The Southern California Edison (SCE) Switchyard was an integral element of the Hoover Dam electrical generation and transmission system. This switchyard provided much-needed electricity during World War II to power Douglas, Vultee, and Northrup aircraft plants, the Long Beach Naval Shipyard, military bases, and major steel and aluminum production plants. Electricity provided by this switchyard and the SCE North and South Transmission Lines was also very important in the post-war agricultural and municipal development of California. Report Prepared by: Associated Cultural Resource Experts (ACRE) Sangre de Cristo Road, STE 202 Littleton, CO Date: April HISTORIC AMERICAN ENGINEERNG RECORD HOOVER DAM, SOUTHERN CALIFORNIA EDISON SWITCHYARD HAER NO.
NV-27-E (Page 2) The Southern California Edison (SCE) Switchyard was an integral element of the Hoover Dam electrical generation and transmission system. This switchyard provided much-needed electricity during World War II to power Douglas, Vultee, and Northrup aircraft plants, the Long Beach Naval Shipyard, military bases, and major steel and aluminum production plants. Electricity provided by this switchyard and the SCE North and South Transmission Lines was also very important in the post-war agricultural and municipal development of California Description: The SCE Switchyard is located south of U.S. Highway 93, to the south of the Metropolitan Water District Switchyard.
The This SCE switchyard was built into a steep north- facing rock slope, and the north fa9ade of the facility includes stone slope curbing and a high concrete wall. The switchyard receives current by means of two transformer circuits that cross the canyon from the Arizona wing of the power plant, and the SCE North and South Transmission Lines exit the west end of the switchyard. To help accommodate the slope, the equipment deck of the switchyard has two levels. The main bus system, oil circuit breakers, selector switches, a capacitor tower, and five take-off structures are located on the main level.
A narrower level along the south side of the switchyard houses two receiving bus towers, three disconnect switches, a 12,000-gallon oil storage tank, and the foundation for a second capacitor tower. And 82' 6" x 25' 10" lower service building also has two levels that house a battery and battery charger room, an oil storage tank, a pump room, a relay control room, a storage room, and a stairwell to the main equipment deck. History: The Southern California Edison Company contracted to begin taking Hoover Dam electricity on June 1, but the company expedited its construction schedule in response to growing power demands in southern California.
Initial plans for the x switchyard on the south side of the highway were prepared in Excavation began in November for the control and power conduits extending from the site of the Metropolitan Water District to the north. Excavation for retaining walls, oil circuit breaker foundations, tower footings and other features began in January Due to the extreme slope of the site, retaining walls up to 36' 3" high were required, and high concrete footings were needed for equipment in the lower, or northern, part of the switchyard. Limited heavy construction equipment was available at that time, and all excavation work for the switchyard was done with manpower using, shovels, and jackhammers.
Installation of power and control conduits from the MWD Switchyard to the SCE Switchyard site began on June 15, and was completed on July 21, As part of this construction, conduits were also run to the 150-ton crane.
Erection of the capacitor tower in the switchyard was accomplished on July 5, and the northeast bus tower was built on July 13, Concrete pouring in the switchyard began in March and construction of the steel bus works was completed by February 15, Erection of three 600-ampere oil circuit breakers began on October 4, and was completed on November Construction of the switchyard was virtually completed by April After tests, the switchyard began receiving electricity from generating unit A-7 on June 19, and from unit A-6 on September 12, HOOVER DAM, SOUTHERN CALIFORNIA EDISON SWITCHYARD HAER NO. NV-27-E (Page 3) Expansion of equipment within the switchyard was started in late to accommodate a second transmission line then under construction.
Equipment in this expansion was similar to the original installation, and by the end of the year concrete footings had been poured and steel erection had begun. This expansion was completed in and power was provided to the second transmission line by the end of that year. A second expansion of equipment began almost immediately to accommodate reception of power from generating unit A-5. Assembly and erection of steel structures in the second expansion began in March Erection of oil circuit breakers for the expansion was completed by August 31, except for filling with oil. The second switchyard expansion and the corresponding Transformer Circuit No.
10 were ready for service by December 31, The two tie circuits between the SCE and MWD switchyards have been discussed above; construction of these tie circuits apparently did not substantially alter the SCE switchyard. SCE had adopted a 50-cycle operating system long before Hoover Dam was built, and the company continued to use this system after most other utilities and agencies, including the Metropolitan Water District, had adopted 60-cycle generation and transmission. SCE's 50-cycle system substantially complicated power plant circuitry and the interconnection with the MWD Switchyard, and by MWD had excess power that SCE needed. On April 8, SCE converted generating units A-5, A-6, and A-7 to 60-cycle operation.
Alterations were made to the SCE Switchyard in in preparation for transfer of control functions to Mead Substation. The changes included installation of current transformers, coupling capacitor potential devices, line traps, and control equipment in the switchyard and the battery oil houses, and installation of an air conditioner in the battery oil house. The large oil circuit breakers were replaced in or and batteries and the battery charger were removed from the battery and oil house beneath the northern part of the switchyard.