Bureau of Mines Boulder City Experimental Station, Administration Offices & Laboratory Building, Date Street north of U.S. Highway 93, Boulder City

Bureau of Mines Boulder City Experimental Station, Administration Offices & Laboratory Building, Date Street north of U.S. Highway 93, Boulder City, Clark County, NV. Surveyed as HABS NEV,2-BOUC,1A-, with a 1,260-word written history.

From the record

“Building as part of the Date Street Complex, was part of the Bureau of Mines Electrometallurgical Research Facility located in Boulder City.”

Written record, HABS NEV,2-BOUC,1A- survey. Machine-read text.

Surveyed by the federal HABS program as HABS NEV,2-BOUC,1A- · the record runs 1260 words · one of 66 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Location

62 words

Source document Quoted word for word from HABS NEV,2-BOUC,1A-. Not written, edited or summarised by this site.

Date Street Complex, bordered by U.S. Highway 93 Truck Route, and Elm and Date streets Boulder City, Clark County, Nevada Building 100 is located in the southeast corner of the complex near the corners of Date and Elm streets. Building 200 is located directly to the north. Boulder City, Nev., Topographic Quadrangle, U.S.G.S., Photorevised Universal Transverse Mercator Coordinates: (approximate center of building)

Significance

1100 words

Source document Quoted word for word from HABS NEV,2-BOUC,1A-. Not written, edited or summarised by this site.

Building as part of the Date Street Complex, was part of the Bureau of Mines Electrometallurgical Research Facility located in Boulder City. As such, it is within the designated Boulder City Historic District. One of seven buildings considered eligible, this is one of two that are currently in use and will not be demolished. The building was included as a contributing element in the Boulder City Historic District Nomination This building was constructed in with an addition built in and alterations made through time that have not affected its architectural integrity (Pfaff The footprint and rootline are unchanged, as is the wall cladding; however, the roof cladding was changed.

Significance for this building includes being a part of the Bureau of Mines Electrometallurgical Laboratory during the period of to and, therefore, it is a contributing element to the District. The significance of the Boulder City Historic District is tied to the Boulder Canyon Project (Hoover Dam) and to the history of American City Planning. This was the first community constructed following the federal New Towns model, as well as the "first fully-developed experience in new town planning as promoted by the Community Planning Movement, a movement which is recognized as the force which most influenced contemporary community planning practices" (Woodward et al. Description: Building 100 was built in as an "L" -shaped administrative and laboratory building.

An extension to the northeast/southwest section of the "L" was constructed in changing the shape to a "T" (NV-35-A-4). It measures 180 feet northeast/southwest on the "T" (northeast and southwest wings) and 77 to 81 feet southeast to northwest on the "leg" (southeast wing). The width of the "T" is 38 feet and the "leg" is 36 feet. The building is a one-story, concrete block with a low pitch (16 ), cross-gabled roof Unlike the other buildings, the roof is clad with asphalt BUREAU OF MINES BOULDER CITY EXPERIMENTAL STATION, ADMINISTRATIVE OFFICES AND LABORATORY BUILDING (Building No. HABS No. NV-35-A (Page 2) shingles that are red, although it originally had clay tile (>Vorswick Pfaff The eaves are open with enclosed rafters and an approximate 10 inch overhang except on the gable ends.

Each of the three gable ends has vertical, round cut, wood planks. A two-block thick concrete frieze band encircles the building. All of the windows are recessed metal-framed, divided-light sash with cement sill, unless otherwise noted. According to Pfaff several of the windows in the addition are replacement aluminum sash made to the same configuration as the original steel sash windows. All of the original wood doors have been replaced with metal-framed metal doors. To describe this building, it will be divided into the southeast wing (contains the primary entrance), the northeast wing, and the southwest wing (constructed in The primary (front) elevation faces northeast. The main entry has a new aluminum storefront commercial door.

This is a power assisted opener door for handicapped access. A full-light aluminum storefront window flanks the door to the northwest. A second, aluminum storefront door is near the southeast end of the wing. There are seven windows on this elevation of the southwest wing. All are casement, 30-part divided-light A shed roof extension provides a covered walkway/patio to the southeast of the entrance. Evenly spaced square wood posts support the roof extension. The walkway is flagstone pavers with a poured concrete curb providing a base for the posts and border for the walkway. On the northeast wing, the east elevation, there are two doors, two air vents, and one covered window. The two doors are flush metal (no panels).

The walkway and roof extension continues along most of the northeast wing to just before the northeasternmost window. There are seven windows on this wing, of three types. From the entry, the first four are casement, 30-part divided-light. The next window is a fixed 4-light, and the last two are fixed 6-light. The southeast elevation on the southeast wing has two casement windows (30-part divided-light) with a full- light door in the center. Above the door is a louvered vent. On the southwest wing there are seven double casement (15-part divided-light) windows. A double louvered wood vent is in the center of the gable on the southwest elevation of the southwest wing. Below it is a half-glass (single-light) over panel door with a single-light transom. The door is handicap accessible.

It is flanked on both sides by windows, which are on the same level as the rest of the windows on the building. The windows are casement 15-part divided-light. A pipe or electrical conduit is on the southeast side of the door and goes to above the roof A second, smaller louvered vent is southeast of the pipe. The entry is accessed by a set of concrete steps entered from the southeast. The steps have pipe railing with pipe rails along the higher leveled parking area to the southwest. On the southwest corner of the elevation at the bottom of the steps is a second entry into the basement. The door is flush metal.

On the northwest elevation is an entry where the southwest wing joins the northeast BUREAU OF MINES BOULDER CITY EXPERIMENTAL STATION, ADMINISTRATIVE OFFICES AND LABORATORY BUILDING (Building No. HABS No. NV-35-A (Page 3) wing. This has been altered to include a ramp, as well as stairs and a power assisted aluminum storefront door with sensor or touch pad. The southwest wing is offset to the southeast from the northeast wing, so the entry stoop fits into the corner where the two wings join. There is no extension of the roof over this entry. There are six symmetrically placed windows on the southwest wing, all of which are 15-part divided-light casement. Near the southwest end of the wing, there is a rectangular bay extending above the northwest slope of the roof.

Its purpose is unknown, although it may be associated with the space apparently provided to Senator Scrogham, who was said to have had office space and a place to sleep at the southwest end of this wing (Carl Dewey, personal communication 2 December On the northeast wing are seven windows of varied size and type. The first, located on the southwest corner of the northeast wing just at the corner with the southwest wing, is a fixed 6-light. The next four are all 15-par divided-light casement. A half- glass door is offset to the northeast. Then there are two fixed 6-light windows, followed by a circuit breaker, and one more fixed 6-light window. BUREAU OF MINES BOULDER CITY EXPERIMENTAL STATION ADMINISTRATIVE OFICES AND LABORA TORY BUILDING (Building No. BABS No. NV-35-A (Page 4)

In context

Boulder City, Nevada The place record: every map, photograph and survey of this town.
Clark County, Nevada 264 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Boulder City

24 of 42 records shown

The federal surveyors worked through Boulder City building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1-17,316 words
Six Companies RailroadHAER NV-4414,857 words
Hoover Dam Aggregate Classification PlantHAER NV-4312,345 words
Bureau of Mines Metallurgical Research LaboratoryHABS NEV,2-BOUC,1B-7,892 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1D-6,399 words
Lake Mead LodgeHABS NV-605,936 words
Lakeshore RoadHAER NEV,2-BOUC.V,1-5,533 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1F-5,308 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1C-5,218 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1E-5,113 words
Arizona Gravel Pit RoadHAER NV-424,819 words
Hoover DamHAER NV-27-Q3,979 words
Hoover DamHAER NV-27-M3,425 words
Hoover DamHAER NV-27-O2,727 words
Hoover DamHAER NV-27-A2,334 words
Hoover DamHAER NV-27-D2,241 words
Hoover DamHAER NV-27-C2,123 words
Hoover DamHAER NV-27-L1,984 words
Hoover DamHAER NV-27-E1,861 words
Hoover DamHAER NV-27-F1,749 words
Hoover DamHAER NV-27-P1,685 words
Hoover DamHAER NV-27-N1,668 words
Hoover DamHAER NV-27-Y1,552 words
Hoover DamHAER NV-27-B1,539 words

Provenance

  • Written history. Quoted verbatim from HABS NEV,2-BOUC,1A-. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.