In addition to the direct association of these transmission lines to the early operation of Hoover Dam, the lines were extremely important for providing energy to war industries in California during World War II. Electricity carried on these lines helped to power Douglas, Vultee, and Northrup aircraft plants, the Long Beach Naval Shipyard, military bases, and major steel and aluminum production plants. The lines were also important in the post-war agricultural and municipal development in California. Report Prepared by: Associated Cultural Resource Experts (ACRE) Sangre de Cristo Road, STE 202 Littleton, CO Date: April HISTORIC AMERICAN ENGINEERNG RECORD HOOVER DAM, SOUTHERN CALIFORNIA EDISON NORTH AND SOUTH LINES HAER NO.
(Page 2) In addition to the direct association of these transmission lines to the early operation of Hoover Dam, the lines were extremely important for providing energy to war industries in California during World War II. Electricity carried on these lines helped to power Douglas, Vultee, and Northrup aircraft plants, the Long Beach Naval Shipyard, military bases, and major steel and aluminum production plants. The lines were also important in the post-war agricultural and municipal development in California. Description: The Southern California Edison North and South Transmission Lines are transmission lines that extend from the Southern California Edison Switchyard at Hoover Dam to Chino, California.
The documented segments of these transmission lines originate at the Southern California Edison (SCE) Switchyard near the Nevada rim of Black Canyon, in Section 29, T22S-R65E. The documented segments extend westward to the west section line of Section 29, T22S-R65E. Each segment includes four single-circuit, suspension type steel towers. The lines have identical lattice-steel, wedge A-frame, and metal-waisted towers. Towers are 27' square at base and up to high. Towers consist of a square leg segment up to 25' high, a square vertical panel 25' high, a standard battered segment either 50' or 60' high, a bridge or cross member 5' high and 50' long, and ground wire extensions 20' high.
Towers vary in height and intervening distance to accommodate topography and cultural features crossed by the transmission line. History: Southern California Edison (SCE) began constructing the SCE North or Hoover-Chino No. transmission line from Chino, California to Hoover Dam in The line was completed in May to the SCE switchyard on the south side of Black Canyon Highway (current U.S. Highway Hoover Dam power plant generating units A-6 and A-7 were nearing completion at that time, and SCE began delivering power over the line on June 19, In response to anticipated growth in demand, SCE began construction of a second line before the first line was energized. The second line (SCE South Line or Hoover-Chino No. 2) was completed in November but transformer circuit No.
IO and the switchyard addition to serve the new line were not completed until near the end of The Hoover-Chino No. 2 line may have been energized from the same switchyard system as the No. 1 line as early as November and the No. 2 line was energized from the expanded switchyard facilities by early These two transmission lines were constructed with metal-wedge, A-frame and metal-waisted towers very similar to towers the Southern California Edison (SCE) Company had previously used in innovative, high-voltage transmission lines in California (this basic design was also used for towers on the Metropolitan Water District transmission lines from Hoover Dam). The two SCE HOOVER DAM, SOUTHERN CALIFORNIA EDISON NORTH AND SOUTH LINES HAER NO.
(Page 3) transmission lines take different courses from the SCE Switchyard at Hoover Dam to Hemenway Wash, but the lines then run parallel and llear each other to the north of Boulder City and then to the southwest toward Chino, California. The two transmission lines remain virtually unchanged in the vicinity of Hoover Dam and Boulder City, except for replacement of conductors and installation of bird guards and vibration dampeners. A segment of the South line was relocated near the Hacienda Hotel/Casino about about three miles west of Hoover Dam, including removal or relocation of at least two towers and construction of at least two additional towers.
The SCE lines were tied to Mead Substation, south of Boulder City, in the early by means of tie lines constructed to the west of the substation.