Central Pacific Transcontinental Railroad, Tunnel No. 18, Milepost 120.5, Newcastle
Central Pacific Transcontinental Railroad, Tunnel No. 18, Milepost 120.5, Newcastle, Placer County, CA. Surveyed as HAER CAL,31-NEWCA,1-, with a 1,453-word written history.
From the record
“The Central Pacific First Transcontinental Railroad is a segment of the western half of the first transcontinental railroad, built from Sacramento, California to Promontory Summit, Utah between and where it joined the Union Pacific Railroad which had built west from Omaha.”
Written record, HAER CAL,31-NEWCA,1- survey. Machine-read text.
Surveyed by the federal HAER program as HAER CAL,31-NEWCA,1- · the record runs 1453 words · one of 28 surveyed structures published for this county.
Source document
Quoted word for word from HAER CAL,31-NEWCA,1-.
Not written, edited or summarised by this site.
The Central Pacific First Transcontinental Railroad is a segment of the western half of the first transcontinental railroad, built from Sacramento, California to Promontory Summit, Utah between and where it joined the Union Pacific Railroad which had built west from Omaha. For the purpose of the current project, the first transcontinental railroad was found likely to be eligible for the National Register of Historic Places at the national level of significance under Criterion A for its significance in transportation history, in uniting the East and the West, and in the development of the West.
The railroad's period of significance is to from the line's completion in through the years of its role in the settlement and development of the West, to the conclusion of the railroad's achievements in World War U. Built in Tunnel 18 is a contributive element of this property. Report Prepared By: John W. Snyder Co-Principal Preservation Services P.O. Box Sacramento CA CENTRAL PACIFIC TRANSCONTINENTAL RAILROAD, TUNNEL 18 (Newcastle Tunnel) HAER No. CA-197 Page 2
Description
Tunnel 18 is a 991-foot, double track railroad tunnel, with granite ashlar portal faces and wingwalls. As-built, the tunnel was concrete-lined for the first fifty feet in from each portal, with the remainder lined in redwood timber; the railroad has subsequently covered the timbering with shotcrete. The tunnel is on a tangent (no curves) alignment, and carries the tracks of the Union Pacific Railroad's (formerly Southern Pacific, and originally Central Pacific) Donner Pass line. H.
Historical Information
Contractors, Erickson & Petterson of San Francisco built Tunnel 18 (originally numbered Tunnel 4) in as an element of the reconstruction and double-tracking of the original Central Pacific line between Rocklin and Colfax. [For a full history of this line and of this undertaking, see the documentation set for the Central Pacific Transcontinental Railroad (Southern Pacific Overland Route) (Southern Pacific Donner Pass Route), Southern Pacific Donner Pass Route Tunnels, HAER No. CA-196.1 After assuming control of the Southern Pacific/Central Pacific and merging them with the Union Pacific in Edward H. Harriman had embarked on a series of huge reconstruction projects system-wide.
One of these was the double-tracking of the original Central Pacific line over Donner Pass, the first segment of which was from Rocklin to Colfax. In connection with this, Harriman also moved the roundhouse and locomotive shop facilities originally built at Rocklin by the Central Pacific, to nearby Roseville where he built a much larger and more modern facility to handle the larger locomotives he was bringing onto the system. Two contracting firms divided the work, with Erickson & Petterson handling the work from Rocklin east to Clipper Gap, and Utah Construction Company of Ogden building the portion from Colfax west to Clipper Gap.
Tunnel 18 was the only double-track tunnel on the entire project; all the tunnels, whether single- or double-track, conformed to Southern Pacific Common Standard plans. Erickson & Petterson built their tunnels by driving a drift (a small pilot tunnel) at the spring line of the final arch, and centered. From this they widened the arch to full section down to the spring line. They then drove one or two drifts at grade line and, using black powder, blasted the remaining bench directly down into dump cars in the drifts. Because the geology at the site of Tunnel 18 consisted of clay shale with some hard granite boulders, the contractors chose to use an air shovel.
The width of the double-track tunnel also required the use of curved I-beams as temporary support while the construction crews installed the final timbering. As was the case for much of this double-tracking project, the proximity of the existing Central Pacific line to the new line complicated construction operations. At Tunnel 18, the original line had skirted the north slope of the hill being pierced, on a slightly higher alignment. As construction progressed on the new line, crews had to work around trains to install temporary crossings. On the east end of the tunnel, crews built a temporary timber pile trestle under the active line to carry it across the new grade.
This work proved extremely difficult, as it required 45 minutes to drive each pile, inclusive of moving the pile drive from its spur track onto the mainline, driving the pile, and moving the pile driver back to the spur. Often there was insufficient time between trains on the busy mainline, so the work dragged on for some time before completion. Then grading crews used horse-drawn scrapers to build feet of fill, CENTRAL PACIFIC TRANSCONTINENTAL RAILROAD, TUNNEL 18 (Newcastle Tunnel) HAERNo.CA-197 Page 3 seventy feet high and containing cubic yards of material to carry the second track. West of the tunnel, their problem similar, with a 65-fooi-high double-track fill feet long and containing cubic yards stretching between the tunnel and Newcastle Station to the west.
Here, however, crews were able to use material from the existing fill to build the new one. III. SOURCES "Colfax Grade Revision; Southern Pacific," Railway Age Gazette, February Daggett, Stuart. Chapters on the History of the Southern Pacific. New York: Augustus M. Kelley, Publishers, originally published Deverell, William. Railroad Crossing: California and the Railroad, Berkeley: University of California Press, "E.H. Harriman Is President," The Sacramento Bee, September 30, "Electrification on the Southern Pacific," The Railroad Gazette, September 6, "General News Section," Railway Age Gazette, April 21, June 30, March Hofsommer, Don L. The Southern Pacific, College Station, TX: Texas A&M University Press, Howard, Robert West.
The Great Iron Trail: The Story of the First Transcontinental Railroad. New York: G. P. Putnam's Sons, Kraus, George. High Road to Promontory: Building the Central Pacific across the High Sierra. Palo Alto: American West Publishing Company, "Millions To Be Expended: Southern Pacific Is to Be Put in Fine Shape," The Sacramento Bee, June "Oil Burning Mallets; Southern Pacific," Railway Age Gazette, 50:24a, June 16, "Railroad Construction," The Railroad Gazette, November 8, December 27, May 5, June Sabin, Edwin L. Building the Pacific Railway. Philadelphia and London: J. B. Lippincott Company, Signor, John R.
to Richard Starzak, Memorandum, "Brief Chronological History of Sierra Tunnels," October 4, "Survey For The Big Tunnel," The Sacramento Bee, August 24, "The Days When The Central Pacific Was Young," Southern Pacific Bulletin, May CENTRAL PACIFIC TRANSCONTINENTAL RAILROAD, TUNNEL 18 (Newcastle Tunnel) HAER No. CA-197 Page 4 'The Harriman Influence," The Railroad Gazette, January "The Harriman Investigation," The Railroad Gazette, March "The Interstate Commerce Commission's Report on the Harriman Investigation," The Railroad Gazette, July 19, "The Roseville Yards of the Southern Pacific," The Railroad Gazette, December 27, United States Geological Survey. Topographic maps. Gold Hill, Calif, quadrangle, series, (photorevised Auburn, Calif, quadrangle, series, (photorevised IV.
PROJECT INFORMATION As a result of the merger of the Union Pacific and Southern Pacific Railroads, a federal undertaking under the jurisdiction of the Surface Transportation Board of the U.S. Department of Transportation, and in order to accommodate freight trains utilizing longer and taller cars and loads-tri-level auto rack cars and cars carrying double-stacked containers, the Union Pacific will need to increase tunnel clearances on the former Southern Pacific Donner Pass Route. The tunnels, built between and are contributing elements of the National Register-eligible Southern Pacific Donner Pass Route Tunnels Historic District. All tunnels have been laser- measured and the railroad will determine clearance needs on a tunnel-by-tunnel basis.
Some, because of curved alignment, will require interior work to allow for longer cars such as tri4evel auto rack cars; others, Tunnel 18 among them, will require both interior and portal work to provide sufficient vertical clearance for "double-stack" container cars. The latter work may impact the character-defining tunnel portals if crown mining of the tunnels (as opposed to lowering the tunnel floors) is selected. Inasmuch as this would cause an adverse effect to the tunnels, Union Pacific has elected to record the tunnels for the Historic American Engineering Record. Documentation was carried out by Preservation Services, John Snyder Field Director and Historian, and Ed Andersen, Photographer. Photos were made in August and research was carried out from August through March
The federal survey recorded these other structures elsewhere in Placer County. These are the other structures
they measured and filed a report on, longest report first.
Written history. Quoted verbatim from HAER CAL,31-NEWCA,1-. United States federal work, no copyright under 17 U.S.C. 105.
Text capture. Machine-read from the scanned typescript filed with the survey, so spelling and spacing follow the original page.
How this page is made. Documentary passages are quoted from the linked federal record; page labels and counts are clearly marked as site presentation or calculations.