and cabins are in good condition. The gasoline-electric powerhouse is located on a small hill about south of the lower gates, close to Route 5S. Powerhouses at locks E8 through E15 were generally placed at a higher elevation to protect the generating machinery from flood waters. In addition, at the locks next to movable dams, the powerhouses were equipped with gasoline-powered generators rather than hydroelectric plants to accommodate the lack of head in the off season.
The single-story concrete structure has an asphalt-shingled, hip roof. A small enclosed frame entrance with a gable roof leads to the basement. The entrance has metal infill around a metal door with a four- 1 Description of current conditions is based on a site visit made by the HAER recording team in NEW YORK STATE BARGE CANAL, LOCK E10 HAER No. (Page 2) light transom window. The rectangular eyebrow windows have been filled in with vertical board paneling. The remainder of the fenestration is steel, multi-light windows with some having a pivot sash. The powerhouse is in good condition.2 The original lockhouse was destroyed in a flood. At the time of the site visit, a new raised concrete foundation had been poured.
A metal trailer located by the upstream lock gate was serving as the temporary lockhouse until construction of the new one could be completed. The southeast approach wall is concrete that is severely spalling in those areas that have not been clad in mild steel plating. Concrete-filled cast-iron bollards are located along the wall. The southwest approach wall is constructed in a similar manner as the southeast wall. The section of this wall outside the lock gate exhibits severe spalling and cracks. The northeast approach wall, which appears to have been recently repaired, is concrete with mild steel plating and cast-iron quarter-round coping.
Finally, the northwest concrete approach wall is spalling, but it appears to have been recently repaired in some areas, although the section closest to the lock gate is severely spalled. Cast-iron quarter-round coping has been installed on the wall. The approach walls are generally in fair condition. The Mohawk River movable dam (referred to as Dam 6) extends across the river. The dam has a three riveted-steel Pratt trusses supported by concrete piers. The dam measures between abutments; the center span is wide and is flanked by spans. The movable dams have steel gate panels and fabricated steel uprights operated by chains hauled by mules (DC electric winches). At Dam 6, the center span has six panels while the end ones have five.
A newly-built concrete spillway is located downstream of the lock and is in good condition. History: The construction of the lock and dam was part of Contract 8, awarded in to Pittsburg-Eastern Company and under the supervision of various state engineers. Excavation of the site began in October with the excavated material placed in spoil banks. The following spring, the contractor began pile driving the upper guide wall, as well as the land and river walls of the lock and the apron between the lock and south pier. Concrete work began at the end of June, with the upper guide wall and land wall of the lock completed first.
The contractor mixed the concrete at a central plant and then transported it in buckets on flat cars to the site since they were also building locks E8 and E9.3 Work at the site ceased in October because of high water and a break in the cofferdam, but work resumed in April A substantial cofferdam was built to enclose the lock and approaches. That year, the forms and concrete for the lock had been completed except for a pier on the river wall and the lock gates.
The Annual Report noted, the water bearing gravel in the foundation for the lock made it necessary to put in a drain the entire length of the foundation 2 The powerhouse was destroyed during the flooding caused by Tropical Storm Irene in 3 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, NEW YORK STATE BARGE CANAL, LOCK E10 HAER No. (Page 3) to take care of the boiling springs. By the following year, work had progressed to the lower end of the lock and the movable dam.
The north abutment and shore protection were subcontracted and completed early in By the concrete work had been completed at Lock E10 and Dam 6. Steel work continued, and the lock gates were erected during the winter of In the erection of the dam superstructure continued and had been nearly completed aside from the installation of some gates that the contractor had not yet received. The Annual Report stated this structure was the first of the Barge canal movable dams to be erected. 5 From work continued at the site, including repairs of defective concrete in the lock walls.
The replacement of the defective concrete was continued under Contract 8A in The power plant was completed under Contract 92, which called for the installation of three gasoline-electric stations at locks E8, E9, and E10, and a hydro-electric power station at Lock E7. The stations provided the power to operate the locks and movable dams. The Annual Report noted that the machinery and electrical equipment to operate and light locks E7, E8, E9, and E10 as well as the movable dams was completed that year.7 Various repairs and alterations were made to the lock and dam after their initial construction. The Annual Report indicates that the lower approach wall was extended that year by the Department of Public Works, who filled abandoned concrete boats with gravel and sunk them.
In the Department of Public Works installed an auxiliary concrete spillway on the lock side of the river and another at the end of the dam on the opposite side of the river. The slopes next to the spillways were also paved over with concrete. The project was in response to flood damage incurred in September An office and shop building were built at the site under Contract M83A by Crane-Nevins Electric Supply Company of Amsterdam, New York.
Additional repairs to damage caused by the flooding were made in Other work included lining the chamber with wrought iron plates, a project that involved chipping off the surface of the chamber wall for a depth of about six inches prior to placing the plates.8 4 Quote from Annual Report, 85; Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 60. 5 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 63. 6 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol.
1 (Albany: Lyon Company, 50; Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 83. 7 Annual Report of the State Engineer and Surveyor of the State of New York for the Fiscal Year ended in September 30, Vol. 1 (Albany: Lyon Company, 8 State of New York, Department of Public Works, Annual Report of the Superintendent of Public Works for the Year Lyon Company, Printers, 19; State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (Albany: Lyon Company, Printers, State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (New York: Publishers Printing Co., 23, quote from 21. NEW YORK STATE BARGE CANAL, LOCK E10 HAER No.
(Page 4) The sills and gates of the lock were rehabilitated in under Contract US90. This may have been part of an initiative by the Department of Public Works in to lower approximately thirty-two lock sills in order to provide a minimum 13' depth, which required alterations to the lock gates to make them fit.
The upper guide wall was extended under Contract and the lower approach wall was reconstructed under Contract in Additional work on the guide walls took place in when a steel sheet pile cut-off was installed, and the walls and upper guide walls were stabilized and repaired under Contract A sheet pile cutoff wall was also installed at the dam in part of Contract In new skin plates for the gates were installed (Contract Extensive repairs at Dam 6 were undertaken in the and In the eight top gates were rebuilt at the movable dam. The top and bottom chains were repaired or replaced, and the north span was repainted. Contract called for the rehabilitation of the dam. New gates were installed on the dam in Contract encompassed new uprights, decking, and riverwall repairs at the dam.
The protective apron was rehabilitated under Contract which was awarded to Lee Turzillo Contracting Company of Breckersville, Ohio, in Originally, fixed dams were planned for construction on the Mohawk River. This was problematic as there was a great deal of development along the river and if flooding occurred due to the fixed dams, the state would be responsible for the damage. Movable dams, on the other hand, would allow ice to flow unimpeded down the river and would also achieve cost savings due to the reduced need for dredging and silt removal. David A. Watt traveled to Europe to study the various dam types and decided upon the bridge type with Boule gates, which he had observed in Mirowicz on the Moldau River (in what is now Czechoslovakia).
In his history of the Barge Canal, Noble Whitford devotes a paragraph to describing these structures. These dams, as they now appear in the Mohawk, seem to be bridges with abutments and piers. From the downstream side of the lower chord hang steel frames with heavy upright pieces 15 feet apart, upon which slide an upper and a lower tier of large rectangular steel plates, called gates. When serving as a dam the bottoms of the lower gates rest on a concrete sill in the river bed, the tops of the upper gates forming the crest of the dam. When m ore water is to be passed one or more of the upper gates are partly or wholly raised.
When all the water is to be passed, in extreme flood or during the winter, all the gates are raised and both gates and frames, which have a pin joint connection with the chord, are swung to a horizontal position under the bridge floor.11 9 State of New York, Department of Public Works, Annual Report of the Superintendent for the Year (Albany: 93; Maintenance Contracts. 10 Annual Report, State of New York, Department of Public Works, Annual Report, (Albany: 79; Maintenance Contracts, March 1, Contracts at Dams, June 23, 11 Noble Whitford, History of the Barge Canal of New York State (Albany: Lyon Company, Printers, quote from Michelle McFee, A Long Haul: The Story of the New York Barge Canal (Fleischmanns, New York: Purple Mountain Press, NEW YORK STATE BARGE CANAL, LOCK E10 HAER No.
(Page 5) The movable dams on the Mohawk River are now one of the character-defining features of the New York State Barge Canal.