The documentation has been prepared for Southern California Edison (SCE) because of proposed modifications to the dam. The modifications include installing a Geomembrane liner on the upstream side of the dam to stop current leakage and to prevent or minimize future leakage from the dam. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) Spanning the South Fork of Bishop Creek No. CA-145-7 (Page 2) PART I. HISTORICAL INFORMATION A. Physical History 1. Date of Construction: Hillside Dam was constructed between and It replaced a previous dam, which was constructed in In the Nevada-California Power Company acquired the site from the Hillside Water Company.
In the new owner enlarged the existing dam and the next year began construction on the current, much larger dam in its place.1 2. Engineers: The engineering firm of Manifold and Poole is credited with the design of the dam.2 Richard G. Manifold and Charles O. Poole were principals of the engineering and consulting firm located in the Central Building at 108 W. 6th Street, Los Angeles.3 The firm worked on several large Nevada-California Power Company projects, including the Silver Lake Power Plant in They also did work for affiliated power companies, such as the Southern Sierras Company. Richard Going Manifold was born on March 12, in Ireland.4 He immigrated to the U.S.
in Around the time of the Hillside Dam construction, he resided in Los Angeles at Hobart Boulevard.5 He moved around somewhat, residing in Riverside, California in and Glendale, California in according to census records. He was married to Charlotte Poole and had two children. He died at the age of 86 on March 8, Charles Oscar Poole was born on June 17, in Salisbury, Massachusetts. He married Margaret A. Egan in Around the time of the Hillside Dam construction, the couple resided at W. Street, Los Angeles.8 They later moved to Crenshaw Boulevard, where Poole resided at the time of his death at age 66 on April 30, Poole was a member of the City Club, Chamber of Commerce, and American Society of Civil Engineers.9 1 Diamond, Valerie H., Stephen G. Helmich, and Robert A. Hicks.
South Lake Dam Historic Resources Inventory Form. Bishop Creek Hydroelectric System Historic District Report. Unpublished report by Theodoratus Cultural Research, Inc.: January 11, p. A-187; Charles O. Poole. Hydroelectric Development on Bishop Creek, Cal., Electric World, p. 7. 2 Ibid; p. A-188. 3 Los Angeles City Directory, 4 U.S. Census data, 5 Los Angeles City Directory, 6 California Death Index, 7 U.S. Census data, 8 Los Angeles City Directory, 9 Member of Local Engineering Firm Paralysis Victim. Los Angeles Times. April 3, p. A7. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) Spanning the South Fork of Bishop Creek No. CA-145-7 (Page 3) 3. Builder: Nevada-California Power Company 10 4.
Original Plans: There are no original plans remaining on file for Hillside Dam; however, there are several later drawings on file in the Southern California Edison offices, as well as early photographs of its resurfacing in the Southern California Edison Company Collection at the Huntington Library in San Marino, California. The following information was gathered from a study of those drawings and photographs and from a Historic Resources Inventory Form prepared for the dam in Hillside Dam was designed as a rock-filled structure with timber sheathing on the upstream face. The downstream face was left as exposed rock fill. The dimensions of the dam were 645 long x 81 - 6 high. It was 11 wide at its apex.
The timber sheathing consisted of redwood and was spaced at 6 on center and attached to 8 Douglas fir stringers spaced at 5 - 4 on center. There were three different thicknesses of plank as the depth increased. The bottom of the sheathing was sealed into a concrete-filled trench. The slope of the upstream face of the dam was horizontal to 1 vertical. The downstream slope was horizontal to 1 vertical. The elevation of the dam was , and the floor of the spillway was 6 lower. The spillway, excavated through solid rock at the east end of the dam, was 40 wide. Two 24 still waste pipes were laid through the base of the dam to provide an emergency outlet. The inlet to one of these pipes was located at the toe of the dam and the other was carried through the rock tunnel 200 into the lake.
The draw-off valves for the outlet pipes were located at the heel of the dam and were protected by a concrete gatehouse.11 An outlet tunnel was also constructed through bedrock below the lowest point in the dam s foundation to create additional storage below the original lake. The unlined tunnel measured in length with a 5 x 7 opening within the reservoir. The elevation was at its upper end and at its lower portal. 5. Alterations and Additions: The dam and outlet tunnel have undergone few changes. The two 24 emergency waste pipes were abandoned and encased in concrete during the Also during the same period, a 24 steel valve pipe was added to one end of the outlet tunnels.12 Portions of redwood facing were replaced in and possibly more recently.13 10 Diamond; p. A-188. 11 Poole; p. 6 7.
12 Ibid; p. A-188. 13 Ibid. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) Spanning the South Fork of Bishop Creek No. CA-145-7 (Page 4) A metal handrail was added to the top of the dam along the upstream edge at an unknown date. B. Historical Context Hillside Dam is significant for its role in the early engineering concept and construction of the Bishop Creek Hydroelectric System. The Bishop Creek Hydroelectric System has been determined eligible for the National Register of Historic Places as a historic district, and Hillside Dam is a contributor to the district.
The system as a whole is significant for its roles in the expansion of hydroelectric power generation technology, in the development of eastern California and western Nevada, and in the development of long-distance electrical power transmission and distribution.14 Hillside Dam itself is significant for its use of innovative engineering methods used to excavate a tunnel beneath the dam for use as a pressure tunnel. Overview of the Bishop Creek Hydroelectric System and Hillside Dam15 The Bishop Creek Hydroelectric System consists of five sets of independent, high-head, impulse water wheel, electricity-generating power plants at various elevations along the south, middle, and north forks of Bishop Creek.
It is a typical run-of-the-river type system that was built to exploit the geography of the eastern slopes of the Sierra Nevada Mountains. Bishop Creek starts at the 13,000-foot crest of the Sierra Nevada Mountains and drops over over a horizontal distance of 14 miles to the Owens Valley. For the most part, Bishop Creek flows in steep-sided canyons with the north wall of the canyon composed of a glacial moraine, which forms a natural, almost continuous ridge paralleling the creek. This ridge was used as the backbone for most of the Bishop Creek Hydroelectric flowlines.
The Bishop Creek system consists of five powerhouses, one control station, two gauging stations, ten flowlines, ten intakes, seven penstocks, four diversions, four reservoirs, four dams, worker housing, and other associated support buildings. Most of the Bishop Creek project area falls within the rain shadow of the Sierra Mountains, and the vast majority of the precipitation in the area falls as snow in the high mountains. The snow fields furnish an abundant water supply during the summer, but the stream flow dwindles in the fall when water is drawn from the reservoirs. South Lake (originally Hillside Reservoir) was designed to regulate flow, rather than to create head, along the creek. In conjunction with Bluff Lake, South Lake confines the headwaters of the South Fork of Bishop Creek.
Like the other lakes in the system, South 14 Taylor, Thomas T. Bishop Creek Hydroelectric System, Bishop Creek, Bishop Vicinity, Inyo County, California. Historic American Engineering Record No. CA-145. From Library of Congress. Built in America Collection: Historic American Buildings Survey/Historic American Engineering Record/Historic American Landscapes Survey, 1933-Present. February 7, p. 1. 15 Excerpted from Taylor, Bishop Creek Hydroelectric System, HAER No. CA-145; p. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) Spanning the South Fork of Bishop Creek No. CA-145-7 (Page 5) Lake stores snow-melt from the high Sierra Nevada Mountains crest near . Its capacity is acre feet. The water in the reservoir is kept ready for release when needed.
Thus, water stored during high flow, which is usually during winter and spring, can be released during summer and fall low-flow periods. Waters from Green Creek and Bluff Lake are diverted to South Lake on the South Fork of Bishop Creek. From South Lake Dam (originally Hillside Dam) to Coates Meadow, a distance of seven and one half miles, the stream travels the natural channel toward its confluence with the Middle Fork. At Coates Meadow the South Fork Bishop Creek Dam and flowline diverts a portion of this water into Intake 2, a stabilizing reservoir. From below Intake 2, the water transportation pattern is repeated from plant to plant: water is taken from an intake or equalizing pond and transported via flowlines and penstock to the next plant.
In this way, the water of Bishop Creek is used five times on its journey down the steep canyon to the edge of the Owens Valley. From Intake 2 to Plant 6, the water drops . After leaving Plant 6, the water is used for irrigation before final disposition into Owens River. History of the Bishop Creek Hydroelectric System and Hillside Dam16 Word of the discovery of economic minerals at Tonopah and Goldfield in western Nevada drew numerous fortune seekers, including Loren B. Curtis, a hydraulic engineer, and Charles M. Hobbs, a former official in the Denver and Rio Grande Railway, in Curtis and Hobbs had come for the mineral prospects but realized that the economic boom could not continue without adequate power.
Although the locally owned and operated Tonopah Light and Power Company and Goldfield Electric Light and Power Company had generated electricity by the burning of fuels, their power was too expensive and unreliable. Curtis and Hobbs recognized the potential market for hydroelectric power and identified Bishop Creek in California as the best location for the generators. The Nevada Power, Mining and Milling Company was incorporated on December 24, Construction began on the first power plant (Plant 4) in January A contract for delivery of power was signed with the Combination Mines Company in May By August water rights had been secured from the Hillside Water Company, and on September 19, hydroelectric power was delivered to the Goldfield Substation, and two days later to Tonopah.
System additions were undertaken in after new ore discoveries in Manhattan, Bullfrog, and Rhyolite, Nevada portended an expanding power market. These included an enlarged South Lake, a new reservoir (Sabrina) on the Middle Fork of Bishop Creek, a new transmission line to Tonopah and Goldfield, a new general office in Goldfield, and expansion 16 Excerpted from Taylor, Bishop Creek Hydroelectric System, HAER No. CA-145; p. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) Spanning the South Fork of Bishop Creek No. CA-145-7 (Page 6) of Plant 4.
In addition, the Nevada Power, Mining and Milling Company reorganized as the Nevada-California Power Company, and all capital stock of Hillside Water Company was purchased in order to guarantee adequate water supplies for electric power generation and permit the construction of additional plants along the course of Bishop Creek. In the Nevada-California Power Company purchased the assets of the Bishop Light and Power Company and the capital stock of the Rhyolite Light, Heat and Power Company. Another unit was added to the Plant 4 powerhouse, and Plants 2 and 5 were constructed and respectively). The existing facilities were now capable of producing twice the power for which there was a market.
In the Nevada-California Power Company decided to diversify their market by expanding into Southern California. In June the Southern Sierras Power Company was formed as part of the expansion efforts. It purchased and operated the equipment installed at Plant 5 and began construction of a transmission line from Plant 5 to San Bernardino, California. Also in Plant 3 was built by the Nevada-California Power Company. It was during this period that the company also completed construction of the new Hillside Dam. In the Southern Sierras Power Company completed construction of Plant 6 on lands downstream from Plant 5 and the system was essentially complete.
(Plant 1 was to have been built at the present site of the Plant 2 intake, but was never built because of the vulnerability of the site to avalanches.) The combined power generated by the Bishop Creek system was now 24, 350 kilowatts. In the Nevada-California Electric Corporation was formed as a holding company for the associated companies. In addition to the Nevada-California Power Company and the Southern Sierras Company, the associated companies included the Sierras Construction Company, the Corona Gas and Electric Company, the Bishop Light and Power Company, the Interstate Telegraph Company, the Hillside Water Company, the Elsinore Electric Light Company, and the Barstow Utilities Company.
In the Nevada-California Electric Corporation reorganized as an operating company and changed its name to the California Electric and Power Company, or CalElectric. CalElectric was absorbed by the Southern California Edison Company in a merger/takeover in BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) Spanning the South Fork of Bishop Creek No. CA-145-7 (Page 7) Significance of the Bishop Creek Hydroelectric System and Hillside Dam17 The Bishop Creek Hydroelectric System is significant for its position in the expansion of hydroelectric generation technology, its role in the development of eastern California and western Nevada, and the development of long-distance power transmission and distribution.
Hillside Dam is significant as a contributor to the system, which is credited with several early long-distance transmission records. The system contributed vitally to the success of the Tonopah and Goldfield mining ventures and the overall economic independence of western Nevada. Additionally, along with the associated companies, the Bishop Creek system provided power to run large-scale ice producing machines in the San Bernardino, Coachella, and Imperial Valleys. 17 Excerpted from Taylor, Bishop Creek Hydroelectric System, HAER No. CA-145; p. 15. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) Spanning the South Fork of Bishop Creek No.
CA-145-7 (Page 8) Documentation of the Hillside Dam was prepared in for Southern California Edison (SCE) when they proposed to install a Geomembrane liner on the upstream side of the dam to stop leakage and to prevent or minimize future leakage from the dam. The purpose of this addendum is to record the intake and intake tunnel, which have never been photographically documented because they are usually under the lake. SCE proposes to modify the existing South Lake Dam intake by removing the existing intake structure, rubble-cover and timber- lined tunnel (located at the entrance only), which are currently in poor condition due to weathering and age.
SCE proposes to replace 85 feet of the tunnel with a new 36 inch diameter stainless steel pipe from the intake downstream toward the dam into the rock tunnel and a new headwall to improve tunnel access and safety, and increase operating control at the intake. Therefore, SCE is documenting the intake and tunnel before these modifications are made. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 21) PART I. HISTORICAL INFORMATION A. Physical History 1. Date of Construction: In the Nevada-California Power Company acquired the site from the Hillside Water Company.
Construction on the Hillside Dam tunnel began in the fall of The Hillside Dam soon followed, which was constructed from to The new Hillside Dam replaced a previous dam, which was constructed in 2. Engineers: The engineering firm of Manifold and Poole is credited with the design of the dam.2 Richard G. Manifold and Charles O. Poole were principals of the engineering and consulting firm located in the Central Building at 108 W. 6th Street, Los Angeles.3 The firm worked on several large Nevada-California Power Company projects, including the Silver Lake Power Plant in They also did work for affiliated power companies, such as the Southern Sierras Company. Richard Going Manifold was born on March 12, in Ireland.4 He immigrated to the U.S.
in Around the time of the Hillside Dam construction, he resided in Los Angeles at Hobart Boulevard.5 He moved around somewhat, residing in Riverside, California in and Glendale, California in according to census records. He was married to Charlotte Poole and had two children. He died at the age of 86 on March 8, Charles Oscar Poole was born on June 17, in Salisbury, Massachusetts. He married Margaret A. Egan in Around the time of the Hillside Dam construction, the couple resided at W.
Street, Los Angeles.8 They later moved to Crenshaw Boulevard, where Poole resided at the time of his death at age 66 on April 30, Poole was a member of the City Club, Chamber of Commerce, and American Society of Civil Engineers.9 1 Difficulties Encountered , from Power Development and Transmission Systems of The Nevada-California Power Company and The Southern Sierras Power Company, p. 8. 2 Diamond, Valerie H., Stephen G. Helmich, and Robert A. Hicks. South Lake Dam Historic Resources Inventory Form. Bishop Creek Hydroelectric System Historic District Report. Unpublished report by Theodoratus Cultural Research, Inc.: January 11, p. A-187; Charles O. Poole. Hydroelectric Development on Bishop Creek, Cal., Electric World, p. A-188. 3 Los Angeles City Directory, 4 U.S.
Census data, 5 Los Angeles City Directory, 6 California Death Index, 7 U.S. Census data, 8 Los Angeles City Directory, 9 Member of Local Engineering Firm Paralysis Victim. Los Angeles Times. April 3, p. A7. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 22) 3. Builder: Nevada-California Power Company 10 4. Original Plans: There are no original plans remaining on file for Hillside Dam; however, there are several later drawings on file in the Southern California Edison offices. There is a description of the inlet and tunnel in a article in Power Development and Transmission Systems of The Nevada-California Power Company and The Southern Sierras Power Company (Poole).
There are also plans drawn by the California Electric Power Company (Riverside California) dated showing modifications made to the Hillside Reservoir (Bishop Creek) Outlet Pipe. The following information was gathered from a study of those drawings and current photographs and from a Historic Resources Inventory Form prepared for the dam in There were originally two 24-inch steel outlet pipes placed through the main fill of the dam. These pipes are partly in rock trench and partly covered with heavy concrete arches to protect them from crushing.
The inlet to one of the pipes is situated at the toe of the dam in the low point, and the inlet of the other pipe is carried through a rock tunnel 200 feet into the lake, thus lessening the change of both outlet becoming clogged with debris at the same time. Both inlets are protected by heavy steel grizzlies (grates).11 This report documents the inlet and tunnel of the second outlet pipe. The outlet tunnel was constructed through bedrock below the lowest point in the dam s foundation to create additional storage below the original lake. The unlined tunnel measured in length with a 5 x 7 opening within the reservoir. The elevation was at its upper end and at its lower portal. 5.
Alterations and Additions: A 24 steel valve pipe was added to one end of the outlet tunnel in the 12 Originally, a large gate was operated from the top of the tunnel shaft to shut off the tunnel downstream to allow safe access to the tunnel. Currently, the gate (located at the bottom of the vertical shaft) is no longer operational. 10 Diamond; p. A-188. 11 Difficulties Encountered, p. 6. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 23) B. Historical Context Overview of the Bishop Creek Hydroelectric System and Hillside Dam13 The Bishop Creek Hydroelectric System consists of five sets of independent, high-head, impulse water wheel, electricity-generating power plants at various elevations along the south, middle, and north forks of Bishop Creek.
It is a typical run-of-the-river type system that was built to exploit the geography of the eastern slopes of the Sierra Nevada Mountains. Bishop Creek starts at the 13,000-foot crest of the Sierra Nevada Mountains and drops over feet over a horizontal distance of 14 miles to the Owens Valley. For the most part, Bishop Creek flows in steep-sided canyons with the north wall of the canyon composed of a glacial moraine, which forms a natural, almost continuous ridge paralleling the creek. This ridge was used as the backbone for most of the Bishop Creek Hydroelectric flowlines.
The Bishop Creek system consists of five powerhouses, one control station, two gauging stations, ten flowlines, ten intakes, seven penstocks, four diversions, four reservoirs, four dams, worker s housing, and other associated support buildings. Most of the Bishop Creek project area falls within the rain shadow of the Sierra Mountains, and the vast majority of the precipitation in the area falls as snow in the high mountains. The snow fields furnish an abundant water supply during the summer, but the stream flow dwindles in the fall when water is drawn from the reservoirs. South Lake (originally Hillside Reservoir) was designed to regulate flow, rather than to create head, along the creek. In conjunction with Bluff Lake, South Lake confines the headwaters of the South Fork of Bishop Creek.
Like the other lakes in the system, South Lake stores snow-melt from the high Sierra Nevada Mountains crest near feet. Its capacity is acre feet. The water in the reservoir is kept ready for release when needed. Thus, water stored during high flow, which is usually during winter and spring, can be released during summer and fall low-flow periods. Waters from Green Creek and Bluff Lake are diverted to South Lake on the South Fork of Bishop Creek. From South Lake Dam (originally Hillside Dam) to Coates Meadow, a distance of seven and one half miles, the stream travels the natural channel toward its confluence with the Middle Fork. At Coates Meadow the South Fork Bishop Creek Dam and flowline diverts a portion of this water into Intake 2, a stabilizing reservoir.
From below Intake 2, the water transportation pattern is repeated from plant to plant: water is taken from an intake or equalizing pond and transported via flowlines and penstock to the next plant. In this way, the water of Bishop Creek is used five times on its journey down the steep canyon to the edge of the Owens Valley. From Intake 2 to Plant 6, the water drops 13 Excerpted from Taylor, Bishop Creek Hydroelectric System, HAER No. CA-145; p. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 24) feet. After leaving Plant 6, the water is used for irrigation before final disposition into Owens River.
History of the Bishop Creek Hydroelectric System and Hillside Dam14 Word of the discovery of economic minerals at Tonopah and Goldfield in western Nevada drew numerous fortune seekers, including Loren B. Curtis, a hydraulic engineer, and Charles M. Hobbs, a former official in the Denver and Rio Grande Railway, in Curtis and Hobbs had come for the mineral prospects but realized that the economic boom could not continue without adequate power. Although the locally owned and operated Tonopah Light and Power Company and Goldfield Electric Light and Power Company had generated electricity by the burning of fuels, their power was too expensive and unreliable.
Curtis and Hobbs recognized the potential market for hydroelectric power and identified Bishop Creek in California as the best location for the generators. The Nevada Power, Mining and Milling Company was incorporated on December 24, Construction began on the first power plant (Plant 4) in January A contract for delivery of power was signed with the Combination Mines Company in May By August water rights had been secured from the Hillside Water Company, and on September 19, hydroelectric power was delivered to the Goldfield Substation, and two days later to Tonopah. System additions were undertaken in after new ore discoveries in Manhattan, Bullfrog, and Rhyolite, Nevada portended an expanding power market.
These included an enlarged South Lake, a new reservoir (Sabrina) on the Middle Fork of Bishop Creek, a new transmission line to Tonopah and Goldfield, a new general office in Goldfield, and expansion of Plant 4. In addition, the Nevada Power, Mining and Milling Company reorganized as the Nevada-California Power Company, and all capital stock of Hillside Water Company was purchased in order to guarantee adequate water supplies for electric power generation and permit the construction of additional plants along the course of Bishop Creek. In the Nevada-California Power Company purchased the assets of the Bishop Light and Power Company and the capital stock of the Rhyolite Light, Heat and Power Company.
Another unit was added to the Plant 4 powerhouse, and Plants 2 and 5 were constructed and respectively). The existing facilities were now capable of producing twice the power for which there was a market. In the Nevada-California Power Company decided to diversify their market by expanding into Southern California. In June the Southern Sierras Power Company was formed as part of the expansion efforts. It purchased and operated the equipment installed at Plant 5 and began construction of a transmission line from Plant 5 to San Bernardino, 14 Excerpted from Taylor, Bishop Creek Hydroelectric System, HAER No. CA-145; p. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 25) California. Also in Plant 3 was built by the Nevada-California Power Company.
It was during this period that the company also completed construction of the new Hillside Dam. In the Southern Sierras Power Company completed construction of Plant 6 on lands downstream from Plant 5 and the system was essentially complete. (Plant 1 was to have been built at the present site of the Plant 2 intake, but was never built because of the vulnerability of the site to avalanches.) The combined power generated by the Bishop Creek system was then 24, 350 kilowatts. In the Nevada-California Electric Corporation was formed as a holding company for the associated companies.
In addition to the Nevada-California Power Company and the Southern Sierras Company, the associated companies included the Sierras Construction Company, the Corona Gas and Electric Company, the Bishop Light and Power Company, the Interstate Telegraph Company, the Hillside Water Company, the Elsinore Electric Light Company, and the Barstow Utilities Company. In the Nevada-California Electric Corporation reorganized as an operating company and changed its name to the California Electric and Power Company, or CalElectric.
CalElectric was absorbed by the Southern California Edison Company in a merger/takeover in History of the Hillside Dam Intake and Tunnel15 As the South Fork reservoir of Bishop Creek is a natural lake formed by glacial action and filled by annual snow melt, hydrographic surveyors discovered that the lake was very deep and the low water level of the lake would be lower than the lowest level of the dam face. So the power company would have to engineer a method of getting water out of the natural lake once its surface had fallen below the bottom of the dam. 16 Due to these naturally occurring conditions, engineers decided to drive a tunnel from below the dam site and tap the lake at a considerable depth below the outlet pipes of the dam.
Through calculations, they determined that a foot tunnel could tap the lake at 65 feet below the base of the dam. Work on the tunnel began in The power company constructed a temporary water-power plant to that utilized the natural fall in the creek directly below the dam site and they constructed an auxiliary steam plant to drive air compressors, ventilating fans, etc. The tunnel was started in the bed of the creek, 600 feet below the dam site, at the foot of a granite cliff. Construction workers started to bore into the side wall of the cliff, driving into the ridge at an angle to insure that the rock wall could withstand the high water pressure that would run through it upon completion.
The tunnel was dug five feet wide and six feet high and ran on a grade of 1 15 Excerpted from Difficulties Encountered and Overcome in Construction of the Hillside Tunnel pp. 16 Rudolph W. Van Norden. System of Nevada-California Power Company and the Southern Sierras Power Company- Part 1. p. 6. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 26) feet per feet. It bends from the outlet to the center of the dam and then runs under the dam to the center of the lake bed. At a point feet upstream above the dam there is a rock ridge that is 30 feet above the outlet pipes of the dam and forms an island in the lake, which is submerged about 40 feet when the reservoir is full.
In order to expedite the work of driving the tunnel, engineers bore a vertical shaft from the center of this island (outcrop) and started to dig toward the dam from the opposite direction. The shaft also served as a safeguard for the men working in the tunnel. Workers dug cautiously as they were uncertain whether the end of the bank was solid or shattered rock. To help determine this, they made sounds at the end of the ridge where the tunnel was to break through. To make the sounds, they cut holes through 2 feet of ice and 65 feet of water. When the face of the tunnel was within a distance of 50 feet of the finish, a hole was drilled ahead of the face from 10 feet to 15 feet.
In December, when the workers were within about 20 feet of the planned terminus of the tunnel, they encountered loose ground and mud and water came through the fissures in the rock. They determined it was unsafe to continue as the lake was frozen over with nearly 2 feet of solid ice and temperature was near zero. In order to break through the remaining portion of tunnel into the lake bed, the engineers decided to use explosive powder. However, because the temperature of the water and air were below the congealing point of the explosive powder, they kept the powder house heated with steam to prevent the powder from freezing and they would have to be placed as quickly as possible into the rock bed when it was intended to be used.
In preparation of blowing through the last 20 feet, the workers gouged out five additional feet on either side of the tunnel, leaving the end of the tunnel in the shape of a T 15 feet across the face. They laid four inch by four inch timbers across the tunnel at the face and placed the powder on the timbers to keep it away from the bottom of the tunnel and the water below. They placed 50- pound boxes of explosive on top of one another with the covers off. The explosive powder consisted of 40 percent giant, with about pounds of 20 percent stump powder and about 500 pounds of 60 percent gelatin powder for a total of pounds in all. The tunnel was tamped to a thickness of 20 feet, using the muck of the excavation.
In order that the tamping would be loosened and removed to prevent its clogging the tunnel after the blast, they placed a considerable charge within the tamping and timed to fire slightly after the main charge.17 Before placing the powder, they laid two three-inch pipes outside the tamping in the bottom of the tunnel for a distance of 40 feet to drain the water away from the powder. The charge was primed by using twelve detonation caps placed in two sets of six each in a stick of 60 percent powder. Each of these sticks was placed in a box of the same kind of powder. Two sets of wires were carried out through tamping in two-inch iron pipes and the ends of the wires were carried through the shaft to a safe distance on shore and attached to separate exploders.
In addition, as a backup, two additional sets of three fuses were 17 Van Norden, p. 6. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 27) connected to the explosives in case the battery failed, the charge could still be fired with fuses. The decision to use explosives to clear the remaining portion of the tunnel was a dangerous operation. If the explosives were unsuccessful in removing the remaining rock and loose ground, then it would have been very dangerous for workers to clear the debris, thereby allowing water to flow into the tunnel uncontrolled. However, the explosion worked as planned; the main charge exploded the tamping charge on the first attempt.
According to the Poole article Difficulties Encountered and overcome in construction of the Hillside Tunnel, the shot threw a column of black mud, water and rock to a height of 300 feet.18 After the entrance to the tunnel had been broken through, it took considerable work to clear out the area around the opening to make it safe to be submerged under the lake. The rock had been badly shattered and decomposed from the explosion so the workers cut a deep trench in the cliff and framed in a tunnel out of heavy mine timbers and then surrounded the timbers with rock fill. The intake was covered by a metal grizzly (grate). In order to control the water s flow, a side tunnel was driven into the solid rock wall for a distance of 35 feet, intersecting the main tunnel at an angle.
The power company placed a 36- inch diameter bell-end steel pipe, which was secured in the rock tunnel with a cast-iron gate covering the outer pipe. There is a trap gate supported by a heavy cast iron frame embedded into the tunnel walls at about 10 feet into the intersection with the branch tunnel. The trap gate is made of 5/8 inch plate steel and reinforced steel I beams. The opening was three feet wide by five feet high, which was large enough for rock cars to pass through during construction of the tunnel. The trap gate was hinged at the top of the framework and opened toward the lake. It was held up against the roof with a 3/8 inch steel cable and wench. When the explosive shot was fired, the trap gate was left wide open and the 36-inch outlet gate was left about half open.
A man was stationed at each gate when the shot was fired and instructed to immediately spring the trap valve after the explosion and close the gate valve as soon as the water should start.19 Each man waited until he heard water rushing in the tunnel and then closed the valve to trap enough air in the tunnel to prevent shock on the gates and to prevent the mechanisms from being carried away with the rushing water. The operation was successful as the water flowed through the tunnel without causing any damage to the tunnel gauging system. An additional gate, measuring three feet by five feet was placed at the intersection of the tunnel and vertical shaft that rises to the top of the island (rock outcrop) in the center of the lake. The gate is operated from the top of the shaft.
This gate helps keep water pressure off the tunnel. There is a water tight man hole at the top of the shaft to keep the water out of the 18 Difficulties Encountered, p. 10. 19 Van Norden, p. 6. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 28) shaft when the island is flooded. The man hole is taken off each season that the water is drained through the pipes and the lake is lowered. Significance of the Bishop Creek Hydroelectric System and Hillside Dam20 Hillside Dam is significant for its role in the early engineering concept and construction of the Bishop Creek Hydroelectric System.
The Bishop Creek Hydroelectric System has been determined eligible for the National Register of Historic Places as a historic district, and Hillside Dam is a contributor to the district. The system as a whole is significant for its roles in the expansion of hydroelectric power generation technology, in the development of eastern California and western Nevada, and in the development of long-distance electrical power transmission and distribution.21 Hillside Dam itself is significant for its use of innovative engineering methods used to excavate the tunnel beneath the dam for use as a pressure tunnel.
The Bishop Creek Hydroelectric System is significant for its position in the expansion of hydroelectric generation technology, its role in the development of eastern California and western Nevada, and the development of long-distance power transmission and distribution. Hillside Dam is significant as a contributor to the system, which is credited with several early long-distance transmission records. The system contributed vitally to the success of the Tonopah and Goldfield mining ventures and the overall economic independence of western Nevada. Additionally, along with the associated companies, the Bishop Creek system provided power to run large-scale ice producing machines in the San Bernardino, Coachella, and Imperial Valleys.
20 Excerpted from Taylor, Bishop Creek Hydroelectric System, HAER No. CA-145; p. 15. 21 Taylor, p. 1. BISHOP CREEK HYDROELECTRIC SYSTEM, HILLSIDE DAM (South Lake Dam) HAER No. CA-145-7 (Page 29)