The section of railroad through Cajon Pass provided a vital link between the greater Los Angeles area and distant markets. In the California State His- toric Preservation Office determined the historic route of the AT &SF (now railroad alignment through Cajon Pass to be eligible for listing in the National Register of Historic Places under Criteria a and c. By connecting Los Angeles and San Bernardino to markets throughout the United States, the railroad dramatically affected demographic, commercial, and cultural trends in Southern California. Furthermore, construction of the long, winding alignment through rugged and often steep terrain represents a significant engineering feat for its time. Structure No.
contributes to the function and significance of the railroad line by carrying rail traffic across a substantial drainage channel. Report Prepared by: Scott Thompson, Senior Historian John Goodman, Archaeologist Statistical Research, Inc. Tucson, Arizona Date: March Burlington Northern Santa Fe Railroad, Cajon Subdivision, Structure No. HAER No. CA-2259-K (page 2) Architectural and Engineering Information Structure No. is a two-span I-beam bridge that carries Main Tracks 1 and 2 over Brush Creek, a ma- jor tributary of Cajon Creek. The bridge is located at Milepost 62. 7, immediately southeast of the now- abandoned Cajon Station (Figure 1).
Each span is and the bridge has a total length of The width of the bridge is from one handrail (located on the deck) to the other, and the distance from the top of the deck to the creek bed is approximately As originally constructed in the bridge supported four tracks-the eastbound and westbound main tracks and two sidings (Bridge List, First District, Los Angeles Division, p. 48, Structures Department, Railway Company Kansas City, Kansas). The sidings have since been removed, leaving only Main Tracks 1 and 2. A maintenance road for carrying service vehicles over the drainage parallels Main Track 2 on the bridge's east side. A reinforced-concrete substructure consisting of two abutments and one pier bears the concentrated vertical load of the bridge.
The north abutment has a length of In the upper area of the abutment is an approximately 4' step-down that supports the I-beams. A 15'-0"-long flared and tapered wing wall joins the abutment on the upstream side of the bridge, and a tapered wing wall with a length of is in place on the downstream side. The south abutment has a length of and incorporates an upper step- down to support the I-beams. The upstream and downstream wing walls are tapered, with lengths of 11 '- 0" and respectively. On the downstream side of the south abutment is a date stamp that reads This date refers to the year the Atchison, Topeka and Santa Fe Railway (AT&SF) repaired the abutment, damaged in the flood of Flood waters may have caused extensive spalling, which neces- sitated the repairs.
The new concrete ( repairs) has a color and texture different from that of the old concrete construction). A hexagonally shaped center pier with upward-sloping sides supports the bridge deck spans. The pier has a top width of a top length of and a true height of (although the base of the pier is beneath the creek bed) (Bridge No. on Mile 63, First District, Los Angeles Division, Plan and De- tail of Concrete Abutments and Pier for Foot I-Beams, Ballast Deck, for 4 Tracks, C. E. C. L. No. drawing, 25 February Structures Department, The pier is located equidis- tant to the north and south abutments. A date of is stamped on the northwest side of the pier.
Like the date stamp on the south abutment, the date indicates the year significant repairs were made to the bridge following a major flooding episode. Each span incorporates thirty-two I-beam girders in four sets of eight, or eight girders for each of the four original tracks. The I-beams have a web height of 24" and a width of 8". Fastened atop and lying perpendicular to the girders are 6" x 8" lengths of treated timber that form the bridge deck. The timber deck supports the ballast, ties, and rails. The ballast curbs that run along the outer edges of the spans are constructed of 6" x 10" lengths of treated timber. Hand rails on both sides of the bridge consist of 2" x 6" timber rails on 4" x 4" timber posts.
In AT&SF constructed an underground, reinforced-concrete cutoff wall on the west (downstream) Burlington Northern Santa Fe Railroad, Cajon Subdivision, Structure No. HAER No. CA-2259-K (page 3) side of the bridge to prevent scouring around the abutment and pier foundations. The wall is joined to the downstream ends of the north and south abutments and has a length of a width of and a height of (mostly underground) (Bridge Cut-off Wall, C. E. C. L. No. drawing, 25 January Structures Department, Currently, an approximately 3' section of the wall is exposed in the streambed rubble. As designed and constructed, the structure lifts the streambed to its original elevation, thus reducing water seepage that would otherwise undermine the bridge's substructure on the downstream side.
A reinforced-concrete retaining wall extends from the southeast abutment of the railroad bridge and joins the abutment of a highway bridge located approximately 55' upstream. The upstream bridge is a relatively elaborate, reinforced-concrete structure that was built in as part of U.S. Highway 66. Burlington Northern Santa Fe Railroad, Cajon Subdivision, Structure No. HAER No. CA-2259-K (page 4) Structure Scale: (inset Universal Transverse Mercator coordinate system Projection: Transverse Mercator Datum: North American Datum Zone 11N Ellipsoid: Geodetic Reference System Unit meter Archaeological data: SRI field data Base data: Cajon, California 7.5-minute USGS topographic quadrangle Statistical Research, Inc., December Figure 1. Project location Cajon, California, 7.5-minute U.S.
Geological Survey quadrangle [photorevised