BlockBefore

Hoover Dam, Los Angeles Bureau of Power & Light Lines 1-3, U.S. Highway 93, Boulder City

Hoover Dam, Los Angeles Bureau of Power & Light Lines 1-3, U.S. Highway 93, Boulder City, Clark County, NV. Surveyed as HAER NV-27-M, with a 3,425-word written history.

From the record

“The Los Angeles Bureau of Power and Light transmission lines included pioneering technology in high-voltage transmission.”

Written record, HAER NV-27-M survey. Machine-read text.

Surveyed by the federal HAER program as HAER NV-27-M · the record runs 3425 words · one of 66 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Location

293 words

Source document Quoted word for word from HAER NV-27-M. Not written, edited or summarised by this site.

U.S. Highway 93 Vicinity of Boulder City Clark County Nevada USGS Hoover Dam, Nevada-Arizona 7.5 Minute Provisional USGS Boulder Beach, Nevada 7.5 Minute USGS Boulder City, Nevada 7.5 Minute UTM Coordinates: Los Angeles BPL Line 1: 1 l (start) 1 (end segment) Los Angeles BPL Line 2: 1 (start) 1 (end segment) Los Angeles BPL Line 3: 1 (start) 1 (end segment) Date of Construction: Engineer: Los Angeles Bureau of Power and Light Builder: Los Angeles Bureau of Power and Light U.S.

Highway 93 Vicinity of Boulder City Clark County Nevada USGS Hoover Dam, Nevada-Arizona 7.5 Minute Provisional USGS Boulder Beach, Nevada 7.5 Minute USGS Boulder City, Nevada 7.5 Minute UTM Coordinates: Los Angeles BPL Line 1: l (start) (end documented segment) Los Angeles BPL Line 2: 1 l (start) 1 (end documented segment) Los Angeles BPL Line 3: 1 (start) 1 (end documented segment) Statement of U.S.

Highway 93 Vicinity of Boulder City Clark County Nevada USGS Hoover Dam, Nevada-Arizona 7.5 Minute Provisional USGS Boulder Beach, Nevada 7.5 Minute USGS Boulder City, Nevada 7.5 Minute UTM Coordinates (NAD Los Angeles BPL Line 1: 1 l (start) 1 l (end segment) Los Angeles BPL Line 2: {start) 1 (end segment) Los Angeles BPL Line 3: (start) (end segment) Date of Construction: Engineer: Los Angeles Bureau of Power and Light Builder: Los Angeles Bureau of Power and Light U.S.

Highway 93 Vicinity of Boulder City Clark County Nevada USGS Hoover Dam, Nevada-Arizona 7.5 Minute Provisional USGS Boulder Beach, Nevada 7.5 Minute USGS Boulder City, Nevada 7.5 Minute UTM Coordinates (NAD Los Angeles BPL Line 1: l l (start) l (end segment) Los Angeles BPL Line 2: l l (start) (end segment) Los Angeles BPL Line 3: l (start) 1 l (end segment) Statement of

Significance

1633 words

Source document Quoted word for word from HAER NV-27-M. Not written, edited or summarised by this site.

The Los Angeles Bureau of Power and Light transmission lines included pioneering technology in high-voltage transmission. The lines were crucial elements of the Hoover Dam electrical complex, particularly in the role played by Hoover Dam power in World War II industries and post-war development in southern California. At the time of construction, these lines transmitted electricity at a higher voltage than any other long- distance transmission line in the world. Report Prepared by: Associated Cultural Resource Experts (ACRE) Sangre de Cristo Road, STE 202 Littleton, CO Date: April HISTORIC AMERICAN ENGINEERNG RECORD HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO.

(Page 2) The Los Angeles Bureau of Power and Light transmission lines included pioneering technology in high-voltage transmission. The lines were crucial elements of the Hoover Dam electrical complex, particularly in the role played by Hoover Dam power in World War II industries and post-war development in southern California. At the time of construction, these lines transmitted electricity at a higher voltage than any other long-distance transmission line in the world. Description: Three identical, high-voltage transmission lines were built by the Los Angeles Bureau of Power and Light (LABPL) from a switchyard at Hoover Dam to Los Angeles, California. The single- circuit steel towers of these lines are narrow-waist type with the base rotated 45 degrees to the direction of the line.

Tower bases are 32' square, and the towers are 2" inches from base to the overhead ground wires at the towers' highest points. From 65'-long cross-members, three conductors are suspended under insulator strings composed of 24 1O" porcelain insulators. The LABPL lines included single-circuit towers, with an average span of between towers; the western end of the line was built with 257 double-circuit towers. The documented segments of these transmission lines originate at the LABPL Switchyard, on the Nevada rim of Black Canyon above Hoover Dam, in Section 29, T.22S-R.65E. The documented segments of 1 and 3 extend southwestward to the point where the transmission lines cross the south section line of Section 25, T.22S-R.64E.

Line 2 was documented to a point southwest of Boulder City Substation. All towers in these segments are standard suspension, single-circuit design. History: The original Hoover Dam power contracts required the City of Los Angeles to transmit power for itself, the Metropolitan Water District, municipalities, the Southern Sierras Power Company, and other utilities, but those other entities could opt for transmission by means other than the City's system. The Los Angeles Bureau of Power and Light (LABPL, also referred to as the L.A.

Department of Water and Power) would obtain power from the first four generating units to come online at Hoover Dam through After extensive research, LABPL determined that transmitting power at volts over two circuits would be economical; after line losses, the transmission lines would deliver volts at Los Angeles. Right-of-way and other considerations determined that the company would build two single circuits that would extend about 225 miles southwestward from a switchyard at Hoover Dam and then a double-circuit line for the final 41 miles. Long-distance transmission at this high voltage had not been attempted at that time, and the LABPL lines would necessarily include several important design innovations. HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO.

(Page 3) Large-diameter conductor was desirable to limit corona losses in the transmission lines. Traditional, solid-copper conductors at this diameter would be unacceptably expensive, both in the cost of the conductor and in the increased bulk and cost of the supporting towers. A tubul<1r copper conductor in diameter was adopted that successfully addressed these issues; this type of conductor had been developed in Germany and had not been previously used in the United States. Lightning protection for the lines also required innovation: two overhead ground wires and copper rods buried under the circuits and attached to each tower.

Tower design was critical: the structures had to be of sufficient height and strength to maintain economical and safe conductor spans between towers, but the structures had to be economical to build and maintain. The single-circuit steel towers were narrow-waist type with the base rotated 45 degrees to the direction of the line. Tower bases were 32' square, and the towers were 2" from base to the overhead ground wires at the towers' highest points. From 65'-long cross- members, three conductors were suspended under insulator strings composed of 24 1O" porcelain insulators. The insulation for the conductors was not determined by the safety margins for current transmission, but by a need to protect the conductors from frequent lightning strikes.

LABPL began construction of its transmission system in June with the assistance of a million loan from the Reconstruction Finance Corporation. Three nearly identical transmission lines were planned (called Boulder 1, 2, and 3). Boulder 1 and 2 were completed as a pair during the summer of The two lines were built parallel to each other from Hoover Dam to Upland California, and the lines in this distance were connected with an underground counterpoise system consisting of two copper wires for each tower, placed apart where they cross-connected. These two wires crossed diagonally to intersect each tower, resulting in a corridor wide.

Commercial power production at Hoover Dam power plant began on October 26, when generating unit N-2 was brought on-line to energize the LABPL Boulder 1 and Boulder 2 lines. The load over these lines served Los Angeles, Pasadena, Glendale, and Burbank, California, and the load was a world record for long-distance transmission at that time. Generating units and N-4 were in regular operation by early feeding electricity through the LA Switchyard to the Boulder 1 and Boulder 2 transmission lines. LABPL Boulder 3 transmission line was constructed in and with towers, conduit, and other equipment virtually identical to Boulder 1 and 2 lines, but the Boulder 3 line was not built with a sunken counterpoise system.

Boulder 3 was built parallel to Boulder 1 and 2 in the vicinity of Hoover Dam, but the new line's route diverged considerably from the other two lines in some areas of western Nevada and California. Boulder 3 was connected to an extension built in the LA Switchyard to handle both the outgoing line and incoming transformer circuit No. 3 from the A-1 generating unit. The transmission line and switchyard were completed in the early months of and the transmission line was placed in service on April 21, The three Los Angeles transmission lines proved to be extremely durable and reliable, and these lines played a crucial role in delivering power to the Los Angeles area during and after World War II.

Beginning in portions of these lines in western Nevada and California were converted to transmission and interconnected as part of the western grid system. All three of these lines continued to transmit power from Hoover Dam at until the mid-1990s, when the lines were converted to more conventional transmission. Minor changes have occurred to the towers of these lines, including installation of bird guards, new conductors, and replacement of some insulators. The Los Angeles Bureau of Power and Light transmission lines included pioneering technology in high-voltage transmission. The lines were crucial elements of the Hoover Dam electrical complex, particularly in the role played by Hoover Dam power in World War II industries and post-war development in southern California.

At the time of construction, these lines transmitted electricity at a higher voltage than any other long- distance transmission line in the world. Report Prepared by: Associated Cultural Resource Experts (ACRE) Sangre de Cristo Road, STE 202 Littleton, CO Date: January HISTORIC AMERICAN ENGINEERNG RECORD ADDENDUM TO HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO. Page 9 The Los Angeles Bureau of Power and Light transmission lines included pioneering technology in high-voltage transmission. The lines were crucial elements of the Hoover Dam electrical complex, particularly in the role played by Hoover Dam power in World War II industries and post-war development in southern California.

At the time of construction, these lines transmitted electricity at a higher voltage than any other long-distance transmission line in the world. Three identical, high-voltage transmission lines were built by the Los Angeles Bureau of Power and Light (LABPL) from a switchyard at Hoover Dam to Los Angeles, California. The single- circuit steel towers of these lines are narrow-waist type with the base rotated 45 degrees to the direction of the line. Tower bases are 32' square, and the towers are 2" inches from base to the overhead ground wires at the towers' highest points. From 65'-long cross-members, three conductors are suspended under insulator strings composed of 24 1O" porcelain insulators.

The LABPL lines included single-circuit towers, with an average span of between towers; the western end of the lines in California were built with 257 double-circuit towers. The documented segments of these transmission lines originate at the LABPL Switchyard, on the Nevada rim of Black Canyon above Hoover Dam, in Section 29, T.22S-R.65E. LAABPL Lines 1 and 3 were previously documented from the LABPL Switchyard southwestward to a point where the transmission lines cross the south section line of Section 25, T.22S-R.64E. LABPL Line 2 was previously documented from the LABPL Switchyard southwestward to a point in the SE\/.i of Section 2, T. 23S-R.64E.

This Amendment extends documentation of all three transmission lines to the southwestward, to the locations where the LABPL lines are intercepted in the SW\/.i of Section 29, T.23S-R.64E by intertie transmission lines to Mead Substation. All towers in the documented segments are standard suspension, single-circuit design. All towers throughout the documented segments are identical in design aild materials, except for standard leg extensions on some towers to accommodate topographic features. History: The history of the LABPL Lines 1, 2, and 3 was submitted previously in HAER No.

Sources

641 words

Source document Quoted word for word from HAER NV-27-M. Not written, edited or summarised by this site.

This documentation of features of Hoover Dam and associated structures was accomplished by Associated Cultural Resource Experts (ACRE). ACRE completed documentation of21 features in HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO.

(Page 4) October Documentation on four linear features was extended and an additional 3 features were newly documented in February Both phases of documentation were conducted as part of the historical/engineering recordation of Hoover Dam-prepared for the Department of Energy, Western Area Power Administration; Bureau of Reclamation; and Federal Highway Administration-that includes a narrative for the Addendum to Hoover Dam and individual documentation of 25 features located at the Hoover Dam facility, photo documentation, and documentation of existing historic photographs and site plans. The recordation conforms to the standards of the Historic American Engineering Record, U.S. Department of the Interior.

Other reports in the HAER collection completed for these projects are a narrative for the Addendum to Hoover Dam and 25 short forms for individual structures: Hoover Dam, Los Angeles Switchyard (NV-27-A); Hoover Dam, Southern Sierras/CEP/Southern California Edison Switchyard Hoover Dam, Metropolitan Water District Switchyard Hoover Dam, State of Nevada Switchyard Hoover Dam, Southern California Edison Switchyard (NV-27-E); Hoover Dam, Arizona-Nevada Switchyard Hoover Dam, Static Towers and Lines Hoover Dam, Los Angeles Relay Control Building Hoover Dam, Switchyard Fire House (NV-27-I); Hoover Dam, Promontory Water Tank Hoover Dam, Control Cable Hoist House Hoover Dam, Transformer Circuits Hoover Dam, Los Angeles BPL Lines 1-3 Hoover Dam, Southern California Edison North and South Lines Hoover Dam, Hoover-Basic Magnesium North and South Lines Hoover Dam, Metropolitan Water District Line 1 Hoover Dam, United States Construction Railroad Hoover Dam, U.S.

Highway 93 Nevada Segment Hoover Dam, Lower Portal Access Road Hoover Dam, Kingman Switchyard Hoover Dam, U.S. Highway 93 Arizona Segment (NV-27-U); Hoover Dam, Explosives Magazines Hoover Dam, Nevada Downstream Waste Tailings and Hoover Dam, Nevada Spoils Tunnel and Hoover Dam, Henderson-Mead Transmission Line 2 Documentation of features of Hoover Dam and associated structures (HAER No. was accomplished by Associated Cultural Resource Experts (ACRE).

ACRE completed documentation of 21 features in October Documentation of four linear features was extended and an additional 3 features were newly documented in February Both phases of documentation were conducted as part of the historical/engineering recordation of Hoover Dam- ADDENDUM TO HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO. (Page 10) prepared for the Department of Energy, Western Area Power Administration; Bureau of Reclamation; and Federal Highway Administration-that includes a narrative for the Addendum to Hoover Dam and individual documentation of 25 features located at the Hoover Dam facility, photo documentation, and documentation of existing historic photographs and site plans.

The recordation conforms to the standards of the Historic American Engineering Record, U.S. Department of the Interior.

Other reports in the HAER collection completed for these projects are a narrative for the Addendum to Hoover Dam and 25 short forms for individual structures: Hoover Dam, Los Angeles Switchyard (NV-27-A); Hoover Dam, Southern Sierras/CEP/Southern California Edison Switchyard Hoover Dam, Metropolitan Water District Switchyard Hoover Dam, State of Nevada Switchyard Hoover Dam, Southern California Edison Switchyard (NV-27-E); Hoover Dam, Arizona-Nevada Switchyard Hoover Dam, Static Towers and Lines Hoover Dam, Los Angeles Relay Control Building Hoover Dam, Switchyard Fire House Hoover Dam, Promontory Water Tank Hoover Dam, Control Cable Hoist House Hoover Dam, Transformer Circuits Hoover Dam, Los Angeles BPL Lines 1-3 Hoover Dam, Southern California Edison North and South Lines Hoover Dam, Hoover-Basic Magnesium North and South Lines Hoover Dam, Metropolitan Water District Line 1 Hoover Dam, United States Construction Railroad Hoover Dam, U.S.

Highway 93 Nevada Segment Hoover Dam, Lower Portal Access Road Hoover Dam, Kingman Switchyard T); Hoover Dam, U.S. Highway 93 Arizona Segment (NV-27-U); Hoover Dam, Explosives Magazines Hoover Dam, Nevada Downstream Waste Tailings and Hoover Dam, Nevada Spoils Tunnel and Hoover Dam, Henderson-Mead Transmission Line 2

Written history

549 words

Source document Quoted word for word from HAER NV-27-M. Not written, edited or summarised by this site.

This documentation was prepared for three federal agencies: U.S. Department of Transportation, Federal Highway Administration (FHWA), Central Federal Lands Highway Division, Lakewood, CO; U.S. Department of Energy, Western Area Power Administration (Western), Desert Southwest Customer Support Region, Phoenix, AZ; and U.S. Department of Interior, Bureau of Reclamation (Reclamation), Lower Colorado Region, Boulder City, NV. This documentation records certain transportation and electrical features associated with Hoover Dam before planned removal or alteration of some structures. FHWA plans to construct a bridge over the Black Canyon of the Colorado River about downstream from Hoover Dam. The Hoover Dam Bypass Project would include realignment of U.S.

Highway 93 on the Nevada and Arizona sides of Black Canyon. The project would include demolition, relocation, or substantial visual impact to a segment of U.S. Highway 93 on the Nevada approach to Hoover Dam, a segment of a former alignment of U.S. Highway 93 in Arizona, electrical transformer circuits in Arizona and Nevada, two electrical switchyards, a segment of the grade of the U.S. Construction Railroad, a stone gate structure for a dam construction and operations road, and six historic transmission lines. This documentation also records certain structures not directly affected by FHWA's Hoover Dam Bypass Project. Electrical transmission facilities at Hoover Dam are administered by Western, but these facilities are within a federal reservation administered by Reclamation.

Documentation of electrical structures is intended to partially fulfill responsibilities of Western and Reclamation under Section 110 of the National Historic Preservation Act (As amended). Some electrical structures addressed by Western and Reclamation would be directly affected by FHWA's Hoover Dam Bypass Project, and all structures addressed by Western and Reclamation are functionally related and geographically near structures addressed by FHWA. HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO. (Page 5) Project Manager and historian for the recordation was Kurt P. Schweigert of Associated Cultural Resource Experts. The photographers were Deborah Dobson-Brown and Douglas M. Edwards of Associated Cultural Resource Experts.

This documentation was prepared on the basis of research conducted at Reclamation archives in Denver, CO, and Boulder City, NV; Western archives and files in Denver and Phoenix, AZ; the National Archives and Records Administration in Denver; libraries of the University of Nevada-Las Vegas; and the Western History Collection of the Denver Public Library. This documentation includes information contained in survey reports for the Hoover Dam Bypass Project Environmental Impact Statement, an evaluation of the Western switchyards at Hoover Dam, an evaluation of the Hoover Dam construction railroads, a National Register nomination for Hoover Dam, and other documents. This Addendum to HAER No. was prepared for the U.S.

Department of Energy, Western Area Power Administration (Western), Desert Southwest Customer Support Region, Phoenix, AZ. Previous documentation of HAER No. recorded electrical features associated with Hoover Dam before planned alteration of some structures to allow double- circuiting necessary to accommodate construction .of a bridge and highway realignment near Hoover Dam, This Addendum extends documentation of the three transmission lines to partially fulfill responsibilities of Western under Section 110 of the National Historic Preservation Act (as amended). Project Manager, historian, and photographer for this Addendum was Kurt P. Schweigert of Associated Cultural Resource Experts.

Research and documentation for this Addendum consisted of field inventory and large-format photography only; additional historical research was not conducted.

Written history

191 words

Source document Quoted word for word from HAER NV-27-M. Not written, edited or summarised by this site.

Kurt P. Schweigert, Associated Cultural Resource Experts, ::i:: i -~ 5 ~ ~ ~ to ~ 0 "'1 ~~ ~~ 9 Ro z r' < a N::i:;: r' ~z "ti m ~ (I) - 0\ I HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO. (Page 7) HISTORIC AMERICAN ENGINEERNG RECORD ADDENDUM TO HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO. Page 8 Kurt P. Schweigert, Associated Cultural Resource Experts, 5 ~ .i 0 [/J ~ C) tTl ~ [/J o::J ~> C 0 ~~ tTl 0 ~ 6?0 . Ro ~C> I C) t, ~ t, I tTJ a;: z ,;a z t, Pl tTl C ~ [/J a;: 0J 0 ADDENDUM TO HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO. (Page 12) ADDENDUM TO HOOVER DAM, LOS ANGELES BUREAU OF POWER & LIGHT LINES 1-3 HAER NO. (Page 13) .. /"O ,. Q,j E(_,. . . . .> ~ :i ; ~ 8 ~- . = e :J~ s .:vi~ 0 OJ) . . , , J:l ' Q .' ,J t:< , , -.,

In context

Boulder City, Nevada The place record: every map, photograph and survey of this town.
Clark County, Nevada 264 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Boulder City

24 of 42 records shown

The federal surveyors worked through Boulder City building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1-17,316 words
Six Companies RailroadHAER NV-4414,857 words
Hoover Dam Aggregate Classification PlantHAER NV-4312,345 words
Bureau of Mines Metallurgical Research LaboratoryHABS NEV,2-BOUC,1B-7,892 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1D-6,399 words
Lake Mead LodgeHABS NV-605,936 words
Lakeshore RoadHAER NEV,2-BOUC.V,1-5,533 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1F-5,308 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1C-5,218 words
Bureau of Mines Boulder City Experimental StationHABS NEV,2-BOUC,1E-5,113 words
Arizona Gravel Pit RoadHAER NV-424,819 words
Hoover DamHAER NV-27-Q3,979 words
Hoover DamHAER NV-27-O2,727 words
Hoover DamHAER NV-27-A2,334 words
Hoover DamHAER NV-27-D2,241 words
Hoover DamHAER NV-27-C2,123 words
Hoover DamHAER NV-27-L1,984 words
Hoover DamHAER NV-27-E1,861 words
Hoover DamHAER NV-27-F1,749 words
Hoover DamHAER NV-27-P1,685 words
Hoover DamHAER NV-27-N1,668 words
Hoover DamHAER NV-27-Y1,552 words
Hoover DamHAER NV-27-B1,539 words
Hoover DamHAER NV-27-W1,538 words

Provenance

  • Written history. Quoted verbatim from HAER NV-27-M. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.