The section of railroad through Cajon Pass provided a vital link between the greater Los Angeles area and distant markets. In the California State His- toric Preservation Office determined the historic route of the AT &SF (now railroad alignment through Cajon Pass to be eligible for listing in the National Register of Historic Places under Criteria a and c. By connecting Los Angeles and San Bernardino to markets throughout the United States, the railroad dramatically affected demographic, commercial, and cultural trends in Southern California. Furthermore, construction of the long, winding alignment through rugged and often steep terrain represents a significant engineering feat for its time. Structure No.
contributes to the function and significance of the railroad line by carrying rail traffic across Lone Pine Creek. Report Prepared by: Scott Thompson, Senior Historian John Goodman, Archaeologist Statistical Research, Inc. Tucson, Arizona Date: March Burlington Northern Santa Fe Railroad, Cajon Subdivision, Structure No. HAER No. CA-2259-N (page 2) Architectural and Engineering Information Structure No. 651 is a reinforced-concrete skewed-arch bridge that crosses Lone Pine Creek near its con- fluence with Cajon Creek (Figure 1). The bridge spans a relatively deep but narrow drainage, and the spandrel walls surrounding the arch openings follow the contours of the rock slopes.
In the Southern California Railway Company (formerly the California Southern Railroad) constructed the reinforced-concrete arch bridge to replace the original iron-girder span (Bridge No. First District on Mile 66, 20 ft. Concrete Arch to Replace 87 ft. Iron Girder, Drawing No. 11 January Structures Department, Railway Company Kansas City, Kansas). The Atchison, Topeka and Santa Fe Railway extended the bridge on the upstream side in during construction of the second line through the pass.
The bridge has an overall length of and a width (measured along the length of the abutment inside the arch) of The arch barrel has a consistent bottom width of however, the height of the arch-measured from the floor of the channel to the arch center-varies from on the upstream side to about 34' on the downstream side because of a change in elevation (Bridge List, First District, Los Angeles Division, p. 48, Structures Department, The space above the arch and between the spandrels is compacted fill, on top of which rest the roadbed, ballast, ties, and rails. The vertical faces of the spandrels recede slightly as they rise from the creek bed.
The downstream spandrel is capped with a beveled coping wall that extends slightly beyond the wall face to protect the masonry below from water penetration. On the upstream side of the bridge, along the deck, the spandrel incorporates a parapet topped with metal-pipe handrails. Retaining walls for holding back roadbed fill and containing the ballast are in place on the north and south sides of the east approach. The retaining wall on the north side consists of three timber planks that measure 4" x 11" x On the southeast side of the bridge is a retaining wall constructed of red sandstone block several courses high. Built in the Blue Cut area of the San Andreas Fault, the bridge began failing progressively due to move- ments along the fault line.
In January AT&SF placed eight 2"-diameter iron rods under the bridge deck to tie the spandrel walls together. The ends of the tie rods were anchored using 12" x 12" x 2" iron plates and nuts. Two years later, following further cracks due to earth movements, additional reinforcing rods were placed above the arch barrel to carry the structure indefinitely (F. D. Kinnie, district engineer, First District, Los Angeles Division, Atchison Topeka and Santa Fe Railway Company, Los Angeles, to M. B. Clark, division engineer, letter, 24 November on file, M. B. Clark, division engineer, to F. D. Kinnie, district engineer, letter, 14 July on file, Burlington Northern Santa Fe Railroad, Cajon Subdivision, Structure No. HAER No.
CA-2259-N (page 3) Scale: (inset Universal Transverse Mercator coordinate system ~ Projection: Transverse Mercator Datum: North American Datum i Zone 11 N Ellipsoid: Geodetic Reference System Unit:meter N Archaeological data: SRI field data Grid Base data: Cajon and Devore, California 7.S~minute USGS topographic quadrangles Statistical Research, Inc., December Figure 1. Project location Cajon, California, 7.5-minute U.S. Geological Survey quadrangle [photorevised