“Army Corps of Engineers, Jacksonville Office in St.”

Written record, HAER FL-20-A survey. Machine-read text.

Surveyed by the federal HAER program as HAER FL-20-A · the record runs 5357 words · one of 10 surveyed structures published for this county.

Sources: the survey record at the Library of Congress

Significance

5240 words

Source document Quoted word for word from HAER FL-20-A. Not written, edited or summarised by this site.

Engineered by the U.S. Army Corps of Engineers, Jacksonville Office in St. Lucie Lock and Dam was designed for preventive measures during hurricanes, floods, and droughts while allowing navigation on the Okeechobee Intracoastal Waterway, a 155-mile passage connecting the Gulf of Mexico with the Atlantic Coast via Lake Okeechobee. Report Prepared by: David E. Port and Dena E. Hodes, New South Associates Date: December ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 2 Part I. Historical Information Physical History: 1. Date of construction: 2. Architect/Engineer: U.S. Engineer Office, Jacksonville, Florida, War Department. 3. Original and subsequent owners: State of Florida, U.S. Corps of Engineers 4. Builder: Cleary Brothers Construction Company, West Palm Beach, Florida. 5.

Alterations and Additions: The original main spillway was outfitted with temporary wooden flashboards. In these were replaced with seven steel taintor gates in the main spillway and a steel auxiliary lock gate was installed in the old lock. Modifications to the spillway in resulted in the lakeward deepening of the spillway and dam structure as well as the installation of the present spillway. B. Historical Context St. Lucie Canal's first lock system, constructed in the was reduced to one lock complex by the In Congress authorized the replacement of St. Lucie Lock No. 1 with a weir at Port Mayaca. Lock No.

2, on the east end of the canal, now the sole lock on this leg of the waterway, was to be expanded and modernized with the addition of a larger lock and spillway to the existing lock complex. In May plans were completed for the new lock and central control station, which included a hydroelectric power plant and a spillway dam. The modernized complex was originally referred to as St. Lucie Lock No. 1 on its engineering plans. Later, it was simply referred to as St. Lucie Lock and Dam. The physical construction history of St. Lucie Canal and its locks is largely a story of local, state, and federal reclamation practices and water management policies dictated by the art of legislation.

The Corps' involvement with the Okeechobee Intracoastal Waterway, then known as the Cross-State Canal, officially began with the Rivers and Harbors Act, ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 3 also known as the Navigation Act. This legislation authorized the Corps to provide deeper and wider channels on the Caloosahatchee and St. Lucie Rivers and to control and manage Lake Okeechobee and the waterways associated with the Everglades Drainage District. Packaged within this navigation legislation, the act made provisions for the construction of a levee that flanked three- quarters of the lake. On June 26, the Permanent Appropriation Repeal Act authorized the Corps to operate and manage the locks and dams along the Cross-State Canal.

In an estimated million was appropriated by the National Rivers and Harbors Congressional Corrunittee for construction contracts to erect new locks along the waterway. The Federal Flood Control Act provided that the Federal Government should improve or participate in the improvement of navigable waters and their tributaries for flood control purposes, and the Corps officially assumed responsibility for the Okeechobee Waterway and its watershed. In the Macwilliams Company and Standard Dredging Company were contracted to widen the St. Lucie Canal while the Cleary Brothers Construction Company was contracted to erect the locks, spillways, and structures at the St. Lucie No.2 facility site.

The Cleary Brothers Company had underbid the Spadaro Contracting Company that had previously built Moore Haven and Ortona's Lock and Dam facilities. In Moore Haven Lock was the first of three new locks erected along the Cross-State Canal and became the prototypical lock and dam facility. Both Ortona and St. Lucie Locks and Dams were built afterwards and adapted many of Moore Haven's original designs. During the Great Depression, the Corps hired locally and abroad, thereby maximizing a labor force for this monumental project. During the early years of the New Deal, construction increased under impetus from President Franklin D. Roosevelt's Public Works Administration, which spent million for the Okeechobee Waterway.

Corps and State funds brought this total to over million, and the Corps major source of construction funds came directly from Washington in the form of unemployment relief. Labor was locally supplied as attested through the National Recovery Act Office in Martin County, Florida. ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 4 PART II. DESCRIPTION A. General Statement The St. Lucie reservation is situated along 154 acres in the vicinity of the Hog Creek and Roebuck Creek drainage into the St. Lucie Canal, which is west of the lower South Fork of the St. Lucie Inlet. Located eight miles inland from Stuart, Florida, St.

Lucie's lock enables navigation while the connecting spillway, located 120 feet north of the lock, is operated for flood control, irrigation, maintenance of water stages during low-flow periods and water conservation during droughts. The lock documented here was added to an existing lock system built in The components were a spillway, a dredge pass perpendicular to the spillway, and a lock measuring by The new lock was aligned with the older lock, approximately to the southeast. Paired machine houses were placed on opposite sides of the upper and lower gate structures. An office and control building was placed adjacent to the new lock and a cluster of five lock tenders' residences were placed further to the southeast on the elevated area adjacent to the lock.

A paved access road led from State Road 109 to the lock and dam facility. The new lock is constructed of steel sector gates and steel sheet pilings line the lock walls. A length of steel sheet pile wall that forms the lock chamber connects the upper and lower gate structures of the lock. The lock's interior is constructed with poured concrete and lined with sill pine timbers along the interior walls as part of its fender system. The spillway, which extends from the dredge bypass across the canal, is a seven steel taintor gate spillway set on a concrete foundation. The overall width between abutment piers of the spillway is B. Physical Description St. Lucie Lock The lock measures approximately in length with the riprap extending 30' east and west of the chamber, 50' in width, and ST.

LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 5 in depth or below mean sea level with a lift averaging 1' to 5' depending upon the water level. In the late the St. Lucie facility was built-up, landscaped and graded to an average height of 17' above mean sea level (AMSL). However, the highest elevation for this facility is a built-up levee directly south of the lock tender's houses, which is 23' AMSL. Considering St. Lucie's history and the hurricane's damage, the facility was designed to be a functional bulwark against flood waters and storm surges. Along the lock chamber, the spillway, and the island between these two structures, which consists of the old lock chamber and dredge pass, the average elevation is at 21' AMSL.

The spillway adds a continuance of the two locks thereby providing a uniformed front that intersects the east-to-west canal. On the up lakeside, the canal's bottom or entrance sill to the lock chamber is -0. 9 4' This elevation decreases to on the St. Lucie River's side as part of the natural grade and release of the water downstream. From the surf ace level along the lock chamber, the total depth of the chamber is 21. This depth permits unrestricted transit between the upper and lower pools even during times when the minimum water level of the upper pool is 10' AMSL.

Only the South Florida District Operation's Office Area Engineer had the authority to determine the height of the lake's water level in The floor of the lock chamber is a length of steel sheet pile wall set on top of a 6' poured reinforced concrete foundation, which is set on a network of timber pilings. The chamber is 50' in width, providing clear navigation, and the lock vault's depth of is deeper than the other lock facilities within the waterway. The housing for the hurricane gate consists entirely of reinforced concrete, exceeding an elevation of 32' at the lower or eastern gates. The upper gates on the up lakeside are The lock chamber floor is reinforced with concrete side beam and cross strut type with intervening free slab pavement.

The re-entrant arches of the lock chamber's steel sheet pile walls are faced with concrete upper and lower approach channel floors adjacent to the lock and revetments. ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 6 All poured concrete foundations and walls are reinforced with steel pile with the design strength of the concrete for the spillway measuring PSI. The working stresses for structural and miscellaneous steel conformed to the requirements using PSI basic stress. The clear distance between the face of the concrete and the surface of the main reinforcement steel is and 4" where concrete is placed against earth or rock. All exposed unformed surfaces are wood float finish.

Lock chamber walls and connecting walls between the old and new lock structures are steel-sheet piling, tie-back, anchorage, retaining walls. The face of the lock chamber walls and the channel side of sector gates are protected with creosote timber bumpers. The chamber also contains eight needle dam girder recesses or sills. There are four on each side of the chamber with two sills in front of and two behind each of the lock sector gates. These recesses measure in width and hold the needle dam girders, which are essentially used to support the temporary dams that are used during dewatering for the repair and maintenance of the inner lock chamber.

Upper and Lower Gate Structures The lower lock gate structure on the down lake side is provided with a hurricane sector gate consisting of two 60 , radius structural steel sectors high on the perimeter face. The upper lock gate structure facing the west entrance has a sector gate consisting of two 60 , radius structural steel sectors high on the perimeter face. The size and the weight of the gates are relative to their position where the lower gate is the larger and thus can withstand more pressure against its mass. The gates are installed in concrete housings or gate chambers and are operated by rack and pinion drive. The gate operating machinery is located in houses on the lock masonry walls. The gate chamber masonry is on a timber pile foundation with a steel sheet pile cut-off walls.

The sector lock gates appear in design and form to resemble the large taintor-type gates that are used on the spillway dam. The taintor gates are horizontal and are laid on their side with additional steel buttressing while the sector gates are on a vertical axis and are enclosed in a concrete gate chamber. The massive concrete housing for the sector gates has the advantage of being able to be opened and closed against a full lake or head of water, thus permitting the use of the gates for filling ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 7 and emptying the lock chamber. This design eliminated the costly filling and emptying of passages in the chamber's walls and floors as well as the filling of control valves to open the gates.

This was the prevailing process for the earlier locks built with funding from the Everglades Drainage District and the basic lock design is also seen in Canadian rivers. Steel sheet piles are used for the lock chamber's walls and the cutoffs under the floor, and wooden piles carry the gate structure. Fenders are of creosote timber. All sector gates are swung from the top by a single hinge and supported at the bottom by a pintle. The lock gates appear in design and form to resemble large taintor-type gates laid on their side with additional steel buttressing. Electrically driven reduction gears prescribe movement. The gates move into arced-shaped housings set into the lock sides to provide unobtrusive boat transit.

The gate assemblies may be accessible by manholes set back from the top of the lock covered by grating, and vertically by climbing down onto the gates when locked into place. The upper gate housing is constructed or poured reinforced concrete. During hurricane storm tides, the hurricane gates can be locked in place. The lock gates have a moveable catwalk at both ends that transverses the canal in a V-shaped pattern when closed. At all three locks and dams, these catwalks over the lock gate allow access to the opposite side of the lock chamber and the spillways. The catwalks are essentially built onto the top of each sector gate and move accordingly. At St.

Lucie, a cathodic protection system is installed in the upper and lower lock gates, lock chamber, the upper end of the lock, and the upper face of the structure extending between the generator house and the lock. Interior of the Lock Chamber and Mechanical Equipment The lock structure machinery consists of four sector gates operated by cable drum units. The motor units for operating each of the four sector gates are located in the four machinery houses and are normally operated by electric power. Provisions are made for each unit to operate manually during emergency conditions. A driving rack is installed around the outside face of each sector gate and movement of the gate is effected by rack and pinion drive. The cable drum units are covered below ST. LUCIE CANAL, LOCK NO. 1 HAER NO.

FL-20-A Page 8 surface within the lock chamber wall, while the gear boxes are located within the arched-shaped housing wells set into the lock chamber's side for each sector gate. The driving rack or channel guide's movement of the gate is effected by cables stretched around the outside surface in the channel guide through sheaves and idlers to cable drums. The cable drums for movement of gate are powered by electric motors through a system of gears and speed reducing units. The operation of two motors is needed to move the sector gates in tandem, or one half of the lock gate. Emergency provisions for these units feature a manual miter crank.

The AC motor functions through a system of speed-reducing gears, which also power the cable drums for movement of the gates, and are engaged through a manually operated clutch. The speed reducer unit is a parallel shaft double reduction unit with an overall ratio of to 1. Rated capacity is with an input shaft speed of 900 revolutions per minute. It is capable of withstanding an overload of 100 percent of full load toque for starting and stopping duties. Gears are balanced double helical type with generated involute teeth. The spur gear units are rated 5 with an input shaft speed of revolutions per minute with an overall ratio of to 1. The speed-reducer units are housed in the machinery recesses. Bearings are sleeve-typed lined with babbitt and bronze backed.

The speed reducer is directly connected to a right angle drive gear unit. The units are equipped with a lubrication system, an oil level indicator and oil drain. A hand hole for inspection of the gears is provided in the case. The hand drive units for each sector gate machine is installed in the machinery houses. The unit consists of a welded steel housing with chain and sprocket hubs and a foot operated brake lever (locking type) assembled together with a device for the engagement and disengagement of the hand drive unit to the lock operating machinery. The overall ratio is to 1. The units are assembled with an engagement and disengagement device from the hand-drive unit to the gate operating machinery.

The following information details the motors and their components within the machinery recesses and sector gates: ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 9 The motors for operation of the gate sectors are located in the machinery houses near each gate. The motors are directly connected to the speed reducer units through the manually operated clutch. They are open type, shunt wound, separately excited, direct current with constant torque. They are rated 15 with normal speed at 450 rpm and are capable of operating over a speed range of 45 to 900 The brakes for stopping each sector gate are mounted on the extended shaft on each sector gate motor. The brakes are spring-set, shoe-type, with thruster-operated releases.

They are rated 160 ft Torque and are motor-operated 125-volt Right angle drive gear units contain the spur, angle and pinion gears assembled in a cast-iron housing and are connected from the speed reducer unit in the machinery houses to the rack gears on each sector gate. The unit is equipped with a grease lubrication system. A hand hole is provided for inspection of the gears. Flexible couplings are mounted on all shafts between motor and speed reducer units and between speed reducer unit and right angle drive gear units. Oil plugs are provided for lubrication. Limit switches are of the traveling type actuated by cams located at either end of the sector gate and geared to the gate operating machinery.

The unit consists of a totally enclosed submersible cast-iron case with switch elements arranged in sequence for the proper function of the sector gates and automatic control of the visual signal system. The limit switches are manufactured by Cutler-Hammer, Inc. Transmitters consist of two selsyn transmitters, one of which is geared directly to the gate operating machinery and serves the purpose of indicating the position of the gates. The other one is connected to a ball float by pulley, stainless steel tape and weight in the gauge wall, and serves the purpose of indicating water level. ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 10 The lock is equipped with traffic control lights and horns, mooring bits, and standard safety equipment to allow efficient and safe passage.

The lock chamber has a water level table register located on both sides of the chamber to allow visual tracking of the water level. The depth decreases 5' on the uplake side and increases 5' downlake to permit unrestricted transit. The operation hours at all of the locks are from AM to PM year round with the last lockage performed at PM. The locks are open upon demand and all lock-through are free of charge. Two long horn blast followed by two short blasts or contacting the Lock Master on the marine radio channel will inform the lock tenders that a vessel is ready for lockage. During a severe drought like the one in the summer the lock is only opened every two hours.

In approximately vessels, not including Corps dredges and boats used this lock facility en route to Lake Okeechobee or the Atlantic Ocean. Dam and Diversion Spillway The original spillway was 17 5 ' The structure consisted of temporary wooden flashboards and diversion spillways. Technically, the spillway was defined as a moveable dam because of its temporary nature and alternate openings (the old lock and dredge by-pass). With the lock chamber and middle structures (powerhouse, old lock, and dredge pass), the spillway adds to this assemblage forming a uniformed concrete facade that bisects the St. Lucie Canal. Modifications to the spillway in resulted in the lakeward deepening of the spillway and dam structure as well as the installation of the present spillway.

The seven steel taintor gate spillway and renovations to the auxiliary (old) lock chamber were completed by March 20, The spillway assembly is constructed on a poured reinforced concrete foundation set at least 6' into the canal bottom. The overall width between abutment piers of the spillway is The spillway consists of seven electrically-operated structural steel taintor gates, each having a length of 20' and a height of 10 The sill is at an elevation of +0. 56' AMSL. Concrete piers that form seven bays separate the taintor gates. St. Lucie's spillway consists entirely of taintor gates rather than slide gates. The vertical lift or slide gates are horizontal sheets of steel that are commonly designed to impede and dam the uplake waters. Taintor gates consist of two-part ST.

LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 11 mechanically operated assemblies. Bulkhead or sluice gates are located on the uplake side of the dam and are raised and lowered in tandem with the taintor gates to admit the passage of water through the spillway. The taintor gates are similarly arc- shaped like the lock's sector gates. The taintor gates at St. Lucie were upgraded in coinciding with the modernization of the old lock facility and equipment. The seven taintor gates are located on the north side of the spillway while seven bulkhead or sluice gates occupy the south frontage. Correspondingly, there is one set of bulkheads for each taintor gate.

The taintor gates and bulkhead or sluice gates work in tandem so that when one of the taintor gates is raised, the sluice gate is lowered, and vice versa. The electrically operated machinery for raising and lowering the taintor gates are housed atop the dividing piers. A service bridge spans the entire structure with its floor at elevation AMSL. An emergency bulkhead and traveling hoist operating on tracks throughout the length of the service bridge is provided for closing off spillway openings during periods when taintor gates are under repair or are inoperative for other reasons. Taintor and Bulkhead Gates on Spillway The taintor gates raise and lower in tandem with the flat vertical bulkhead gates.

Movement is accentuated by approximately of cables attached to the taintor gates' faces near the bottom of the end frames of the gates. These cables lead around the arc of the face of the frames to the combination gear and cable drum, which is part of the taintor gate assembly. The taintor gates at St. Lucie were upgraded in when the second (present) lock was put into service The bulkheads for the taintor gates are opened and closed by a hoist car that runs along a trolley line across the length of the spillway. Each bulkhead or sluice gate has three bulkhead gates (top, intermediate, and bottom). Operation of this assembly involves positioning the hoist car over each of the seven sets and the extension of a mechanical arm to turn an equalizer valve.

In a separate operation, an electromechanical wheel and pulley system allows each of the huge taintor gates to be moved to fully regulate water flow. ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 12 The flow control valve for each hoist unit is adjusted to regulate the sluice gate speed to 6" per minute regardless of the load. Lowering of the gates must be achieved (by gravity) without operation of the power unit, by proper positioning the directional control valve. An engraved laminated Bakelite label is located adjacent to the directional control valve showing the position of the valve handle for the "Raise," "Hold" and "Lower" operation.

Cable slings are provided (two for each gate) as a means of supporting the sluice gate at the full open position, independent of the hoist proper for servicing or replacing of hoist cables. While there are slight differences between Ortona and St. Lucie's spillways, the two lock facilities feature a combination of taintor gates. The gates' designs are identical. Likewise, the lock or sector gates at all three locks and dams are similar in design but vary according to their height. Together, the lock and spillway's maximum discharge designed for flood capacity is Cubic Feet per Second During flood capacity, the spillways and lock discharge CFS to limit shoreline erosion and downlake flooding. All sector, taintor, and sluice gates are equipped with vertical and horizontal seals.

The gates seal by way of a heavy-duty rubber bumper that effectively prevents water leakage when closed. The seals are constructed of hard rubber with a tire tread core and are attached to the gates by corrosion-resisting steel bolts. These seals are also called baffle seals, which impede the force of water when the gates are opened, thereby slowing discharge and possible water erosion damage. Spillway Bulkhead Hoist Car and Machinery The bulkhead hoist car consists of a structural steel car mounted on eight car wheels that houses the electrically operated hoisting machinery of the bulkheads. The hoist car is moved manually on tracks extending from the hydroelectric powerhouse across the top of the spillway toward Taintor Gate No. 7. The bulkhead hoist car is stored in the powerhouse.

The hoist motor for operation of the hoist machinery is located on top of the structural steel car. The motor and gear head combination is manufactured by Master Electric Company and is of high-torque, high-slip, squirrel cage induction type designed ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 13 for across the line starting. The motor is enclosed and self- ventilating. It is rated 900 rpm synchronous speed, 208 volt, 3 phase, 60 cycle and is direct connected to a gear head which forms an integral part of the unit. The gear head is a right-angle shaft double-reduction unit with an input shaft speed of 765 rpm and an output speed of 3.6 The unit will deliver torque at the output shaft. The unit is equipped with a lubrication system, an oil level indicator, and an oil drain.

The brake for stopping the bulkhead hoist is mounted on the extended shaft located on the hoist motor. The brake is spring set disc type with magnetic operated release. It is rated 200 percent of full load torque for the hoist motor. The limit switch is of the hoist type and is actuated by counter weight. The unit consists of a totally enclosed cast iron case with a switch element arranged to stop the hoist motor when the bulkhead gate has reached its upper limit. Cutler-Hammer, Inc., manufactures the limit switch. The magnetic contactor is a reversing, magnetic, full-voltage-starting shunt-type controller, which is remotely controlled by a three-button lever type selector switch. The contact tips are removable and are made of copper and faced with a non-welding alloy.

As previously mentioned, the seven taintor gates are raised and lowered by cables that are attached to the face of each gate and lead around the arc to the combination gear and cable drum. The speed reducer unit is directly connected to this combination gear and cable drum. This unit is a parallel shaft, double reduction, worm gear type assemblage with an overall ratio of 333-to-1. The rated capacity is 3 with an input shaft speed of 390 It is capable of withstanding an overload of 150 percent of full load torque for starting and stopping activities. Worm gears are bronze and the worms themselves are formed from hardened, ground, polished steel. Bearings are ball and roller type.

This unit is equipped with a lubrication system for proper lubrication at all operating speeds, an oil level, indicator, and an oil drain. Flexible couplings are mounted on all shafts between motor and speed reducer units and between speed reducer units and pinion gears. The motors for operation of the seven-taintor gates' machinery are located in the machinery recesses on the spillway. ST. LUCIE CANAL, LOCK NO. 1 HAER NO. FL-20-A Page 14 The motors are Century Electric. They are high-torque, high- slip, squirrel cage induction types designed for across the line starting. They are also enclosed and self-ventilated. The motors are rated 3 rpm synchronous speed, 208 volt, 3 phase, 60 cycle, and are direct connected to a gear head which forms an integral part of the unit.

The gear head is a single reduction, helical geared with an overall ratio of 3.93-to-1. Rated capacity is 3 with an input shaft speed of Bearings are ball-type. The unit is equipped with a lubrication system, an oil level indicator, and an oil drain. A portable emergency hand drive unit capable of being attached to the taintor gate machinery is stored in the powerhouse, which is located on the spillway. The unit consists of a welded steel angle iron with chain and sprocket hubs assembled together. The brakes for stopping the taintor gates are mounted on the extended shaft, which is connected to each taintor gate motor. The brakes are spring-set, shoe-type with solenoid-operated release.

They are rated 25' torque, 160 volts DC current, which is supplied by selenium rectifier and are mounted in a watertight enclosure. The brakes are also provided with a hand release lever mounted on the outside of the enclosure. Limit switches are of the traveling cam type and are geared to the gate operating machinery. The unit consists of a totally enclosed submersible cast-iron case with switch elements arranged in sequence for the proper function of the taintor gates. The limit switches are the same for the lock sector gates and are also manufactured by Cutler-Hammer, Inc. Magnetic connectors are reversing, magnetic, full-voltage- starting shunt type, with removable contact tips faced by a non- welding alloy.

They are remotely controlled by the drum-type selector switch for control of the taintor gate motors and are located in the enclosed control panel in the taintor gates' machinery recesses. Selector switches are of the drum type manually operated for control of the magnetic contactors, which control the electric motors for each taintor gate motor. The selector switches consist of five switch elements: lower service, close, off, open and upper service. The selector switches are located on the handrail of the downstream side of the spillway. ST. LUCIE CANAL, LOCK NO. 1 HAER NO.

FL-20-A Page 15 Lock Channel A protective dolphin system, which resemble timbered tripods and act as protective fenders, is located on each side of the channel, approximately 25' from the upstream and downstream ends of the lock and fender system. A creosote pile fender system with catwalks extends above and below the lock on the southeast side of the channel with a protective dolphin located 25' upstream and downstream from the ends of the fender system. A system of seven tie-up dolphins is located on the southeast side of the channel extending from to from the upstream end of the lock. Another system of seven tie-up dolphins is located on the southeast side of the channel extending from to from the downstream end of the lock.

The bottom and side slopes of the approach channel are riprapped for a distance of uplake and downstream, beyond the ends of the lock structure. The revetment extends across the channel downstream above the spillway structure for a distance of 6", and below the spillway. The grouted riprap over the bottom area is 2' thick and all side slopes are riprapped to a thickness of on a 1 to 1.5 percent slope. C. General Siting and Orientation The lock complex is situated in an isolated area that has remained intact as a federal reservation. The lock and dam lie across the channel in an east-west fashion and form an industrial landscape within the undeveloped area that surrounds it. PART III. Sources of Information A.

Drawings Selected as built engineering drawings were photocopied for this documentation from the U.S. Corps of Engineers, Jacksonville District Collection. A full collection of high-resolution images of engineering drawing for St. Lucie Lock No. 1 will be donated to the Florida State Archives, located in Tallahassee, Florida.

In context

Stuart, Florida The place record: every map, photograph and survey of this town.
Martin County, Florida 78 topographic sheets across the county.
Library of Congress record The original filed report as the survey filed it.

Also surveyed in Stuart

9 records

The federal surveyors worked through Stuart building by building. These are the other structures they measured and filed a report on, longest report first.

SheetStructure SurveyReport
St. Lucie CanalHAER FL-2012,389 words
St. Lucie CanalHAER FL-20-A-32,406 words
St. Lucie CanalHAER FL-20-A-12,383 words
St. Lucie CanalHAER FL-20-A-51,255 words
St. Lucie CanalHAER FL-20-B1,222 words
St. Lucie CanalHAER FL-20-A-21,201 words
St. Lucie CanalHAER FL-20-A-41,144 words
St. Lucie CanalHAER FL-20-B-11,029 words
St. Lucie CanalHAER FL-20-B-2788 words

Provenance

  • Written history. Quoted verbatim from HAER FL-20-A. United States federal work, no copyright under 17 U.S.C. 105.
  • Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
  • How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.